40-35000-24-08760_40-35000-24-08760 NMBHI Forensic Amendment 02.docx.DOCX
DOCX document 48 KB Posted
- Attached to
- NMBHI FORENSIC FACILITY
- Solicitation number
- 40-35000-24-08760
- Issued by
- San Miguel County, Las Cruces City, New Mexico
About this file
This document is an Amendment #02 to a Request for Proposals (RFP) issued by the New Mexico General Services Department (GSD) Facilities Management Division (FMD) for the NMBHI Forensic Facility project in Las Vegas, New Mexico, RFP #40-35000-24-08760. The amendment modifies several sections of the RFP, including the Sequence of Events table, the Procurement Manager contact information, the Subcontractor Listing Form, and the Project Staffing criteria. Key updates include extending the deadline for written questions to July 17, 2024, the proposal submission deadline to July 31, 2024, and the contract award date to October 25, 2024. The amendment also clarifies that subcontractors whose contract value exceeds 5% of the total project value must complete the Statement of Qualifications form.
The RFP seeks to identify a contractor to provide construction services for the NMBHI Forensic Facility project. The project has an estimated value over $50 million, and the contractor must demonstrate relevant experience with public or private facility projects of similar size and scope. Additional evaluation factors include the contractor's project staffing, past performance, and proposed project approach. Pricing details, funding sources, and other contract terms are not specified in the amendment.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT #02
STATE PURCHASING DIVISION
OF THE
GENERAL SERVICES DEPARTMENT
AND
FACILITIES MANAGEMENT DIVISION (FMD)
REQUEST FOR PROPOSALS (RFP)
NMBHI Forensic Facility Las Vegas, New Mexico
RFP# 40-35000-24-08760
Amendment 02 Issue Date:
July 12, 2024
Proposal Due Date:
July 25, 2024 3:00 p.m. Mountain Time
Request for Proposal # 40-35000-24-08760 Amendment Two
Page-2
This Amendment No. Two (02) serves to modify the following section on the specified pages of the RFP. It also modifies the contract documents as shown in the attached Addendum #02 and #03.
1) Section II. A. Sequence of Events Table- revise the date for #4-12.
FROM:
| Action |
| Responsible Party |
| Due Dates |
| 1. Issue RFP |
| SPD |
| May 30, 2024 |
| 2. Acknowledgement of Receipt Form |
| Potential Offerors |
| June 25, 2024 |
| 3. Mandatory Pre-Proposal Conference |
| Agency |
| June 25, 2024 1:00 PM MDT |
4. Deadline to submit Written Questions
| Potential Offerors |
| July 3, 2024 9:00 AM MDT |
5. Response to Written Questions
| Procurement Manager |
| July 11, 2024 |
| 6. Submission of Proposal |
| Potential Offerors |
| July 18, 2024 3:00PM MDT |
| 7.* Proposal Evaluation |
| Evaluation Committee |
| July 23, 2024 |
| 8.* Selection of Finalists |
| Evaluation Committee |
| July 26, 2024 |
| 9 * Oral Presentation(s) |
| Finalist Offerors |
| August 1, 2024 |
| 10.* Best and Final Offers |
| Finalist Offerors |
| August 5, 2024 |
| 11.* Finalize Contractual Agreements |
| Agency/Finalist Offerors |
| August 16, 2024 |
| 12.* Contract Awards |
| Agency/ Finalist Offerors |
| September 24, 2024 |
| 13.* Protest Deadline |
| SPD |
| +15 days |
TO:
| Action |
| Responsible Party |
| Due Dates |
| 1. Issue RFP |
| SPD |
| May 30, 2024 |
| 2. Acknowledgement of Receipt Form |
| Potential Offerors |
| June 18, 2024 |
| 3. Mandatory Pre-Proposal Conference |
| Agency |
| June 25, 2024 1:00 PM MDT |
4. Deadline to submit Written Questions
| Potential Offerors |
| July 17, 2024 9:00 AM MDT |
5. Response to Written Questions
| Procurement Manager |
| July 23, 2024 |
| 6. Submission of Proposal |
| Potential Offerors |
| July 31, 2024 3:00PM MDT |
| 7.* Proposal Evaluation |
| Evaluation Committee |
| August 6, 2024 |
| 8.* Selection of Finalists |
| Evaluation Committee |
| August 21, 2024 |
| 9 * Oral Presentation(s) |
| Finalist Offerors |
| September 04, 2024 |
| 10.* Best and Final Offers |
| Finalist Offerors |
| September 09, 2024 |
| 11.* Finalize Contractual Agreements |
| Agency/Finalist Offerors |
| September 24, 2024 |
| 12.* Contract Awards |
| Agency/ Finalist Offerors |
| October 25, 2024 |
| 13.* Protest Deadline |
| SPD |
| +15 days |
2.) D. Change in Procurement Manager and contact information of RFP.
FROM:
D. PROCUREMENT MANAGER
The General Services Department (GSD) Facility Management Division (FMD) has assigned a Procurement Manager who is responsible for the conduct of this procurement whose name, address, telephone number and e-mail address are listed below:
| Name: | Peter Barrington, Procurement Manager | |
| Telephone: | (505) 629-8936 | |
| Email: | Peter.Barrington@gsd.nm.gov |
D. PROCUREMENT MANAGER
The General Services Department (GSD) Facilities Management Division (FMD) has assigned a Procurement Manager who is responsible for the conduct of this procurement whose name, address, telephone number and e-mail address are listed below:
Facilities Management Division Attn: Joseph Lovato, Capital Projects Procurement Bureau Chief 2542 Cerrillos Road Santa Fe, NM 87505 Phone: 505-487-3825 E-mail: joseph.lovato@gsd.nm.gov
3) Attachment D-2 Subcontractor Listing Form Correct B. $3,900,000 which represents one/half of one percent of total project to $390,000.
FROM:
APPENDIX D-2
SUBCONTRACR LISTING FORM
REFERENCE: B. $3,900,000 which represents one/half of one percent of the total project (to be estimated by the architect and/or engineer of record).
TO:
Appendix D-2
SUBCONTACTOR LISTING FORM
REFERENCE: B. $390,000 which represents one/half of one percent of the total project (to be estimated by the architect and/or engineer of record).
4) B.2 Project Staffing (See Table 1) (120 Points) correct item Section A. to reflect proper language of value.
FROM:
1. B.2 Project Staffing (See Table 1) (120 Points)
a) Statement of Qualifications submittal (Appendix F & G). Although the Statement of Qualifications deals with topics in other sections, it must be submitted here under Project Staffing. The General Contractor is required to fill out and submit the form Appendix F. Each subcontractor who is subject to the subcontractor listing form where the value of their contract is over half of one percent of the project value shall complete the form Appendix G. Contractor and Subcontractor Statement of Qualifications form Sections 3, 4 & 5 apply to this factor.
TO:
1. B.2 Project Staffing (See Table 1) (120 Points)
b) Statement of Qualifications submittal (Appendix F & G). Although the Statement of Qualifications deals with topics in other sections, it must be submitted here under Project Staffing. The General Contractor is required to fill out and submit the form Appendix F. Each subcontractor who is subject to the subcontractor listing form where the value of their contract is over five percent of the project value shall complete the form Appendix G. Contractor and Subcontractor Statement of Qualifications form Sections 3, 4 & 5 apply to this factor.
5) Attachment A correct dollar threshold in section 2.b. from $75 million to $50 million.
FROM:
Attachment A
REFERENCE: 2.b. Experience in Public or Private Facilities projects over $75 million since 2014
COMPLETE ONE FORM FOR EACH PROJECT LISTED ON THE QUESTIONNAIRE (MAXIMUM 5)
TO:
Attachment A
REFERENCE: 2.b. Experience in Public or Private Facilities projects over $50 million since 2014
COMPLETE ONE FORM FOR EACH PROJECT LISTED ON THE QUESTIONNAIRE (MAXIMUM 5)
6) Attachment E to correct number of years from 3years to 10 years to match evaluation criteria.
FROM:
REFERENCE: 2.a. Projects Completed for Facilities Management Division or other Governmental Bodies (State/City/County) in last 3 years. Federal Projects may also be included
REFERENCE: 2.a. Projects Completed for Facilities Management Division or other Governmental Bodies (State/City/County) in last 10 years. Federal Projects may also be included
Questions and Answers 7/11/2024 Q. Can you clarify if the allowance shall cover costs for Builders risk and the performance and payment bond.
A. Any Allowance in the alternate needs to be marked up in the alternate bid and does not cover Builders risk, performance and payment bonds. Any allowance in the base bid should be marked up as a sub-contractor cost.
Q. Will the general contractor be able to secure funds in the base bid to secure materials for alternate #1 future funding release?
A. The contractor cannot secure funding for materials in the base bid for materials in the alternate. Once a contract is awarded it may be a possibility by change order.
Amendment #2 is on the GSD/SPD website at:
https://www.generalservices.state.nm.us/statepurchasing/active-procurements.aspx
Offerors must acknowledge receipt of this Amendment on the Appendix D-1 Cost Proposal Form.
Please use the following link to access Addendum #2:
https://studiosw.sharefile.com/d-s13491fa2d0704435b246ebef5305fd89
Please use the following link to access Addendum #3:
https://studiosw.sharefile.com/d-s7643751ca0f74c30ada1de4b96eba84e image1.jpeg
File details come from the government source that posted it. Updated .