40 05 53 - Identification for Process Piping.doc

DOC document 36 KB Posted

Attached to
Clarifier Rehab Waste Water Plant
Solicitation number
092025-01
Issued by
Clay County, Tennessee

About this file

This document is a technical specification section (40 05 53) for identification of process piping for Newport Utilities' Waste Water Treatment Plant (WWTP) Clarifier Upgrades project located in Tennessee. The specification provides detailed requirements for stenciling and marking process piping, including guidelines for letter sizes based on pipe diameter (ranging from 1/2-inch to 1-3/4-inch high letters), pipe identification methods, and installation protocols. The project involves labeling piping systems with service names and flow direction, with identification markers to be placed at intervals not exceeding 20 feet on straight runs, near valves, penetrations, and obstructions.

The specification indicates that the work is part of a lump sum contract and will not be separately measured for payment. The documentation references ASME International standard ASME A13.1 for piping system identification, requiring compliance with specific color schemes and lettering standards. Materials must be stored in clean, dry locations and protected from moisture and dust. The project is being managed by WK Dickson (Project No. 20240712PR.WK) and is scheduled for bidding in March 2025, with the specific scope involving rehabilitation of two clarifiers at the Newport Utilities Waste Water Plant in Tennessee.

View the file

Other files

File Type Posted
Clarifier Instructions to Bidder.pdf PDF
Newport_Utilities_RFP_Clarifier_Rehab_Contact.pdf PDF
Clarifier Bid_Form.docx DOCX document
PR-WWTP CLARIFIER UPGRADES.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 40 05 53

IDENTIFICATION FOR PROCESS PIPING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Stencils.

2. Pipe markers.

B. Related Sections:

1. Documents affecting Work of this section include, but are not necessarily limited to, General Conditions, Supplementary Conditions, and Sections in Division 01 of these Specifications.

1.2 measurment and payment

A. General: Work of this section will not be measured for payment but is included in the lump sum cost of Work.

1.3 REFERENCE STANDARDS

A. ASME International: ASME A13.1 - Scheme for the Identification of Piping Systems.

B. Section 01 33 00 - Submittal Procedures: Requirements for submittals.

C. Shop Drawings:

1. Indicate list of wording, symbols, letter size, and color-coding for mechanical identification and valve chart and schedule.

1.4 CLOSEOUT SUBMITTALS

A. Section 01 70 00 - Execution and Close-out Requirements for submittals.

1.5 QUALITY ASSURANCE.

A. Label Color Scheme and Lettering Size: Comply with ANSI/ASME A13.1.

1.6 DELIVERY, STORAGE, AND HANDLING

A. Inspection: Accept materials on site in manufacturer’s original packaging and inspect for damage.

B. Store materials according to manufacturer instructions.

C. Protection:

1. Protect materials from moisture and dust by storing in clean, dry location remote from construction operations areas.

2. Provide additional protection according to manufacturer instructions.

PART 2 - PRODUCTS

2.1 STENCILS

A. Description:

1. Quality: Clean-cut symbols.

2. Letters:

a. Up to 2-Inch OD of Insulation or Pipe: 1/2-inch high letters.

b. 2-1/2- to 6-Inch OD of Insulation or Pipe: 1-inch high letters.

c. More Than 6-Inch OD of Insulation or Pipe: 1-3/4-inch high letters.

B. Stencil Paint:

1. Description: Semigloss enamel.

2. [and bar code].

PART 3 - EXECUTION

3.1 PREPARATION

A. Section 01 70 00 - Execution and Close-out Requirements for installation preparation.

3.2 INSTALLATION

A. According to manufacturer instructions.

B. Piping:

1. Identify piping, concealed or exposed, with stenciled painting.

2. Identify service, flow direction.

a. Service: Use full-service name.

3. Install in clear view and align with axis of piping.

4. Locate identification not to exceed 20 feet on straight runs, including risers and drops, adjacent to each valve and tee, at each side of penetration of structure or enclosure, and at each obstruction.

END OF SECTION

Newport Utilities Identification for Process Piping PR. WWTP Clarifier Upgrades 40 05 53 - 10 WK Dickson Project No.: 20240712PR.WK

March/2025 Issued for Bidding