QuickStartGuide
| C-100 (2026) |
| Updated June 2025 |
| Quick Start Guide |
| GENERAL INFORMATION |
| 1) The intended use of the C-100 (2026) is to enable project managers to communicate their project cost estimates to budget officers in the standard format required for capital project budget requests/submittals to OFM. |
2) This workbook is protected so that the worksheets within it cannot be moved or deleted in the usual manner. This protection is necessary to ensure that the cost estimate details and formulas align with the estimating application in the Capital Budgeting System.
| 3) The estimating format to develop the maximum allowable construction cost (MACC) is presented in Uniformat II. |
| 4) Form-calculated costs such as A/E Basic Design Service fees and Agency Project Management costs are dependent on other estimated project costs such as MACC, equipment, etc. |
5) Project estimates generated with this tool are not sufficient for budget request submittals to OFM. Use the Capital Budgeting System to submit capital project budget requests and attach the C-100 form.
| 6) Contact your assigned OFM Capital Budget Analyst with questions. |
| OFM Capital Budget Analyst |
| INSTRUCTIONS |
| 1) Only green cells are available for data entry. |
| 2) Fill in all known cells in the 'Summary' tab prior to moving on to the cost entry tabs A-G. |
| 3) It is recommended, but not required, to fill out cost entry tabs in the following order: |
| A. Acquisition, C. Construction Contracts, D. Equipment, G. Other Costs, B. Consultant Services, F. Project Management, then E. Artwork. |
4) If additional rows are inserted to capture additional project costs, a description must be provided in the Notes column or within Tab H. Additional Notes. Be particularly detailed for additional costs estimated for contingencies and project management.
| FORM-CALCULATED COSTS (FEE CALCULATIONS) |
| 1) A/E Basic Design Services: AE Fee % (x) (MACC or TCC + Contingency) |
| 2) Design Services Contingency: Contingency % (x) Consultant Services Subtotal |
| 3) Construction Contingency: Contingency % (x) MACC or TCC |
| 4) Artwork: 0.5% (x) Total Project Cost |
| 5) Agency Project Management (Greater than $1 million): (AE Fee % - 3%) (x) (Acquisition Total + Consultant Services Total + MACC + Construction Contingency + Other Costs) |
http://ofm.wa.gov/budget/contacts/default.asp Summary
| STATE OF WASHINGTON | |
| AGENCY / INSTITUTION PROJECT COST SUMMARY | |
| Updated June 2025 | |
| Agency | Washington State Criminal Justice Training Commission |
| Project Name | New Burien Firing Range |
| OFM Project Number | 2023-500 |
| Contact Information | | | |
| Name | Todd Dana | | |
| Phone Number | 206-835-7317 | | |
| Email | todd.dana@cjtc.wa.gov | | |
| Statistics | | | |
| Gross Square Feet | 55,000 | MACC per Gross Square Foot | $805 |
| Usable Square Feet | 38,000 | Escalated MACC per Gross Square Foot | $895 |
| Alt Gross Unit of Measure | | | |
| Space Efficiency | 69.1% | A/E Fee Class | B |
| Construction Type | Vocational schools | A/E Fee Percentage | 6.78% |
| Remodel | No | Projected Life of Asset (Years) | |
| Additional Project Details | | | |
| Procurement Approach | DBB | Art Requirement Applies | Yes |
| Inflation Rate | 3.16% | Higher Ed Institution | No |
| Sales Tax Rate % | 10.20% | Location Used for Tax Rate | Burien, WA |
| Contingency Rate | 5% | | |
| Base Month (Estimate Date) | September-25 | OFM UFI# (from FPMT, if available) | |
| Project Administered By | DES | | |
| Schedule | | | |
| Predesign Start | July-26 | Predesign End | February-27 |
| Design Start | March-27 | Design End | March-28 |
| Construction Start | June-28 | Construction End | December-29 |
| Construction Duration | 18 Months | | |
| Green cells must be filled in by user | | | |
| Project Cost Summary | | | |
| Total Project | $64,683,368 | Total Project Escalated | $71,595,366 |
| | Rounded Escalated Total | $71,595,000 |
| Amount funded in Prior Biennia | $500,000 |
| Amount in current Biennium | $7,279,000 |
| Next Biennium | $63,817,000 |
| Out Years | $0 |
| Acquisition | | | |
| Acquisition Subtotal | $0 | Acquisition Subtotal Escalated | $0 |
| Consultant Services | | | |
| Predesign Services | $350,000 | | |
| Design Phase Services | $2,175,794 | | |
| Extra Services | $2,040,000 | | |
| Other Services | $1,182,531 | | |
| Design Services Contingency | $808,202 | | |
| Consultant Services Subtotal | $6,556,527 | Consultant Services Subtotal Escalated | $7,069,193 |
| Construction | | | |
| Maximum Allowable Construction Cost (MACC) | $44,294,490 | Maximum Allowable Construction Cost (MACC) Escalated | $49,248,268 |
| DBB Risk Contingencies | $0 | | |
| DBB Management | $0 | | |
| Owner Construction Contingency | $2,214,724 | | $2,467,425 |
| Non-Taxable Items | $0 | | $0 |
| Sales Tax | $4,743,940 | Sales Tax Escalated | $5,275,001 |
| Construction Subtotal | $51,253,154 | Construction Subtotal Escalated | $56,990,694 |
| Equipment | | | |
| Equipment | $3,100,614 | | |
| Sales Tax | $316,263 | | |
| Non-Taxable Items | $0 | | |
| Equipment Subtotal | $3,416,877 | Equipment Subtotal Escalated | $3,806,744 |
| Artwork | | | |
| Artwork Subtotal | $356,196 | Artwork Subtotal Escalated | $356,196 |
| Agency Project Administration | | | |
| Agency Project Administration Subtotal | $0 | | |
| DES Additional Services Subtotal | $0 | | |
| Other Project Admin Costs | $0 | | |
| Project Administration Subtotal | $0 | Project Administration Subtotal Escalated | $0 |
| Other Costs | | | |
| Other Costs Subtotal | $3,100,614 | Other Costs Subtotal Escalated | $3,372,539 |
| Project Cost Estimate | | | |
| Total Project | $64,683,368 | Total Project Escalated | $71,595,366 |
| | Rounded Escalated Total | $71,595,000 |
https://webgis.dor.wa.gov/taxratelookup/SalesTax.aspx Biennium Summary Funding Summary
| | | Current Biennium | | |
| Project Cost (Escalated) | Funded in Prior Biennia | 2025-2027 | 2027-2029 | Out Years |
| Acquisition | | | | | |
| Acquisition Subtotal | $0 | | | | $0 |
| Consultant Services | | | | | |
| Consultant Services Subtotal | $7,069,193 | $500,000 | $6,604,219 | -$35,026 | $0 |
| Construction | | | | |
| Construction Subtotal | $56,990,694 | $0 | $56,990,694 | $0 |
| Equipment | | | | |
| Equipment Subtotal | $3,806,744 | $0 | $3,806,744 | $0 |
| Artwork | | | | |
| Artwork Subtotal | $356,196 | $0 | $356,196 | $0 |
| Agency Project Administration | | | | |
| Project Administration Subtotal | $0 | $0 | $0 | $0 |
| Other Costs | | | | |
| Other Costs Subtotal | $3,372,539 | $674,508 | $2,698,031 | $0 |
| Project Cost Estimate | | | | | |
| Total Project | $71,595,366 | $500,000 | $7,278,727 | $63,816,639 | $0 |
| $71,595,000 | $500,000 | $7,279,000 | $63,817,000 | $0 |
Percentage requested as a new appropriation 10%
| What is planned for the requested new appropriation? (Ex. Acquisition and design, phase 1 construction, etc.) |
| Commence design phase in March 26 |
| Insert Row Here |
| What has been completed or is underway with a previous appropriation? |
| Previous predesign that focused on master plan of Burien |
| Insert Row Here |
| What is planned with a future appropriation? |
| Complete construction / closeout / move in (FY 29-30) |
Insert Row Here
Basis of Estimate
| C-100(2021) |
| Basis of Estimate |
| Scope of work: Brief description of project |
| Function, size, number of storys, character, quality |
| Insert Row Here |
| Site Conditions: Brief summary of key site factors influencing cost |
| Site constraints, congestion, site access, topography, ground conditions |
| Insert Row Here |
| Construction Conditions: Brief summary of key construction operations influencing cost |
| Working hours, noise/dust, other users, ease of access |
Insert Row Here
| Market Conditions: Brief summary of key bidding factors influencing cost |
| Availability of labor, market hunger, market readiness |
Insert Row Here
| Major Risks |
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
| 6 |
| 7 |
| 8 |
| 9 |
| 10 |
| Insert Row Here |
| Exclusions: Major cost items excluded from the project |
Insert Row Here
Other Comments
Insert Row Here
A. Acquisition Cost Estimate Details
| Acquisition Costs | | | | |
| Item | Base Amount | Escalation Factor | Escalated Cost | Notes |
| Purchase/Lease | | | | |
| Appraisal and Closing | | | | |
| Right of Way | | | | |
| Demolition | | | | |
| Pre-Site Development | | | | |
| Other | | | | |
| Insert Row Here | | | | |
| ACQUISITION TOTAL | $0 | NA | $0 | |
Green cells must be filled in by user
B. Consultant Services Cost Estimate Details
| Consultant Services | | | | |
| Item | Base Amount | Escalation Factor | Escalated Cost | Notes |
| 1) Pre-Schematic Design Services | | | | |
| Programming/Site Analysis | $0 | | | |
| Environmental Analysis | $0 | | | |
| Predesign Study | $0 | | | |
| DB Preconstruction Services | | | | |
| PreDesign - Supplement Study | $350,000 | | | |
| Insert Row Here | | | | |
| Sub TOTAL | $350,000 | 1.0473 | $366,555 | Escalated to Design Start |
| 2) Construction Documents | | | | |
| A/E Basic Design Services | $2,175,794 | | | 69% of A/E Basic Services |
| Other | | | | |
| Insert Row Here | | | | |
| Sub TOTAL | $2,175,794 | 1.0638 | $2,314,610 | Escalated to Mid-Design |
| 3) Extra Services | | |
| Civil Design (Above Basic Svcs) | $150,000 | |
| Geotechnical Investigation | $50,000 | |
| Commissioning | $200,000 | Enhanced CA |
| Site Survey | $50,000 | |
| Testing | $130,000 | |
| LEED Services | $300,000 | |
| Voice/Data Consultant | $50,000 | |
| Value Engineering | $125,000 | |
| Constructability Review | $125,000 | |
| Environmental Mitigation (EIS) | $0 | |
| Landscape Consultant | $100,000 | |
| A/E Time Participate in Commissioning | $60,000 | |
| Acoustical Consultant | $50,000 | |
| Art Coordination | $25,000 | |
| Bid Package Coordination | $0 | |
| Building Analysis and Modeling | $75,000 | |
| Conformed Document Set | $0 | |
| Document Reproduction | $0 | |
| Energy Conservation Report (ELCCA) | $80,000 | |
| Energy Modeling for Code | $40,000 | |
| Envelope Consultant | $75,000 | |
| Existing Building Seismic Design | $0 | |
| FF&E Consulting | $30,000 | |
| Fire / Life Safety Consultant | $0 | |
| Graphics / Signage Consultant | $10,000 | |
| Hardware Consultant | $15,000 | |
| Interior Design Consultant | $0 | |
| Kitchen Consultant | $0 | |
| LEED Documentation | $0 | |
| Life Cycle Cost Assessment Tool | $0 | |
| Lighting Consultant | $25,000 | |
| Models / Graphics / Animations | $30,000 | |
| NPDES Design Services | $50,000 | |
| Photo Voltaic Design | $20,000 | |
| Estimate Reviews by 3rd Party | $50,000 | |
| Security / Access Consultant | $25,000 | |
| SEPA Services | $50,000 | |
| Site Electrical and Data | $20,000 | |
| Storm Water Report | $0 | |
| Traffic Consultant | $30,000 | |
| Auditor | $0 | |
| Hazmat Consultant | $0 | |
| Insert Row Here | | | | |
| Sub TOTAL | $2,040,000 | 1.0638 | $2,170,152 | Escalated to Mid-Design |
| 4) Other Services | | |
| Bid/Construction/Closeout | $977,531 | 31% of A/E Basic Services |
| HVAC Balancing | $75,000 | |
| Staffing | | |
| Record Drawings | $50,000 | |
| Reimbursables | $80,000 | |
| User Training | Included above | |
| Insert Row Here | | | | |
| Sub TOTAL | $1,182,531 | 1.1141 | $1,317,458 | Escalated to Mid-Const. |
| 5) Design Services Contingency | | | | |
| Design Services Contingency | $287,416 | | | |
| DB Contractor OH&P on DB Design Fees (6%) | $0 | | | Does not include owner consultants |
| Sales Tax on DB Design Fees | $520,786 | | | |
| Insert Row Here | | | | |
| Sub TOTAL | $808,202 | 1.1141 | $900,418 | Escalated to Mid-Const. |
CONSULTANT SERVICES TOTAL $6,556,527 $7,069,193
Green cells must be filled in by user
C. Construction Contracts Cost Estimate Details
| Construction Contracts | | | | |
| Item | Base Amount | Escalation Factor | Escalated Cost | Notes |
| 1) Site Work | | | | |
| G10 - Site Preparation | $863,100 | | | |
| G20 - Site Improvements | $1,006,800 | | | |
| G30 - Site Mechanical Utilities | $389,550 | | | |
| G40 - Site Electrical Utilities | $487,550 | | | |
| G60 - Other Site Construction | $0 | | | |
| PD Design Contingency | $549,400 | | | |
| Other | $0 | | | |
| Insert Row Here | | | | |
| Sub TOTAL | $3,296,400 | 1.0877 | $3,585,495 | |
| 2) Related Project Costs | | | |
| Offsite Improvements | $500,000 | | |
| City Utilities Relocation | | | |
| Parking Mitigation | | | |
| Stormwater Retention/Detention | | | |
| Other | | | |
| Insert Row Here | | | |
| Sub TOTAL | $500,000 | 1.0877 | $543,850 |
| 3) Facility Construction | | | |
| A10 - Foundations | $1,548,250 | | |
| A20 - Basement Construction | $0 | | |
| B10 - Superstructure | $3,638,250 | | |
| B20 - Exterior Closure | $2,054,551 | | |
| B30 - Roofing | $1,730,827 | | |
| C10 - Interior Construction | $1,321,205 | | |
| C20 - Stairs | $0 | | |
| C30 - Interior Finishes | $1,375,823 | | |
| D10 - Conveying | $0 | | |
| D20 - Plumbing Systems | $417,395 | | |
| D30 - HVAC Systems | $6,583,170 | | |
| D40 - Fire Protection Systems | $330,000 | | |
| D50 - Electrical Systems | $3,558,500 | | |
| F10 - Special Construction | $0 | | |
| F20 - Selective Demolition | $0 | | |
| General Conditions | $3,981,020 | | |
| E10 - Equipment (CFCI) | $6,654,278 | | |
| E20 - Fixed Furnishings (CFCI) | $110,142 | | |
| PD Design Contingency | $1,706,590 | | |
| Cont/Bonds/Ins/Risk/B&O/OH&P | $5,488,089 | | |
| Insert Row Here | | | |
| Sub TOTAL | $40,498,090 | 1.1141 | $45,118,923 |
| 4) Maximum Allowable Construction Cost | | | |
| MACC Sub TOTAL | $44,294,490 | $49,248,268 | |
| $805 | $895 | per GSF |
| $0 |
| This Section is Intentionally Left Blank | |
$0
| 6) Total Cost of Construction (TCC) | | | |
| TCC Sub TOTAL | $44,294,490 | $49,248,268 | |
| $805 | $895 | per 0 |
| 7) Owner Construction Contingency | | | | |
| Allowance for Change Orders | $2,214,724 | | | |
| Long Range Planning - Construction Market Volatility | $0 | | | Transfer to MACC if needed |
| Insert Row Here | | | | |
| Sub TOTAL | $2,214,724 | 1.1141 | $2,467,425 | |
| 8) Non-Taxable Items | | | |
| Other | | | |
| Insert Row Here | | | |
| Sub TOTAL | $0 | 1.1141 | $0 |
| 9) Sales Tax | | |
| Sub TOTAL | $4,743,940 | $5,275,001 |
CONSTRUCTION CONTRACTS TOTAL $51,253,154 $56,990,694
Green cells must be filled in by user
D. Equipment Cost Estimate Details
| Equipment | | | | |
| Item | Base Amount | Escalation Factor | Escalated Cost | Notes |
| 1) Equipment | | | | |
| E10 - Equipment | $1,550,307 | | | |
| E20 - Furnishings | $1,550,307 | | | |
| F10 - Special Construction | | | | |
| Other | | | | |
| Insert Row Here | | | | |
| Sub TOTAL | $3,100,614 | 1.1141 | $3,454,395 | |
| 2) Non Taxable Items | | | |
| Other | | | |
| Insert Row Here | | | |
| Sub TOTAL | $0 | 1.1141 | $0 |
| 3) Sales Tax | | |
| Sub TOTAL | $316,263 | $352,349 |
EQUIPMENT TOTAL $3,416,877 $3,806,744
Green cells must be filled in by user
E. Artwork Cost Estimate Details
| Artwork | | | | |
| Item | Base Amount | Escalation Factor | Escalated Cost | Notes |
| 1) Artwork | | | | |
| Project Artwork | $356,196 | | | 0.5% of total project cost for new construction |
| Higher Ed Artwork | $0 | | | 0.5% of total project cost for new and renewal construction |
| Other | | | | |
| Insert Row Here | | | | |
| ARTWORK TOTAL | $356,196 | NA | $356,196 | |
Green cells must be filled in by user
F. Project Management Cost Estimate Details
| Project Management | | | | |
| Item | Base Amount | Escalation Factor | Escalated Cost | Notes |
| 1) Agency Project Management | | | | |
| Agency Project Management | $0 | | | |
| Additional Services | | | | |
| Additional DB Contract Admin. Costs (RFQ preparation) | $0 | | | |
| Insert Row Here | | | | |
| Subtotal of Other | $0 | | | |
| PROJECT MANAGEMENT TOTAL | $0 | 1.1141 | $0 | |
Green cells must be filled in by user
G. Other Costs Cost Estimate Details
| Other Costs | | | | |
| Item | Base Amount | Escalation Factor | Escalated Cost | Notes |
| Mitigation Costs | | | | |
| Hazardous Material Remediation/Removal | $0 | | | |
| Historic and Archeological Mitigation | $0 | | | |
| Permits | $442,945 | | | |
| Builder's Risk Insurance | $0 | | | |
| Municipal Utility Fees | $442,945 | | | |
| Management Reserve | $2,214,724 | | | |
| Insert Row Here | | | | |
| OTHER COSTS TOTAL | $3,100,614 | 1.0877 | $3,372,539 | |
Green cells must be filled in by user
H. Additional Notes
| C-100 (2026) |
| Additional Notes |
Tab A. Acquisition
| Insert Row Here |
| Tab B. Consultant Services |
| Insert Row Here |
| Tab C. Construction Contracts |
Insert Row Here
Tab D. Equipment
Insert Row Here
Tab E. Artwork
| Insert Row Here |
| Tab F. Project Management |
Insert Row Here
Tab G. Other Costs
Insert Row Here
Audit
| Named Ranges | | | |
| Range Name | Location | Value |
| ACQ_TOTAL | ='A. Acquisition'!$C$12 | 0.00 |
| ACQ_TOTAL_ESC | ='A. Acquisition'!$F$12 | 0.00 |
| TotalMinusPM | =ACQ_TOTAL+CONSUL_TOTAL+MACC+CONT+OTHER_TOTAL | |
| PREDESIGN_TOTAL | ='B. Consultant Services'!$C$11 | 350000.00 |
| CONST_DOCS | ='B. Consultant Services'!$C$20 | 2175794.07 |
| OTHER_SVCS_TOTAL | ='B. Consultant Services'!$C$29 | 1182530.67 |
| EX_SVCS_TOTAL | ='B. Consultant Services'!$C$52 | 2040000.00 |
| DES_CONT_TOTAL | ='B. Consultant Services'!$C$58 | 808201.82 |
| CONSUL_TOTAL | ='B. Consultant Services'!$C$60 | 6556526.56 |
| PREDESIGN_TOTAL_ESC | ='B. Consultant Services'!$F$11 | 366555.00 |
| CONST_DOCS_ESC | ='B. Consultant Services'!$F$20 | 2314610.00 |
| OTHER_SVCS_TOTAL_ESC | ='B. Consultant Services'!$F$29 | 1317458.00 |
| EX_SVCS_TOTAL_ESC | ='B. Consultant Services'!$F$52 | 2170152.00 |
| DES_CONT_TOTAL_ESC | ='B. Consultant Services'!$F$58 | 900418.00 |
| CONSUL_TOTAL_ESC | ='B. Consultant Services'!$F$60 | 7069193.00 |
| SITE_TOTAL | ='C. Construction Contracts'!$C$13 | 3296400.00 |
| RELATED_COSTS_TOTAL | ='C. Construction Contracts'!$C$22 | 500000.00 |
| FACILITY_TOTAL | ='C. Construction Contracts'!$C$42 | 40498089.95 |
| MACC | ='C. Construction Contracts'!$C$55 | 44294489.95 |
| GCCM_RISK | ='C. Construction Contracts'!$C$64 | 0.00 |
| GCCM_DB_TOTAL | ='C. Construction Contracts'!$C$72 | 0.00 |
| CONT | ='C. Construction Contracts'!$C$86 | 2214724.50 |
| SALES_TAX | ='C. Construction Contracts'!$C$94 | 4743939.87 |
| CONST_TOTAL | ='C. Construction Contracts'!$C$96 | 51253154.32 |
| SITE_TOTAL_ESC | ='C. Construction Contracts'!$F$13 | 3585495.00 |
| RELATED_COSTS_TOTAL_ESC | ='C. Construction Contracts'!$F$22 | 543850.00 |
| FACILITY_TOTAL_ESC | ='C. Construction Contracts'!$F$42 | 45118923.00 |
| MACC_ESC | ='C. Construction Contracts'!$F$55 | 49248268.00 |
| GCCM_RISK_ESC | ='C. Construction Contracts'!$F$64 | |
| GCCM_DB_TOTAL_ESC | ='C. Construction Contracts'!$F$72 | |
| CONT_ESC | ='C. Construction Contracts'!$F$86 | 2467425.00 |
| SALES_TAX_ESC | ='C. Construction Contracts'!$F$94 | 5275000.69 |
| CONST_TOTAL_ESC | ='C. Construction Contracts'!$F$96 | 56990693.69 |
| EQUIP_SUBTOTAL | ='D. Equipment'!$C$10 | 3100614.30 |
| EQUIP_NON_TAX | ='D. Equipment'!$C$15 | 0.00 |
| EQUIP_SALES_TAX | ='D. Equipment'!$C$18 | 316262.66 |
| EQUIP_TOTAL | ='D. Equipment'!$C$20 | 3416876.95 |
| EQUIP_SUBTOTAL_ESC | ='D. Equipment'!$F$10 | 3454395.00 |
| EQUIP_NON_TAX_ESC | ='D. Equipment'!$F$15 | 0.00 |
| EQUIP_SALES_TAX_ESC | ='D. Equipment'!$F$18 | 352349.00 |
| EQUIP_TOTAL_ESC | ='D. Equipment'!$F$20 | 3806744.00 |
| MPD | ='Data Tables'!$H$2 | 9/14/27 |
| MPC | ='Data Tables'!$I$2 | 3/9/29 |
| PMD | ='Data Tables'!$N$1 | 3.00% |
| ART | ='Data Tables'!$N$2 | 0.50% |
| Infl | ='Data Tables'!$N$3 | 3.16% |
| ContN | ='Data Tables'!$N$4 | 5.00% |
| ContR | ='Data Tables'!$N$5 | 10.00% |
| Rem_Ad | ='Data Tables'!$N$6 | 3.00% |
| PMMinor | ='Data Tables'!$N$7 | 4.00% |
| ART_TOTAL | ='E. Artwork'!$C$9 | 356195.85 |
| ART_TOTAL_ESC | ='E. Artwork'!$F$9 | 356195.85 |
| PM_TOTAL | ='F. Project Management'!$C$10 | 0.00 |
| AGENCY_PM | ='F. Project Management'!$C$5 | 0.00 |
| DES_ADD_SVCS | ='F. Project Management'!$C$6 | 0.00 |
| PM_OTHER | ='F. Project Management'!$C$8 | 0.00 |
| PM_TOTAL_ESC | ='F. Project Management'!$F$10 | 0.00 |
| OTHER_TOTAL | ='G. Other Costs'!$C$10 | 3100614.30 |
| OTHER_TOTAL_ESC | ='G. Other Costs'!$F$10 | 3372539.00 |
| ESC_MidC | =ROUND((1+Infl)^((MPC-Base_Month)/365), 4) | ERROR:#REF! |
| ESC_MidD | =ROUND((1+Infl)^((MPD-Base_Month)/365), 4) | ERROR:#REF! |
| ESC_StartC | =ROUND((1+Infl)^((StartC-Base_Month)/365), 4) | ERROR:#REF! |
| ESC_StartD | =ROUND((1+Infl)^((StartD-Base_Month)/365), 4) | ERROR:#REF! |
| GSF | =Summary!$C$14 | 55000.00 |
| USF | =Summary!$C$15 | 38000.00 |
| APW | =Summary!$C$21 | No |
| STR | =Summary!$C$23 | 0.10 |
| CONT_RATE | =Summary!$C$24 | 0.05 |
| Base_Month | =Summary!$C$25 | 9/18/25 |
| StartPD | =Summary!$C$29 | 7/15/26 |
| StartD | =Summary!$C$30 | 3/15/27 |
| StartC | =Summary!$C$31 | 6/1/28 |
| Agency | =Summary!$C$4 | Washington State Criminal Justice Training Commission |
| Project_Name | =Summary!$C$5 | New Burien Firing Range |
| AEFP | =Summary!$F$18 | 0.07 |
| Art_Req | =Summary!$F$21 | Yes |
| HEI | =Summary!$F$22 | No |
| ENDPD | =Summary!$F$29 | 2/15/27 |
| EndD | =Summary!$F$30 | 3/15/28 |
| EndC | =Summary!$F$31 | 12/15/29 |
Data Extract
| Data Extract | | | | C:\Users\jeffg179\AppData\Local\Microsoft\Windows\INetCache\Content.Outlook\6YCCK7TU\[WSCJTC C100 Updated Form SWL TD Range 2025-11-17 R2.xlsx]Summary |
| Field | Value | Data_type | |
| Filename | C:\Users\jeffg179\AppData\Local\Microsoft\Windows\INetCache\Content.Outlook\6YCCK7TU\[WSCJTC C100 Updated Form SWL TD Range 2025-11-17 R2.xlsx]Summary | text | |
| Agency | Washington State Criminal Justice Training Commission | Text | |
| Project Name | New Burien Firing Range | text | |
| OFM Project Number | 2023-500 | Text | |
| Gross Square Feet | 0 | number | |
| Usable Square Feet | 0 | number | |
| Alt Gross | Todd Dana | number | |
| Alt Gross Unit of Measure | 0 | Text | |
| Construction Type | Convention facilities | Text | |
| Remodel | No | Text | |
| A/E Fee Class | B | Text | |
| A/E Fee Percentage | 6.78% | percentage | |
| Projected Life of Asset (Years) | 0 | number | |
| Procurement Approach | DBB | Text | |
| Inflation Rate | 3.16% | percentage | |
| Sales Tax Rate pct | 10.20% | percentage | |
| Location Used for Tax Rate | Burien, WA | Text | |
| Contingency Rate | 5.00% | percentage | |
| Art Requirement Applies | Yes | percentage | |
| Higher Ed Institution | No | percentage | |
| Base Month (Estimate Date) | 9/18/25 | date | |
| Project Administered By | DES | Text | |
| Predesign Start | 9/18/25 | date | |
| Predesign End | 9/18/25 | date | |
| Design Start | 9/18/25 | date | |
| Design End | 9/18/25 | date | |
| Construction Start | 9/18/25 | date | |
| Construction End | 9/18/25 | date | |
| Acquisition Subtotal | $0.00 | currency | |
| Acquisition Subtotal Esc | $0.00 | currency | |
| Purchase/Lease | $0.00 | currency | |
| Appraisal and Closing | $0.00 | currency | |
| Right of Way | $0.00 | currency | |
| Demolition | $0.00 | currency | |
| Pre-Site Development | $0.00 | currency | |
| Acquisition Other | $0.00 | currency | |
| Predesign Services | $350,000.00 | currency | |
| Predesign Services Esc | $366,555.00 | currency | |
| Programming/Site Analysis | $0.00 | currency | |
| Environmental Analysis | $0.00 | currency | |
| Predesign Study | $0.00 | currency | |
| Predesign Other | $350,000.00 | currency | |
| Design Phase Services | $2,175,794.07 | currency | |
| Design Phase Services Esc | $2,314,610.00 | currency | |
| A/E Basic Design Services | $2,175,794.07 | currency | |
| A/E Basic Design Services Other | $0.00 | currency | |
| Extra Services | $2,040,000.00 | currency | |
| Extra Services Esc | $2,170,152.00 | currency | |
| Civil Design (Above Basic Svcs) | $150,000.00 | currency | |
| Geotechnical Investigation | $50,000.00 | currency | |
| Commissioning | $200,000.00 | currency | |
| Site Survey | $50,000.00 | currency | |
| Testing | $130,000.00 | currency | |
| LEED Services | $300,000.00 | currency | |
| Voice/Data Consultant | $50,000.00 | currency | |
| Value Engineering | $125,000.00 | currency | |
| Constructability Review | $125,000.00 | currency | |
| Environmental Mitigation (EIS) | $0.00 | currency | |
| Landscape Consultant | $100,000.00 | currency | |
| Extra Services Other | $760,000.00 | currency | |
| Other Services | $1,182,530.67 | currency | |
| Other Services Esc | $1,317,458.00 | currency | |
| Bid/Construction/Closeout | $977,530.67 | currency | |
| HVAC Balancing | $75,000.00 | currency | |
| Staffing | $0.00 | currency | |
| Other Services Other | $130,000.00 | currency | |
| Design Services Contingency | $808,201.82 | currency | |
| Design Services Contingency Esc | $900,418.00 | currency | |
| Design Services Contingency Det | $287,416.24 | currency | |
| Design Services Contingency Other | $520,785.58 | currency | |
| Consultant Services Subtotal | $6,556,526.56 | currency | |
| Consultant Services Subtotal Esc | $7,069,193.00 | currency | |
| Site Work | $3,296,400.00 | currency | |
| Site Work Esc | $3,585,495.00 | currency | |
| G10 - Site Preparation | $863,100.00 | currency | |
| G20 - Site Improvements | $1,006,800.00 | currency | |
| G30 - Site Mechanical Utilities | $389,550.00 | currency | |
| G40 - Site Electrical Utilities | $487,550.00 | currency | |
| G60 - Other Site Construction | $0.00 | currency | |
| Site work Other | $549,400.00 | currency | |
| Related Project Costs | $500,000.00 | currency | |
| Related Project Costs Esc | $543,850.00 | currency | |
| Offsite Improvements | $500,000.00 | currency | |
| City Utilities Relocation | $0.00 | currency | |
| Parking Mitigation | $0.00 | currency | |
| Stormwater Retention/Detention | $0.00 | currency | |
| Related Project Costs Other | $0.00 | currency | |
| Facility Construction | $40,498,089.95 | currency | |
| Facility Construction Esc | $45,118,923.00 | currency | |
| A10 - Foundations | $1,548,250.00 | currency | |
| A20 - Basement Construction | $0.00 | currency | |
| B10 - Superstructure | $3,638,250.00 | currency | |
| B20 - Exterior Closure | $2,054,551.00 | currency | |
| B30 - Roofing | $1,730,827.00 | currency | |
| C10 - Interior Construction | $1,321,205.00 | currency | |
| C20 - Stairs | $0.00 | currency | |
| C30 - Interior Finishes | $1,375,823.00 | currency | |
| D10 - Conveying | $0.00 | currency | |
| D20 - Plumbing Systems | $417,395.00 | currency | |
| D30 - HVAC Systems | $6,583,170.00 | currency | |
| D40 - Fire Protection Systems | $330,000.00 | currency | |
| D50 - Electrical Systems | $3,558,500.00 | currency | |
| F10 - Special Construction | $0.00 | currency | |
| F20 - Selective Demolition | $0.00 | currency | |
| General Conditions | $3,981,020.00 | currency | |
| Facility Construction Other | $13,959,098.95 | currency | |
| MACC | $44,294,489.95 | currency | |
| MACC Esc | $49,248,268.00 | currency | |
| GCCM Risk Contingency | $0.00 | currency | |
| GCCM Risk Contingency Esc | | currency | |
| GCCM Risk Contingency Det | $0.00 | currency | |
| GCCM Risk Contingency Other | $0.00 | currency | |
| GCCM or Design Build Costs | $0.00 | currency | |
| GCCM or Design Build Costs Esc | | currency | |
| GCCM Fee | $0.00 | currency | |
| Bid General Conditions | $0.00 | currency | |
| GCCM Preconstruction Services | $0.00 | currency | |
| GCCM Fee Other | $0.00 | currency | |
| Owner Construction Contingency | $2,214,724.50 | currency | |
| Owner Construction Contingency Esc | $2,467,425.00 | currency | |
| Allowance for Change Orders | $2,214,724.50 | currency | |
| Owner Construction Contingency Other | $0.00 | currency | |
| Const Non-Taxable Items | $0.00 | currency | |
| Const Non-Taxable Items Esc | $0.00 | currency | |
| Sales Tax | $4,743,939.87 | currency | |
| Sales Tax Esc | $5,275,000.69 | currency | |
| CONSTRUCTION CONTRACTS TOTAL | $51,253,154.32 | currency | |
| CONSTRUCTION CONTRACTS TOTAL Esc | $56,990,693.69 | currency | |
| Equipment | $3,100,614.30 | currency | |
| Equipment Esc | $3,454,395.00 | currency | |
| E10 - Equipment | $1,550,307.15 | currency | |
| E20 - Furnishings | $1,550,307.15 | currency | |
| F10 - Special Construction - Eq | $0.00 | currency | |
| Equipment Other | $0.00 | currency | |
| Eq Non Taxable Items | $0.00 | currency | |
| Eq Non Taxable Items Esc | $0.00 | currency | |
| Eq Sales Tax | $316,262.66 | currency | |
| Eq Sales Tax Esc | $352,349.00 | currency | |
| Sub TOTAL | $1.50 | currency | |
| EQUIPMENT TOTAL | $3,416,876.95 | currency | |
| EQUIPMENT TOTAL Esc | $3,806,744.00 | currency | |
| Project Artwork | $356,195.85 | currency | |
| Higher Ed Artwork | $0.00 | currency | |
| Artwork Other | $356,195.85 | currency | |
| ARTWORK TOTAL | $356,195.85 | currency | |
| ARTWORK TOTAL Esc | $356,195.85 | currency | |
| PROJECT MANAGEMENT TOTAL | $0.00 | currency | |
| PROJECT MANAGEMENT TOTAL Esc | $0.00 | currency | |
| Agency Project Administration Subtotal | $0.00 | currency | |
| DES Additional Services Subtotal | $0.00 | currency | |
| Other Project Admin Costs | $0.00 | currency | |
| OTHER COSTS TOTAL | $3,100,614.30 | currency | |
| OTHER COSTS TOTAL Esc | $3,372,539.00 | currency | |
| Add Notes - Acq | Tab A. AcquisitionInsert Row Here | long_text | |
| Add Notes - Cons | Tab B. Consultant ServicesInsert Row Here | long_text | |
| Add Notes - Const | Tab C. Construction ContractsInsert Row Here | long_text | |
| Add Notes - Eq | Tab D. EquipmentInsert Row Here | long_text | |
| Add Notes - Art | Tab E. ArtworkInsert Row Here | long_text | |
| Add Notes - PM | Tab F. Project ManagementInsert Row Here | long_text | |
| Add Notes - Other | Tab G. Other CostsInsert Row Here | long_text | |
Data Tables
| Yes/No | Project Administration | Contingency | Month/Year | Predesign Month/Year | Design Month/Year | Construction Month/Year | Mid-Point of Design | Mid-Point of Construction | A/E Schedule | A/E Fee Class Schedule A | Project Mgmt (AE-4%) | PM Discount | 3.00% |
| Yes | Agency | 5% | January-16 | January-16 | January-16 | January-16 | September-27 | March-29 | A | 7.9100% | $1,292,956 | Art | 0.50% |
| No | DES | 10% | February-16 | February-16 | February-16 | February-16 | | | B | 6.7800% | | Inflation Rate | 3.16% |
| | | March-16 | March-16 | March-16 | March-16 | | | C | 5.6600% | | Contingency New | 5.00% |
| | | April-16 | April-16 | April-16 | April-16 | | | DBB A | 7.9100% | | Contingency Remodel | 10.00% |
| | | May-16 | May-16 | May-16 | May-16 | | | DBB C | 5.6600% | | Remodel Add-on | 3.00% |
| | | June-16 | June-16 | June-16 | June-16 | | | GCCM A | 8.5100% | | PM Minor | 4.00% |
| DBB | 5% | No | July-16 | July-16 | July-16 | July-16 | | | GCCM C | 6.7100% | | Base Inflation | 3.16% |
| DB-Criteria | 1% | No | August-16 | August-16 | August-16 | August-16 | | | | | | | |
| DB-Bridging | 2% | No | September-16 | September-16 | September-16 | September-16 | | | Other Sch. A Projects | A | | | |
| DB-Progressive | 1% | No | October-16 | October-16 | October-16 | October-16 | | | Art galleries | A | | | |
| GCCM | 2% | yes | November-16 | November-16 | November-16 | November-16 | | | Auditorium with stage | A | | | |
| | | December-16 | December-16 | December-16 | December-16 | | | Communications Building | A | | | |
| | | January-17 | January-17 | January-17 | January-17 | | | Courthouses | A | | | |
| | | February-17 | February-17 | February-17 | February-17 | | | Detention/correctional facilities - maximum | A | | | |
| | | March-17 | March-17 | March-17 | March-17 | | | Exposition building | A | | | |
| | | April-17 | April-17 | April-17 | April-17 | | | Extended care facilities | A | | | |
| | | May-17 | May-17 | May-17 | May-17 | | | Fish hatcheries | A | | | |
| | | June-17 | June-17 | June-17 | June-17 | | | Heating and power plants | A | | | |
| | | July-17 | July-17 | July-17 | July-17 | | | Hospitals | A | | | |
| | | August-17 | August-17 | August-17 | August-17 | | | Laboratories (Research) | A | | | |
| | | September-17 | September-17 | September-17 | September-17 | | | Medical office and clinics | A | | | |
| | | October-17 | October-17 | October-17 | October-17 | | | Mental Institutions | A | | | |
| | | November-17 | November-17 | November-17 | November-17 | | | Museums | A | | | |
| | | December-17 | December-17 | December-17 | December-17 | | | Observatories | A | | | |
| | | January-18 | January-18 | January-18 | January-18 | | | Research Facilities | A | | | |
| | | February-18 | February-18 | February-18 | February-18 | | | Sewer treatment plants | A | | | |
| | | March-18 | March-18 | March-18 | March-18 | | | Special schools for physically disadvantaged | A | | | |
| | | April-18 | April-18 | April-18 | April-18 | | | Theaters and similar facilities | A | | | |
| | | May-18 | May-18 | May-18 | May-18 | | | Veterinary hospitals | A | | | |
| | | June-18 | June-18 | June-18 | June-18 | | | Water treatment plants | A | | | |
| | | July-18 | July-18 | July-18 | July-18 | | | Other Sch. B Projects | B | | | |
| | | August-18 | August-18 | August-18 | August-18 | | | Apartment | B | | | |
| | | September-18 | September-18 | September-18 | September-18 | | | Archive building | B | | | |
| | | October-18 | October-18 | October-18 | October-18 | | | Armories | B | | | |
| | | November-18 | November-18 | November-18 | November-18 | | | Auditorium without stage | B | | | |
| | | December-18 | December-18 | December-18 | December-18 | | | College classroom facilities | B | | | |
| | | January-19 | January-19 | January-19 | January-19 | | | Computer rooms | B | | | |
| | | February-19 | February-19 | February-19 | February-19 | | | Convention facilities | B | | | |
| | | March-19 | March-19 | March-19 | March-19 | | | Day care facilities | B | | | |
| | | April-19 | April-19 | April-19 | April-19 | | | Detention/correctional facilities - min & max | B | | | |
| | | May-19 | May-19 | May-19 | May-19 | | | Dining halls/institute | B | | | |
| | | June-19 | June-19 | June-19 | June-19 | | | Dormitories | B | | | |
| | | July-19 | July-19 | July-19 | July-19 | | | Fire and police stations | B | | | |
| | | August-19 | August-19 | August-19 | August-19 | | | Gymnasiums | B | | | |
| | | September-19 | September-19 | September-19 | September-19 | | | Laundry and cleaning facilities | B | | | |
| | | October-19 | October-19 | October-19 | October-19 | | | Libraries | B | | | |
| | | November-19 | November-19 | November-19 | November-19 | | | Neighborhood centers and similar recreation facilities | B | | | |
| | | December-19 | December-19 | December-19 | December-19 | | | Nursing homes | B | | | |
| | | January-20 | January-20 | January-20 | January-20 | | | Office buildings | B | | | |
| | | February-20 | February-20 | February-20 | February-20 | | | Recreational building | B | | | |
| | | March-20 | March-20 | March-20 | March-20 | | | Residence | B | | | |
| | | April-20 | April-20 | April-20 | April-20 | | | Schools (primary and secondary) | B | | | |
| | | May-20 | May-20 | May-20 | May-20 | | | Science labs (teaching) | B | | | |
| | | June-20 | June-20 | June-20 | June-20 | | | Stadiums multi-purpose | B | | | |
| | | July-20 | July-20 | July-20 | July-20 | | | Storage-cold | B | | | |
| | | August-20 | August-20 | August-20 | August-20 | | | Transportation terminals | B | | | |
| | | September-20 | September-20 | September-20 | September-20 | | | Vocational schools | B | | | |
| | | October-20 | October-20 | October-20 | October-20 | | | Other Sch. C Projects | C | | | |
| | | November-20 | November-20 | November-20 | November-20 | | | Civil Construction | C | | | |
| | | December-20 | December-20 | December-20 | December-20 | | | Emergency generator facilities | C | | | |
| | | January-21 | January-21 | January-21 | January-21 | | | Farm structures | C | | | |
| | | February-21 | February-21 | February-21 | February-21 | | | Greenhouses | C | | | |
| | | March-21 | March-21 | March-21 | March-21 | | | Guard towers | C | | | |
| | | April-21 | April-21 | April-21 | April-21 | | | Industrial buildings without special facilities | C | | | |
| | | May-21 | May-21 | May-21 | May-21 | | | Parking structures and garages | C | | | |
| | | June-21 | June-21 | June-21 | June-21 | | | Printing plants | C | | | |
| | | July-21 | July-21 | July-21 | July-21 | | | Prototype facilities | C | | | |
| | | August-21 | August-21 | August-21 | August-21 | | | Service garages | C | | | |
| | | September-21 | September-21 | September-21 | September-21 | | | Shop and maintenance facilities | C | | | |
| | | October-21 | October-21 | October-21 | October-21 | | | Simple loft-type structures (w/out special equipment) | C | | | |
| | | November-21 | November-21 | November-21 | November-21 | | | Stadium-grandstand type | C | | | |
| | | December-21 | December-21 | December-21 | December-21 | | | Warehouses | C | | | |
| | | January-22 | January-22 | January-22 | January-22 | | | | | | | |
| | | February-22 | February-22 | February-22 | February-22 | | | | | | | |
| | | March-22 | March-22 | March-22 | March-22 | | | | | | | |
| | | April-22 | April-22 | April-22 | April-22 | | | | | | | |
| | | May-22 | May-22 | May-22 | May-22 | | | | | | | |
| | | June-22 | June-22 | June-22 | June-22 | | | | | | | |
| | | July-22 | July-22 | July-22 | July-22 | | | | | | | |
| | | August-22 | August-22 | August-22 | August-22 | | | | | | | |
| | | September-22 | September-22 | September-22 | September-22 | | | | | | | |
| | | October-22 | October-22 | October-22 | October-22 | | | | | | | |
| | | November-22 | November-22 | November-22 | November-22 | | | | | | | |
| | | December-22 | December-22 | December-22 | December-22 | | | | | | | |
| | | January-23 | January-23 | January-23 | January-23 | | | | | | | |
| | | February-23 | February-23 | February-23 | February-23 | | | | | | | |
| | | March-23 | March-23 | March-23 | March-23 | | | | | | | |
| | | April-23 | April-23 | April-23 | April-23 | | | | | | | |
| | | May-23 | May-23 | May-23 | May-23 | | | | | | | |
| | | June-23 | June-23 | June-23 | June-23 | | | | | | | |
| | | July-23 | July-23 | July-23 | July-23 | | | | | | | |
| | | August-23 | August-23 | August-23 | August-23 | | | | | | | |
| | | September-23 | September-23 | September-23 | September-23 | | | | | | | |
| | | October-23 | October-23 | October-23 | October-23 | | | | | | | |
| | | November-23 | November-23 | November-23 | November-23 | | | | | | | |
| | | December-23 | December-23 | December-23 | December-23 | | | | | | | |
| | | January-24 | January-24 | January-24 | January-24 | | | | | | | |
| | | February-24 | February-24 | February-24 | February-24 | | | | | | | |
| | | March-24 | March-24 | March-24 | March-24 | | | | | | | |
| | | April-24 | April-24 | April-24 | April-24 | | | | | | | |
| | | May-24 | May-24 | May-24 | May-24 | | | | | | | |
| | | June-24 | June-24 | June-24 | June-24 | | | | | | | |
| | | July-24 | July-24 | July-24 | July-24 | | | | | | | |
| | | August-24 | August-24 | August-24 | August-24 | | | | | | | |
| | | September-24 | September-24 | September-24 | September-24 | | | | | | | |
| | | October-24 | October-24 | October-24 | October-24 | | | | | | | |
| | | November-24 | November-24 | November-24 | November-24 | | | | | | | |
| | | December-24 | December-24 | December-24 | December-24 | | | | | | | |
| | | January-25 | January-25 | January-25 | January-25 | | | | | | | |
| | | February-25 | February-25 | February-25 | February-25 | | | | | | | |
| | | March-25 | March-25 | March-25 | March-25 | | | | | | | |
| | | April-25 | April-25 | April-25 | April-25 | | | | | | | |
| | | May-25 | May-25 | May-25 | May-25 | | | | | | | |
| | | June-25 | June-25 | June-25 | June-25 | | | | | | | |
| | | July-25 | July-25 | July-25 | July-25 | | | | | | | |
| | | August-25 | August-25 | August-25 | August-25 | | | | | | | |
| | | September-25 | September-25 | September-25 | September-25 | | | | | | | |
| | | October-25 | October-25 | October-25 | October-25 | | | | | | | |
| | | November-25 | November-25 | November-25 | November-25 | | | | | | | |
| | | December-25 | December-25 | December-25 | December-25 | | | | | | | |
| | | January-26 | January-26 | January-26 | January-26 | | | | | | | |
| | | February-26 | February-26 | February-26 | February-26 | | | | | | | |
| | | March-26 | March-26 | March-26 | March-26 | | | | | | | |
| | | April-26 | April-26 | April-26 | April-26 | | | | | | | |
| | | May-26 | May-26 | May-26 | May-26 | | | | | | | |
| | | June-26 | June-26 | June-26 | June-26 | | | | | | | |
| | | July-26 | July-26 | July-26 | July-26 | | | | | | | |
| | | August-26 | August-26 | August-26 | August-26 | | | | | | | |
| | | September-26 | September-26 | September-26 | September-26 | | | | | | | |
| | | October-26 | October-26 | October-26 | October-26 | | | | | | | |
| | | November-26 | November-26 | November-26 | November-26 | | | | | | | |
| | | December-26 | December-26 | December-26 | December-26 | | | | | | | |
| | | January-27 | January-27 | January-27 | January-27 | | | | | | | |
| | | February-27 | February-27 | February-27 | February-27 | | | | | | | |
| | | March-27 | March-27 | March-27 | March-27 | | | | | | | |
| | | April-27 | April-27 | April-27 | April-27 | | | | | | | |
| | | May-27 | May-27 | May-27 | May-27 | | | | | | | |
| | | June-27 | June-27 | June-27 | June-27 | | | | | | | |
| | | July-27 | July-27 | July-27 | July-27 | | | | | | | |
| | | August-27 | August-27 | August-27 | August-27 | | | | | | | |
| | | September-27 | September-27 | September-27 | September-27 | | | | | | | |
| | | October-27 | October-27 | October-27 | October-27 | | | | | | | |
| | | November-27 | November-27 | November-27 | November-27 | | | | | | | |
| | | December-27 | December-27 | December-27 | December-27 | | | | | | | |
| | | January-28 | January-28 | January-28 | January-28 | | | | | | | |
| | | February-28 | February-28 | February-28 | February-28 | | | | | | | |
| | | March-28 | March-28 | March-28 | March-28 | | | | | | | |
| | | April-28 | April-28 | April-28 | April-28 | | | | | | | |
| | | May-28 | May-28 | May-28 | May-28 | | | | | | | |
| | | June-28 | June-28 | June-28 | June-28 | | | | | | | |
| | | July-28 | July-28 | July-28 | July-28 | | | | | | | |
| | | August-28 | August-28 | August-28 | August-28 | | | | | | | |
| | | September-28 | September-28 | September-28 | September-28 | | | | | | | |
| | | October-28 | October-28 | October-28 | October-28 | | | | | | | |
| | | November-28 | November-28 | November-28 | November-28 | | | | | | | |
| | | December-28 | December-28 | December-28 | December-28 | | | | | | | |
| | | January-29 | January-29 | January-29 | January-29 | | | | | | | |
| | | February-29 | February-29 | February-29 | February-29 | | | | | | | |
| | | March-29 | March-29 | March-29 | March-29 | | | | | | | |
| | | April-29 | April-29 | April-29 | April-29 | | | | | | | |
| | | May-29 | May-29 | May-29 | May-29 | | | | | | | |
| | | June-29 | June-29 | June-29 | June-29 | | | | | | | |
| | | July-29 | July-29 | July-29 | July-29 | | | | | | | |
| | | August-29 | August-29 | August-29 | August-29 | | | | | | | |
| | | September-29 | September-29 | September-29 | September-29 | | | | | | | |
| | | October-29 | October-29 | October-29 | October-29 | | | | | | | |
| | | November-29 | November-29 | November-29 | November-29 | | | | | | | |
| | | December-29 | December-29 | December-29 | December-29 | | | | | | | |
| | | January-30 | January-30 | January-30 | January-30 | | | | | | | |
| | | February-30 | February-30 | February-30 | February-30 | | | | | | | |
| | | March-30 | March-30 | March-30 | March-30 | | | | | | | |
| | | April-30 | April-30 | April-30 | April-30 | | | | | | | |
| | | May-30 | May-30 | May-30 | May-30 | | | | | | | |
| | | June-30 | June-30 | June-30 | June-30 | | | | | | | |
| | | July-30 | July-30 | July-30 | July-30 | | | | | | | |
| | | August-30 | August-30 | August-30 | August-30 | | | | | | | |
| | | September-30 | September-30 | September-30 | September-30 | | | | | | | |
| | | October-30 | October-30 | October-30 | October-30 | | | | | | | |
| | | November-30 | November-30 | November-30 | November-30 | | | | | | | |
| | | December-30 | December-30 | December-30 | December-30 | | | | | | | |
| | | January-31 | January-31 | January-31 | January-31 | | | | | | | |
| | | February-31 | February-31 | February-31 | February-31 | | | | | | | |
| | | March-31 | March-31 | March-31 | March-31 | | | | | | | |
| | | April-31 | April-31 | April-31 | April-31 | | | | | | | |
| | | May-31 | May-31 | May-31 | May-31 | | | | | | | |
| | | June-31 | June-31 | June-31 | June-31 | | | | | | | |
| | | July-31 | July-31 | July-31 | July-31 | | | | | | | |
| | | August-31 | August-31 | August-31 | August-31 | | | | | | | |
| | | September-31 | September-31 | September-31 | September-31 | | | | | | | |
| | | October-31 | October-31 | October-31 | October-31 | | | | | | | |
| | | November-31 | November-31 | November-31 | November-31 | | | | | | | |
| | | December-31 | December-31 | December-31 | December-31 | | | | | | | |
| | | January-32 | January-32 | January-32 | January-32 | | | | | | | |
| | | February-32 | February-32 | February-32 | February-32 | | | | | | | |
| | | March-32 | March-32 | March-32 | March-32 | | | | | | | |
| | | April-32 | April-32 | April-32 | April-32 | | | | | | | |
| | | May-32 | May-32 | May-32 | May-32 | | | | | | | |
| | | June-32 | June-32 | June-32 | June-32 | | | | | | | |
| | | July-32 | July-32 | July-32 | July-32 | | | | | | | |
| | | August-32 | August-32 | August-32 | August-32 | | | | | | | |
| | | September-32 | September-32 | September-32 | September-32 | | | | | | | |
| | | October-32 | October-32 | October-32 | October-32 | | | | | | | |
| | | November-32 | November-32 | November-32 | November-32 | | | | | | | |
| | | December-32 | December-32 | December-32 | December-32 | | | | | | | |
| | | January-33 | January-33 | January-33 | January-33 | | | | | | | |
| | | February-33 | February-33 | February-33 | February-33 | | | | | | | |
| | | March-33 | March-33 | March-33 | March-33 | | | | | | | |
| | | April-33 | April-33 | April-33 | April-33 | | | | | | | |
| | | May-33 | May-33 | May-33 | May-33 | | | | | | | |
| | | June-33 | June-33 | June-33 | June-33 | | | | | | | |
| | | July-33 | July-33 | July-33 | July-33 | | | | | | | |
| | | August-33 | August-33 | August-33 | August-33 | | | | | | | |
| | | September-33 | September-33 | September-33 | September-33 | | | | | | | |
| | | October-33 | October-33 | October-33 | October-33 | | | | | | | |
| | | November-33 | November-33 | November-33 | November-33 | | | | | | | |
| | | December-33 | December-33 | December-33 | December-33 | | | | | | | |
| | | January-34 | January-34 | January-34 | January-34 | | | | | | | |
| | | February-34 | February-34 | February-34 | February-34 | | | | | | | |
| | | March-34 | March-34 | March-34 | March-34 | | | | | | | |
| | | April-34 | April-34 | April-34 | April-34 | | | | | | | |
| | | May-34 | May-34 | May-34 | May-34 | | | | | | | |
| | | June-34 | June-34 | June-34 | June-34 | | | | | | | |
| | | July-34 | July-34 | July-34 | July-34 | | | | | | | |
| | | August-34 | August-34 | August-34 | August-34 | | | | | | | |
| | | September-34 | September-34 | September-34 | September-34 | | | | | | | |
| | | October-34 | October-34 | October-34 | October-34 | | | | | | | |
| | | November-34 | November-34 | November-34 | November-34 | | | | | | | |
| | | December-34 | December-34 | December-34 | December-34 | | | | | | | |
| | | January-35 | January-35 | January-35 | January-35 | | | | | | | |
| | | February-35 | February-35 | February-35 | February-35 | | | | | | | |
| | | March-35 | March-35 | March-35 | March-35 | | | | | | | |
| | | April-35 | April-35 | April-35 | April-35 | | | | | | | |
| | | May-35 | May-35 | May-35 | May-35 | | | | | | | |
| | | June-35 | June-35 | June-35 | June-35 | | | | | | | |
| | | July-35 | July-35 | July-35 | July-35 | | | | | | | |
| | | August-35 | August-35 | August-35 | August-35 | | | | | | | |
| | | September-35 | September-35 | September-35 | September-35 | | | | | | | |
| | | October-35 | October-35 | October-35 | October-35 | | | | | | | |
| | | November-35 | November-35 | November-35 | November-35 | | | | | | | |
| | | December-35 | December-35 | December-35 | December-35 | | | | | | | |
| | | January-36 | January-36 | January-36 | January-36 | | | | | | | |
| | | February-36 | February-36 | February-36 | February-36 | | | | | | | |
| | | March-36 | March-36 | March-36 | March-36 | | | | | | | |
| | | April-36 | April-36 | April-36 | April-36 | | | | | | | |
| | | May-36 | May-36 | May-36 | May-36 | | | | | | | |
| | | June-36 | June-36 | June-36 | June-36 | | | | | | | |
| | | July-36 | July-36 | July-36 | July-36 | | | | | | | |
| | | August-36 | August-36 | August-36 | August-36 | | | | | | | |
| | | September-36 | September-36 | September-36 | September-36 | | | | | | | |
| | | October-36 | October-36 | October-36 | October-36 | | | | | | | |
| | | November-36 | November-36 | November-36 | November-36 | | | | | | | |
| | | December-36 | December-36 | December-36 | December-36 | | | | | | | |
Transition
| Date Ranges | | | | | | |
| Estimate Date | 9/18/25 | | | Days | Wkdays |
| Predesign | 7/15/26 | 2/15/27 | | 215 | 154 |
| Design | 3/15/27 | 3/15/28 | | 366 | 263 |
| Construction | 6/1/28 | 12/15/29 | | 562 | 402 |
| Closeout | | | | | |
| Unit of Measure | | | | | | |
| GSF | 55,000 | | GSF | | |
| Alt | 0 | | 0 | | |
Use 55,000 GSF
APW
| Method | DBB | | | | |
| APW | No | | | | |
| Check on Prior & current biennium | | | | | | |
| Prior Biennia | 500000 | | | | |
| Current Biennium | 7278726.8 | | | | |
| Next | 63816638.73443 | | | | |
| Out | 0 | | | | |
| | | prior | current | next | out |
| Is there predesign | 1 | 0 | 0 | 1 | |
| Is there design | 1 | 0 | 0 | 1 | |
| Is there construction | 1 | 0 | 0 | 0 | |
| Validation Flags | | | | | |
| Funding in prior, but no activity | | 1 | | | |
| Activity in prior, but no funding | | 0 | | | |
| Activity in current but no funding | | 0 | | | |
| Activity in next but no funding | | 0 | | | |