This is a Bid Schedule addendum document for a state and local contract opportunity in Utah involving the Little Dell Dam Restoration of DOCS Pipe Coating project (Project No. 512700026). The work consists of furnishing and installing equipment, facilities, services, and appurtenances for pipe and pipe fitting exterior surface preparation, exterior coating, repair, associated environmental and safety controls, and waste disposal in three facilities located at Little Dell Dam Outlet Works. The project includes three separate alternate bid schedules—Alternate A (Adit Structure), Alternate B (DOCS), and Alternate C (ECC)—with the Owner having the option to award one alternate bid schedule, a combination of the three alternates, or all bid schedules. An open bid meeting is scheduled for September 23, 2026 at 2:00 PM MST via Microsoft Teams. Each alternate includes line items for mobilization and demobilization, heating/ventilation/dehumidification/lighting, surface preparation, coating application, preparation for potential water in pipe, and general allowances.
The pricing structure consists entirely of lump sum bid items across all three alternates. Alternate A includes a fixed allowance of $26,666 for preparation for potential water in pipe and $81,000 for general allowance. Alternate B includes $6,667 for water preparation and $12,960 for general allowance. Alternate C includes $6,667 for water preparation, $9,040 for general allowance, and an additional line item for concrete pipe support pad repair on a per-pad basis for four pads. Payment procedures follow APWA Section 01 29 00 standards, with mobilization and demobilization measured on a percentage basis tied to original contract amount earned, heating/ventilation/dehumidification/lighting and surface preparation measured at 20 percent upon first pay request and 80 percent during progress of work, and coating application measured on a lump sum basis. Unused allowance funds are to be credited to the Owner through final reconciliation change orders.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Schedule 00 43 00 - 1
DOCUMENT 00 43 00
BID SCHEDULE
PART 1 GENERAL
1.1 DOCUMENT INCLUDES
A. Price schedules.
B. Measurement and payment provisions.
1.2 1.2 CONSTRUCTION CONTRACT
A. Little Dell Dam - Restoration of DOCS Pipe Coating
B. Project No. 512700026
1.3 REFERENCES
A. APWA Section 01 29 00: Payment Procedures.
B. Document 00 52 00: Agreement.
1.4 SCHEDULE TO BE ADDED TO THE AGREEMENT
A. This document will be added to the Agreement by reference.
PART 2 PRICE SCHEDULES
2.1 GENERAL
A. Number of schedules in Base Bid: Zero
B. Number of alternate schedules: Three.
C. Owner may award one alternate bid schedule, a combination of the three alternate bid schedules, or all bid schedules.
D. For progress payment procedures, see APWA Section 01 29 00 requirements.
2.2 BIDS
A. CAUTION: Bidder shall complete all blanks in the following price schedule.
B. Failure to do so may cause the bid to be declared non-responsive by ENGINEER.
C. Alternate A (Adit Structure):This bid alternate includes surface preparation and coating of existing pipe and pipe fittings, hazardous and non-hazardous waste handling and disposal in the Adit Structure. Additionally, it includes an allowance for additional equipment and preparations being needed in the event of water in the pipes in the Adit Structure at the time of coating. If water is not present at the time of coating, all costs associated with this line item are to be credited back to the Owner. Furthermore, a General Allowance is included which can be used with Owner permission see Section 00 43 00 3.02.
D. Alternate B (DOCS): This bid alternate includes surface preparation and coating of existing pipe and pipe fittings, hazardous and non-hazardous waste handling and disposal in the DOCS. Additionally, it includes an allowance for additional equipment
00 43 00 - 2 and preparations being needed in the event of water in the pipes in the DOCS at the time of coating. If water is not present at the time of coating, all costs associated with this line item are to be credited back to the Owner. Furthermore, a General Allowance is included which can be used with Owner permission see Section 00 43 00 3.02.
E. Alternate C (ECC):This bid alternate includes surface preparation and coating of existing pipe and pipe fittings, hazardous and non-hazardous waste handling and disposal in the ECC. Additionally, it includes an allowance for additional equipment and preparations needed in the event of water in the pipes in the ECC at the time of coating. If water is not present at the time of coating, all costs associated with this line item are to be credited back to the Owner. Furthermore, a General Allowance is included which can be used with Owner permission see Section 00 43 00 3.02.
00 43 00 - 3
Schedule 1
LITTLE DELL DAM - RESTORATION OF DOCS PIPE COATING
PROJECT NO. 512700026
Alternate Bid A (Adit Structure)
Item Specification Reference Number
Classification of Work Quantity and Unit
Unit Price
Total Cost
1.01 01 71 13 Mobilization and Demobilization (Adit Structure)
Lump Sum
1.02 01 57 00 Heating, Ventilation, Dehumidification, Lighting (Adit Structure)
1.03 09 96 00 Surface Preparation (Adit Structure)
1.04 09 96 00 Coating Application (Adit Structure)
1.05 01 14 00 Preparation for Potential Water In Pipe (Adit Structure)
Lump Sum
$26,666 $26,666
1.06 00 72 00 and 00 73 10 General Allowance
$81,000 $81,000
Schedule A Total $________________________
Alternate Bid B (DOCS)
Item Specification Reference Number
Classification of Work Quantity and Unit
Unit Price
Total Cost
1.07 01 71 13 Mobilization and Demobilization
1.08 01 57 00
Dehumidification, Lighting
1.09 09 96 00 Surface Preparation (DOCS)
1.10 09 96 00 Coating Application (DOCS)
1.11 01 14 00 Preparation for Potential Water In Pipe (DOCS)
Lump Sum
$6,667 $6,667
1.12 00 72 00 and 00 73 10 General Allowance
$12,960 $12,960
00 43 00 - 4
Schedule B Total $________________________
Alternate Bid C (ECC)
Item Specification Reference Number
Classification of Work Quantity and Unit
Unit Price
Total Cost
1.13 01 71 13 Mobilization and Demobilization
1.14 01 57 00
Dehumidification, Lighting
1.15 09 96 00 Surface Preparation (ECC)
1.16 09 96 00 Coating Application (ECC)
1.17 03 30 00 Concrete Pipe Support Pad Repair
Per Pad (4)
1.18 01 14 00 Preparation for Potential Water In Pipe (ECC)
Lump Sum
$6,667 $6,667
1.19 00 72 00 and 00 73 10 General Allowance
$9,040 $9,040
Schedule C Total $________________________
2.3 BID SUMMARY
A. Schedule A Total (Alternate Bid A (Adit Structure)): $________________________
B. Schedule B Total (Alternate Bid B (DOCS)): $________________________
C. Schedule C Total (Alternate Bid C (ECC)): $________________________
PART 3 MEASUREMENT AND PAYMENT
3.1 IN GENERAL
A. See APWA Section 01 29 00 for general measurement and payment provisions.
B. Specification sections referenced in price schedule line items give additional definitions to the classification of work.
C. Incidental work or material will not be measured, counted or paid for separately.
D. Backfilling demolition work depressions will not be measured or paid for separately except where structure or obstructions that are not designated for removal and disposal in the Bidding Documents, and that cannot be removed with equipment reasonably expected to be used in the Work without cutting, drilling, or blasting, will be paid for after adjusting the Contract Price by Contract Modification pricing.
00 43 00 - 5
3.2 MOBILIZATION AND DEMOBILIZATION - (ADIT STRUCTURE) (BID ITEM
NO. 1.01)
A. Measurement:
Percent of Original Contract Amount Earned
Percent of Amount Bid for Mobilization to be Paid
5 40 15 20 40 30 50 10
B. Payment Covers:
1. Includes the following for the ADIT Structure: mobilization, video recording site conditions prior to construction, installation of temporary facilities, temporary utilities, bringing all necessary construction equipment to site, security and protection, construction support, construction schedules risk, and incidentals such as coordination with and assisting utility companies while they do their utility work, miscellaneous probing for buried utilities public information dissemination, obtaining any additional permits not already obtained by the OWNER, the removal and replacement of work obstructions, the removal and replacement of site access appurtenances, and demobilization (refer to Section 01 71 13, Mobilization and Demobilization).
3.3 HEATING, VENTILATION, DEHUMIDIFICATION, AND LIGHTING (ADIT
STRUCTURE) (BID ITEM NO. 1.02)
A. Measured on a lump sum basis.
1. 20 percent with first pay request.
2. 80 percent during progress of work.
B. Bid price covers the following for the ADIT Structure:
ventilation, dehumidification, and lighting efforts as indicated in the contract documents including but not limited to; labor, materials and equipment required to properly light, vent, heat, dehumidify, keep site drains free of chemicals and debris, and protect the work from any seeps within the Adit structure as needed to perform the work.
3.4 SURFACE PREPARATION (ADIT STRUCTURE) (BID ITEM NO. 1.03)
A. Measured on a lump sum basis.
1. 20 percent with first pay request.
2. 80 percent during progress of work.
B. Payment covers materials, equipment, and labor required for surface preparation on all surfaces to be coated, including piping, pipe supports, pipe couplers, pipe hold down straps, etc.
control efforts as indicated in the contract documents including but not limited to;
labor, materials and equipment required to properly control dust according to
00 43 00 - 6
SLCDPU standards in the ADIT Structure. Furthermore, this includes containment, clean up, proper handling and storage of waste, laboratory analyses of waste material, and disposal of hazardous and non-hazardous waste, in accordance with Section 09 96 00, HIGH PERFORMANCE COATING and Drawings, complete.
C. Payment for laboratory testing and analyses, and costs associated with sample collection, storage, and transport to be the actual fees assessed to the CONTRACTOR.
3.5 COATING APPLICATION (ADIT STRUCTURE) (BID ITEM NO. 1.04)
A. Measured on a lump sum basis.
B. Payment includes materials, equipment, and labor required for coating system application in the Adit structure on surfaces identified by the ENGINEER in the contract drawings, in accordance with Section 09 96 00, HIGH PERFORMANCE COATING. These items include but are not limited to piping, pipe supports, couplings, restraints, etc.
3.6 PREPARATION FOR POTENTIAL WATER FLOW IN PIPE (ADIT
STRUCTURE) (BID ITEM NO. 1.05)
A. To minimize delays and expedite the flow of work on the project, a maximum dollar amount has been included in the Bid Schedule for the ADIT Structure to compensate the CONTRACTOR for unspecified extra or additional Work related to preparations in the event that the piping is full of water at the time of coating.
B. Allowance funds that have not been disbursed at the completion of the project will be credited to the OWNER by the final reconciliation Change Order.
3.7 GENERAL ALLOWANCE (BID ITEM NO. 1.06)
A. To minimize delays and expedite the flow of work on the project, a maximum dollar amount has been included in the Bid Schedule for the ADIT Structure to compensate the CONTRACTOR for unspecified extra or additional Work that was not foreseeable at the time of the bid, but that is necessary to complete the Project as originally contemplated. An owner authorized General Allowance Work Order is required to obtain payment from the General Allowance.
B. See Article 10.4 in the Modifications to the General Conditions for additional information on the management, approval and payment for General Allowance Work Orders.
C. General Allowance funds that have not been disbursed at the completion of the project will be credited to the OWNER by the final reconciliation Change Order.
3.8 MOBILIZATION AND DEMOBILIZATION - (DOCS STRUCTURE) (BID ITEM
NO. 1.07)
A. Measurement:
Percent of Original Contract Amount Earned
Percent of Amount Bid for Mobilization to be Paid
5 40 15 20
00 43 00 - 7
40 30 50 10
B. Payment Covers:
1. Includes the following for the DOCS Structure: mobilization, video recording site conditions prior to construction, installation of temporary facilities, temporary utilities, bringing all necessary construction equipment to site, security and protection, construction support, construction schedules risk, and incidentals such as coordination with and assisting utility companies while they do their utility work, miscellaneous probing for buried utilities public information dissemination, obtaining any additional permits not already obtained by the OWNER, the removal and replacement of work obstructions, the removal and replacement of site access appurtenances, and demobilization (refer to Section 01 71 13, Mobilization and Demobilization).
3.9 HEATING, VENTILATION, DEHUMIDIFICATION, AND LIGHTING (DOCS
STRUCTURE) (BID ITEM NO. 1.08)
A. Measured on a lump sum basis.
1. 20 percent with first pay request.
2. 80 percent during progress of work.
B. Bid price covers the following for the DOCS Structure:
ventilation, dehumidification, and lighting efforts as indicated in the contract documents including but not limited to; labor, materials and equipment required to properly light, vent, heat, dehumidify, keep site drains free of chemicals and debris, and protect the work from any seeps within the Adit structure as needed to perform the work.
3.10 SURFACE PREPARATION (DOCS STRUCTURE) (BID ITEM NO. 1.09)
A. Measured on a lump sum basis.
1. 20 percent with first pay request.
2. 80 percent during progress of work.
B. Payment covers materials, equipment, and labor required for surface preparation on all surfaces to be coated, including piping, pipe supports, pipe couplers, pipe hold down straps, etc.
control efforts as indicated in the contract documents including but not limited to;
labor, materials and equipment required to properly control dust according to SLCDPU standards in the DOCS Structure. Furthermore, this includes containment, clean up, proper handling and storage of waste, laboratory analyses of waste material, and disposal of hazardous and non-hazardous waste, in accordance with Section 09 96 00, HIGH PERFORMANCE COATING and Drawings, complete.
C. Payment for laboratory testing and analyses, and costs associated with sample collection, storage, and transport to be the actual fees assessed to the CONTRACTOR.
00 43 00 - 8
3.11 COATING APPLICATION (DOCS STRUCTURE) (BID ITEM NO. 1.10)
A. Measured on a lump sum basis.
B. Payment includes materials, equipment, and labor required for coating system application in the DOCS structure on surfaces identified by the ENGINEER in the contract drawings, in accordance with Section 09 96 00, HIGH PERFORMANCE COATING. These items include but are not limited to piping, pipe supports, couplings, restraints, etc.
3.12 PREPARATION FOR POTENTIAL WATER FLOW IN PIPE (DOCS
STRUCTURE) (BID ITEM NO. 1.11)
A. To minimize delays and expedite the flow of work on the project, a maximum dollar amount has been included in the Bid Schedule for the DOCS Structure to compensate the CONTRACTOR for unspecified extra or additional Work related to preparations in the event that the piping is full of water at the time of coating.
B. Allowance funds that have not been disbursed at the completion of the project will be credited to the OWNER by the final reconciliation Change Order.
3.13 GENERAL ALLOWANCE (DOCS STRUCTURE) (BID ITEM NO. 1.12)
A. To minimize delays and expedite the flow of work on the project, a maximum dollar amount has been included in the Bid Schedule for the DOCS Structure to compensate the CONTRACTOR for unspecified extra or additional Work that was not foreseeable at the time of the bid, but that is necessary to complete the Project as originally contemplated. An owner authorized General Allowance Work Order is required to obtain payment from the General Allowance.
B. See Article 10.4 in the Modifications to the General Conditions for additional information on the management, approval and payment for General Allowance Work Orders.
C. General Allowance funds that have not been disbursed at the completion of the project will be credited to the OWNER by the final reconciliation Change Order.
3.14 MOBILIZATION AND DEMOBILIZATION - (ECC STRUCTURE) (BID ITEM
NO. 1.13)
A. Measurement:
Percent of Original Contract Amount Earned
Percent of Amount Bid for Mobilization to be Paid
5 40 15 20 40 30 50 10
B. Payment Covers:
1. Includes the following for the ECC Structure: mobilization, video recording site conditions prior to construction, installation of temporary facilities, temporary utilities, bringing all necessary construction equipment to site, security and
00 43 00 - 9 protection, construction support, construction schedules risk, and incidentals such as coordination with and assisting utility companies while they do their utility work, miscellaneous probing for buried utilities public information dissemination, obtaining any additional permits not already obtained by the OWNER, the removal and replacement of work obstructions, the removal and replacement of site access appurtenances, and demobilization (refer to Section 01 71 13, Mobilization and Demobilization).
3.15 HEATING, VENTILATION, DEHUMIDIFICATION, AND LIGHTING (ECC
STRUCTURE) (BID ITEM NO. 1.14)
A. Measured on a lump sum basis.
1. 20 percent with first pay request.
2. 80 percent during progress of work.
B. Bid price covers the following for the ECC Structure:
ventilation, dehumidification, and lighting efforts as indicated in the contract documents including but not limited to; labor, materials and equipment required to properly light, vent, heat, dehumidify, keep site drains free of chemicals and debris, and protect the work from any seeps within the Adit structure as needed to perform the work.
3.16 SURFACE PREPARATION (ECC STRUCTURE) (BID ITEM NO. 1.15)
A. Measured on a lump sum basis.
1. 20 percent with first pay request.
2. 80 percent during progress of work.
B. Payment covers materials, equipment, and labor required for surface preparation on all surfaces to be coated, including piping, pipe supports, pipe couplers, pipe hold down straps, etc.
control efforts as indicated in the contract documents including but not limited to;
labor, materials and equipment required to properly control dust according to SLCDPU standards in the ECC Structure. Furthermore, this includes containment, clean up, proper handling and storage of waste, laboratory analyses of waste material, and disposal of hazardous and non-hazardous waste, in accordance with Section 09 96 00, HIGH PERFORMANCE COATING and Drawings, complete.
C. Payment for laboratory testing and analyses, and costs associated with sample collection, storage, and transport to be the actual fees assessed to the CONTRACTOR.
3.17 COATING APPLICATION (ECC STRUCTURE) (BID ITEM NO. 1.16)
A. Measured on a lump sum basis.
B. Payment includes materials, equipment, and labor required for coating system application in the ECC structure on surfaces identified by the ENGINEER in the contract drawings, in accordance with Section 09 96 00, HIGH PERFORMANCE COATING. These items include but are not limited to piping, pipe supports, couplings, restraints, etc.
00 43 00 - 10
3.18 CONCRETE PIPE SUPPORT PAD REPAIR (BID ITEM NO. 1.17)
A. Measured and paid on a per pad unit basis.
B. Payment will cover materials, equipment, and labor to properly repair a total of 4 pipe support pads in the ECC for removal of existing pads, new forms, molds, appurtenances, admixtures, and curing new concrete in place.
3.19 PREPARATION FOR POTENTIAL WATER FLOW IN PIPE (ECC
STRUCTURE) (BID ITEM NO. 1.18)
A. To minimize delays and expedite the flow of work on the project, a maximum dollar amount has been included in the Bid Schedule for the ECC Structure to compensate the CONTRACTOR for unspecified extra or additional Work related to preparations in the event that the piping is full of water at the time of coating.
B. Allowance funds that have not been disbursed at the completion of the project will be credited to the OWNER by the final reconciliation Change Order.
3.20 GENERAL ALLOWANCE (ECC STRUCTURE) (BID ITEM NO. 1.19)
A. To minimize delays and expedite the flow of work on the project, a maximum dollar amount has been included in the Bid Schedule for the ECC Structure to compensate the CONTRACTOR for unspecified extra or additional Work that was not foreseeable at the time of the bid, but that is necessary to complete the Project as originally contemplated. An owner authorized General Allowance Work Order is required to obtain payment from the General Allowance.
B. See Article 10.4 in the Modifications to the General Conditions for additional information on the management, approval and payment for General Allowance Work Orders.
C. General Allowance funds that have not been disbursed at the completion of the project will be credited to the OWNER by the final reconciliation Change Order.
END OF DOCUMENT