4_-_MNWR__100__Drawings__Foundation.pdf
PDF 3 MB Posted
- Attached to
- CA-Modoc NWR Construct Concrete Foundation
- Solicitation number
- 140F0322Q0040
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ABBREVIATIONS
ADDL. ADDITIONAL
AGGR. AGGREGATE
ALT. ALTERNATE
A.B. ANCHOR BOLT
ANC. ANCHOR
APPROX. APPROXIMATE
ARCH. ARCHITECTURAL
ASS'Y ASSEMBLY
AVG. AVERAGE
BM. BEAM
BRG. BEARING
BEL. BELOW
BETW. BETWEEN
BLK. BLOCK
BLKG. BLOCKING
BOTT. BOTTOM
B.O. BOTTOM OF
B.O.D. BOTTOM OF DECK
B.N. BOUNDARY NAILING
B.S., B/S BOTH SIDES
BLDG. BUILDING
C.B.C. CALIFORNIA BUILDING CODE
CANTL. CANTILEVER
CLG. CEILING
CEN. CENTER
C.L. CENTERLINE
c.c. CENTER TO CENTER
C.G. CENTER OF GRAVITY
CHNL. CHANNEL
CLR. CLEAR
COL. COLUMN
C.P. COMPLETE PENETRATION
CONC. CONCRETE
CONN. CONNECTION
C.J. CONSTRUCTION JOINT
CONTROL JOINT
CONT. CONTINUOUS
CONTR. CONTRACTOR
CONST. CONSTRUCTION
C/S COUNTERSINK
D.L. DEAD LOAD
D.B.A. DEFORMED BAR ANCHOR
DET. DETAIL
DIAG. DIAGONAL
DIA. DIAMETER
DIM. DIMENSION
D.O. DITTO
DBL. DOUBLE
DWG. DRAWING
D.J. DOWEL JOINT
D.T. DRAG TRUSS
EA. EACH
E.F. EACH FACE
E.S. EACH SIDE
E.W. EACH WAY
ELEC. ELECTRICAL
EL. ELEVATION
EMBED. EMBEDMENT
ENGR. ENGINEER
EQ. EQUAL
EQUIP. EQUIPMENT
EXCAV. EXCAVATION
(E) EXISTING
EXP. EXPANSION
E.J. EXPANSION JOINT
EXT. EXTERIOR
FAB. FABRICATION
F.O. FACE OF
F.O.C. FACE OF CONCRETE
F.O.S. FACE OF STUD
FT. FEET
FIG. FIGURE
FIN. FINISH
F.F. FINISHED FLOOR
FLR. FLOOR
F.D. FLOOR DRAIN
FTG. FOOTING
FDN. FOUNDATION
FRMG. FRAMING
GA. GAUGE
GALV. GALVANIZED
GR. GRADE
GB GRADE BEAM
GRND. GROUND
HGR. HANGER
H.S.A. HEADED STUD ANCHOR
HDR. HEADER
HT. HEIGHT
H.S.B. HIGH STRENGTH BOLT
HSS HOLLOW STRUCTURAL SECTION
HORIZ. HORIZONTAL
HORIZONTAL REINF.
I.B.C. INTERNATIONAL BUILDING CODE
IN. INCHES
INCL'D INCLUDED
INFO. INFORMATION
I.D. INSIDE DIAMETER
INT. INTERIOR
I.J. ISOLATION JOINT
JT. JOINT
JST. JOIST
LBS. POUNDS
LT. LIGHT
L.L. LIVE LOAD
LG. LONG
L.L.H. LONG LEG HORIZONTAL
L.L.V. LONG LEG VERTICAL
L.V.L. LAMINATED VENEER LUMBER
M.B. MACHINE BOLT
M.I.W. MALLEABLE IRON WASHER
MFR. MANUFACTURER
MK MARK
MAX. MAXIMUM
M.D. MID DEPTH
MECH. MECHANICAL
MTL. METAL
MIN. MINIMUM
MISC. MISCELLANEOUS
N.F. NEAR FACE
N.S. NEAR SIDE
(N) NEW
NOM. NOMINAL
N.I.C. NOT IN CONTRACT
NTS NOT TO SCALE
# NUMBER OR POUNDS
O.C. ON CENTER
OPNG. OPENING
OPP. OPPOSITE
O.H. OPPOSITE HAND
O.D. OUTSIDE DIAMETER
PR. PAIR
PTN. PARTITION
PSL PARALLEL STRAND LUNBER
PARL. PARALLEL
PEN. PENETRATION
PERP. PERPENDICULAR
PL. PLATE
pcf POUNDS PER CUBIC FOOT psf POUNDS PER SQUARE FOOT psi POUNDS PER SQUARE INCH
P.A.F. POWDERED ACTUATED FASTENER
P.D.F. POWDER DRIVER FASTENER
PREFAB. PRE-FABRICATED
P.J.F. PREMOLDED JOINT FILLER
PROJ. PROJECT
P.T. PRESSURE TREATED
RAD. RADIUS
REF. REFERENCE
REINF. REINFORCEMENT
R.C. REINFORCED CONCRETE
REQ'D REQUIRED
REV. REVISION
SCHED. SCHEDULE
SECT. SECTION
STS SELF TAPPNG SCREW
SW SHEAR WALL
SHT. SHEET
SHTG. SHEATHING
SIM. SIMILAR
S.J. SLAB JOINT
S.O.G. SLAB ON GRADE
S.B. SOLID BLOCK
SPECS. SPECIFICATIONS
SQ. SQUARE
s.f. SQUARE FEET
STAGG. STAGGERED
STD. STANDARD
STFNR. STIFFENER
STRUCT. STRUCTURAL
SYM. SYMMETRICAL
THRD. THREADED
THRU THROUGH
T.N. TOE NAIL
TOL. TOLERANCE
T&B TOP AND BOTTOM
T.O. TOP OF
T.O.B. TOP OF BEAM
T.O.C. TOP OF CONCRETE
T.O.F. TOP OF FOOTING
T.O.P. TOP OF PLATE
T.O.S. TOP OF STEEL
T.O.W. TOP OF WALL
TS TUBE STEEL
TYP. TYPICAL
U.N.O. UNLESS NOTED OTHERWISE
V.I.F. VERIFY IN FIELD
VERT. VERTICAL
WT. WEIGHT
W.S. WELDED STUD OR WOOD SCREW
WWF WELDED WIRE FABRIC
WWM WELDED WIRE MESH
WF WIDE FLANGE
w/ WITH w/O WITHOUT
WP WORK POINT
PERF. PERFORATED
DRAWN CHECKED
DATE DRAWING NO.
DESIGNEDSERVEYED
PROGRAMMATIC REVIEW
SUBMITTED BY REGIONAL ENGINEER
CERTIFIED 10 CFR 435 COMPLIANCE
(ENERGY)
REVIEWED FOR ADA COMPLIANCE
REVIEWED FOR ENVIRONMENTAL
COMPLIANCE
REVIEWED FOR SAFETY COMPLIANCE
SUBMITTED BY PROJECT MANAGER
UNITED STATES DEPARTMENT OF THE INTERIOR
STATEFIELDSTATTIONCOUNTYFIELDSTATTION
OFSHEET
VERIFY SCALE
THIS BAR IS ONE INCH
ON ORIGINAL DRAWING
ADJUST SCALES
ACCORDINGLY, IF NOT
ONE INCH ON THIS
SHEET
0" 1"
VME BAM
05/24/2021 G000
VME
FISH AND WILDLIFE SERVICE
REGIONS 1, 7 & 8 OFFICE OF ENGINEERING
PORTLAND, OREGON
MODOC
MODOC METAL BUILDING
5364 COUNTY ROAD 115
ALTURAS, CA 96101
SUBSETSHTNO
1 4
PROJECT
LOCATION
S001 GENERAL NOTES
S002 GENERAL FOUNDATION DETAILS
S101 FOUNDATION PLAN
SHEET INDEX
PROJECT INFORMATION
GENERAL NOTES
OWNER
UNITED STATES DEPARTMENT OF THE INTERIOR
FISH AND WILDLIFE SERVICE
REGIONS 1,7 & 8 OFFICE OF ENGINEERING
PORTLAND, OREGON
P: (503) 231-2396
E: ZACH_SPRUELL@FWS.GOV
1. THE CONTRACT DOCUMENTS ARE COMPLEMENTARY AND WHAT IS REQUIRED BY ANY ONE SHALL BE AS BINDING AS IF REQUIRED BY ALL. THE INTENTIONS OF THE DOCUMENTS IS TO INCLUDE ALL LABOR, MATERIALS, EQUIPMENT AND OTHER ITEMS AS NECESSARY FOR THE PROPER EXECUTION AND COMPLETION OF THE WORK. CONTRACTOR IS TO VERIFY ALL EXISTING CONDITIONS AND DIMENSIONS AND IS TO CONTACT ENGINEER PRIOR TO PROCEEDING WITH WORK IF DISCREPANCIES OR UNANTICIPATED CONDITIONS ARE FOUND.
2. DO NOT SCALE DRAWINGS. ANY QUESTIONS REGARDING DIMENSIONS SHOULD BE DIRECTED TO THE
ENGINEER PRIOR TO PROCEEDING WITH THE WORK.
3. NOTES REPRESENT ITEMS OF WORK TO BE ACCOMPLISHED AT EACH LOCATION OF THE ITEM THROUGHOUT
THE SITE, BUILDING OR PROJECT LIMITS.
4. BEFORE SUBMITTING A BID: EACH BIDDER SHALL CAREFULLY EXAMINE THE DRAWINGS, READ THE SPECIFICATIONS AND ALL OTHER PROPOSED CONTRACT DOCUMENTS AND VISIT THE SITE OF THE WORK.
EACH BIDDER SHALL FULLY INFORM HIM/HERSELF PRIOR TO BIDDING AS TO ALL EXISTING CONDITIONS AND LIMITATIONS UNDER WHICH THE WORK IS TO BE PERFORMED AND HE SHALL INCLUDE IN HIS BID A SUM TO COVER ALL COSTS OF ALL ITEMS NECESSARY TO PERFORM THE WORK AS SET FORTH IN THE PROPOSED CONTRACT DOCUMENTS. NO ALLOWANCE WILL BE MADE TO ANY BIDDER BECAUSE OF LACK OF SUCH EXAMINATION OR KNOWLEDGE. THE SUBMISSION OF A BID WILL BE CONSTRUED AS CONCLUSIVE EVIDENCE
THAT THE BIDDER HAS MADE SUCH EXAMINATION.
5. THE CONTRACTOR SHALL CAREFULLY STUDY AND COMPARE THE CONTRACT DOCUMENTS WITH EACH OTHER, WITH INFORMATION FURNISHED BY THE OWNER, WITH EXISTING CONDITIONS AND SHALL AT ONCE REPORT TO
THE ENGINEER ERRORS, INCONSISTENCIES, OR OMISSIONS DISCOVERED.
6. ALL WORK PERFORMED UNDER THIS CONTRACT SHALL COMPLY WITH THE CURRENT EDITION OF THE CALIFORNIA BUILDING CODE, UNIFORM PLUMBING CODE, CALIFORNIA ELECTRICAL CODE AND OTHER RELATED LOCAL CODES, ORDINANCES AND STATE STATUTES.
7. COORDINATION: COORDINATE VARIOUS CONSTRUCTION ACTIVITIES TO ASSURE EFFICIENT AND ORDERLY INSTALLATION OF EACH PART OF THE WORK. COORDINATE CONSTRUCTION OPERATIONS THAT ARE
DEPENDENT UPON EACH OTHER FOR PROPER INSTALLATION, CONNECTION AND OPERATION.
8. INSPECTION OF CONDITIONS: THE INSTALLER OF EACH COMPONENT SHALL INSPECT THE SUBSTRATE AND CONDITIONS UNDER WHICH WORK IS TO BE PERFORMED. DO NOT PROCEED UNTIL UNSATISFACTORY
CONDITIONS HAVE BEEN CORRECTED.
9. MANUFACTURER'S INSTRUCTIONS: COMPLY WITH MANUFACTURER'S INSTALLATION INSTRUCTIONS AND RECOMMENDATIONS, TO THE EXTENT THAT THEY ARE MORE STRINGENT THAN REQUIREMENTS CONTAINED IN
THE CONTRACT DOCUMENTS.
10. INSPECT MATERIAL AND EQUIPMENT IMMEDIATELY UPON DELIVERY AND AGAIN PRIOR TO INSTALLATION.
REJECT DAMAGED AND DEFECTIVE ITEMS.
11. PROVIDE ATTACHMENT AND CONNECTION DEVICES AND METHODS NECESSARY FOR SECURING WORK. SECURE
EACH WORK TRUE TO LINE AND LEVEL.
12. INSTALL EACH COMPONENT DURING WEATHER CONDITIONS AND PROJECT STATUS THAT WILL ENSURE THE BEST RESULTS. ISOLATE EACH PART FROM INCOMPATIBLE MATERIAL AS NECESSARY TO PREVENT
DETERIORATION.
13. CLEANING AND PROTECTION DURING HANDLING AND INSTALLATION: CLEAN AND PROTECT CONSTRUCTION IN PROGRESS AND ADJOINING MATERIALS IN PLACE. APPLY PROTECTIVE COVERING WHERE REQUIRED TO INSURE PROTECTION FROM DAMAGE OR DETERIORATION. CLEAN AND MAINTAIN COMPLETED CONSTRUCTION
AS OFTEN AS NECESSARY THROUGH THE CONSTRUCTION PERIOD.
14. LIMITING EXPOSURES: SUPERVISE CONSTRUCTION ACTIVITIES TO ENSURE THAT NO PART OF CONSTRUCTION, EXISTING, COMPLETED OR IN PROGRESS, IS SUBJECT TO HARMFUL OR DELETERIOUS EXPOSURE. SUCH
EXPOSURES INCLUDE:
· EXCESSIVE STATIC OR DYNAMIC LOADING
· EXCESSIVE WEATHERING
· EXCESSIVE HIGH OR LOW TEMPERATURES OR HUMIDITY
· AIR CONTAMINATION OR POLLUTION
· WATER OR ICE
· CHEMICALS OR SOLVENTS
· HEAVY TRAFFIC, SOILING, STAINING OR CORROSION
· UNUSUAL WEAR OR OTHER MISUSE
· CONTACT BETWEEN INCOMPATIBLE MATERIALS
· THEFT OR VANDALISM
15. APPLICABILITY OF STANDARDS: EXCEPT WHERE CONTRACT DOCUMENTS INCLUDE MORE STRINGENT REQUIREMENTS, APPLICABLE INDUSTRY STANDARDS HAVE THE SAME FORCE AND EFFECT AS IF BOUND OR COPIED INTO CONTRACT DOCUMENTS. SUCH STANDARDS ARE PART OF THE CONTRACT DOCUMENTS BY REFERENCE. WHERE COMPLIANCE WITH A STANDARD IS REQUIRED, COMPLY WITH STANDARD IN EFFECT AS
OF DATE OF CONTRACT DOCUMENTS.
16. CONFLICTING REQUIREMENTS: WHERE COMPLIANCE WITH TWO OR MORE STANDARDS THAT ESTABLISH DIFFERENT OR CONFLICTING REQUIREMENTS FOR MINIMUM QUANTITIES OR QUALITY LEVELS IS SPECIFIED, THE MOST STRINGENT REQUIREMENT WILL BE ENFORCED. REFER UNCERTAINTIES AS TO WHICH QUALITY LEVEL IS
MORE STRINGENT TO THE ARCHITECT FOR A DECISION BEFORE PROCEEDING.
17. CONTRACTOR RESPONSIBILITIES: PROVIDE INSPECTIONS AND TESTS SPECIFIED OR REQUIRED BY GOVERNING
AUTHORITIES, FOR YOUR PART OF THE WORK.
18. SOURCE LIMITATIONS: TO THE FULLEST EXTENT POSSIBLE, PROVIDE PRODUCTS OF THE SAME KIND, FROM A
SINGLE SOURCE.
STRUCTURAL
McELHANEY STRUCTURAL ENGINEERS, LLC
290 BRINKBY AVE. #205
RENO, NV 89509
P: (775) 853-5525 F: (775) 297-0739 E: Brett@mcelhaneystructural.com
STRUCTURAL
PROJECT TEAM
GENERAL
SCOPE OF WORK
VICINITY MAP
PRE-ENGINEERED METAL BUILDING FOUNDATION
G000 TITLE SHEET
MODOC METAL BUILDING FOUNDATION
REV. DATE DESCRIPTION BY
zspruell Text Box
BELOW GRADE BUILDING FOUNDATION SYSTEM TO BE CONSTRUCTED UNDER THIS CONTRACT.
zspruell Text Box 8R-CA-10000-X-121 - Page 1.0
DIVISION 01
GENERAL REQUIREMENTS
1. THE CONTRACTOR SHALL VERIFY ALL DIMENSIONS AND CONDITIONS PRIOR TO STARTING
CONSTRUCTION. THE ENGINEER SHALL BE NOTIFIED OF ANY DISCREPANCIES OR INCONSISTENCIES.
2. DO NOT SCALE THE DRAWINGS FOR WORKING DIMENSIONS.
3. NOTES AND DETAILS ON DRAWINGS SHALL TAKE PRECEDENCE OVER GENERAL NOTES AND TYPICAL
DETAILS. TYPICAL DETAILS SHALL APPLY TO THE PROJECT DRAWINGS EXCEPT WHEN SPECIFIC DETAILS
ARE SHOWN WHICH SHALL TAKE PRECEDENCE.
4. ALL WORK SHALL CONFORM TO THE MINIMUM STANDARDS OF THE FOLLOWING CODE: THE 2018 CALIFORNIA BUILDING CODE (CBC), ANY OTHER REGULATING AGENCIES WHICH HAVE AUTHORITY OVER
ANY PORTION OF THE WORK, AND THE CODES AND STANDARDS LISTED IN THESE NOTES AND
SPECIFICATIONS.
5. SEE ARCHITECTURAL DRAWINGS FOR THE FOLLOWING:
a. SIZE AND LOCATION OF WINDOW AND DOOR OPENINGS.
b. SIZE AND LOCATION OF CONCRETE CURBS, FLOOR DRAINS, AND DEPRESSED AREAS.
c. SIZE AND LOCATION OF FLOOR AND ROOF OPENINGS, EXCEPT AS SHOWN.
d. SIZE AND LOCATION OF INTERIOR AND EXTERIOR NON-BEARING PARTITIONS.
6. SEE MECHANICAL, PLUMBING, AND ELECTRICAL DRAWINGS FOR THE FOLLOWING:
a. ELECTRICAL CONDUIT RUNS, BOXES, OUTLETS IN WALLS, AND SIZE AND LOCATION OF
EQUIPMENT BASES.
b. PIPE RUNS, SLEEVES, HANGERS, TRENCHES, AND OPENINGS.
c. CONCRETE INSERTS OR FIXTURES.
7. CONTRACTOR SHALL INVESTIGATE SITE DURING CLEARING AND EARTH WORK OPERATIONS FOR FILLED EXCAVATIONS OR BURIED STRUCTURES SUCH AS CESSPOOLS, CISTERNS, FOUNDATIONS, ETC. IF ANY
SUCH STRUCTURES ARE FOUND, NOTIFY STRUCTURAL ENGINEER IMMEDIATELY.
8. THE CONTRACT STRUCTURAL DRAWINGS AND SPECIFICATIONS REPRESENT THE FINISHED STRUCTURE.
THEY DO NOT INDICATE THE METHOD OF CONSTRUCTION. THE CONTRACTOR SHALL PROVIDE ALL
MEASURES NECESSARY TO PROTECT THE STRUCTURE DURING CONSTRUCTION. SUCH MEASURES
SHALL INCLUDE, BUT NOT BE LIMITED TO, BRACING, SHORING FOR LOADS DUE TO CONSTRUCTION EQUIPMENT, ETC. OBSERVATION VISITS TO THE SITE BY THE STRUCTURAL ENGINEER SHALL NOT
INCLUDE INSPECTION OF THE ABOVE ITEMS.
9. OPENINGS, POCKETS, ETC. LARGER THAN 6 INCHES SHALL NOT BE PLACED IN SLABS, DECKS, BEAMS, JOISTS, COLUMNS, WALLS, ETC. UNLESS SPECIFICALLY DETAILED ON THE STRUCTURAL DRAWINGS.
NOTIFY THE STRUCTURAL ENGINEER WHEN DRAWINGS BY OTHERS SHOW OPENINGS, POCKETS, ETC.
NOT SHOWN ON THE STRUCTURAL DRAWINGS, BUT WHICH ARE LOCATED IN STRUCTURAL MEMBERS.
10. CONSTRUCTION MATERIALS SHALL BE SPREAD OUT IF PLACED ON FRAMED FLOORS OR ROOF. LOAD SHALL NOT EXCEED THE DESIGN LIVE LOAD PER SQUARE FOOT. PROVIDE ADEQUATE SHORING AND/OR
BRACING WHERE STRUCTURE HAS NOT ATTAINED DESIGN STRENGTH.
11. SHOP DRAWINGS SUBMITTED TO THE STRUCTURAL ENGINEER FOR REVIEW SHALL CONSIST OF THE
NUMBER OF SETS TO BE RETURNED PLUS ONE. SHOP DRAWING SUBMITTALS SHALL BE BOUND
COPIES.
12. ADHESIVE ANCHORS SHALL BE SIMPSON SET-XP EPOXY PER ICC ESR-2508 WITH ASTM A-36 THREADED ROD OR APPROVED EQUAL, U.N.O. EXPANSION ANCHORS SHALL BE SIMPSON STRONG-BOLT CARBON STEEL PER ICC ESR-1771, U.N.O. ADHESIVE OR EXPANSION ANCHORS SHALL NOT BE INSTALLED UNTIL
MASONRY OR CONCRETE HAS CURED TO DESIGN STRENGTH.
13. DESIGN LOADS:
PER METAL BUILDING MFR.
WIND DESIGN DATA:
1. ULTIMATE DESIGN WIND SPEED = 97 mph (3-SECOND GUST)
2. RISK CATEGORY II
3. WIND EXPOSURE C
4. INTERNAL PRESSURE COEFFICIENT = 0.18
EARTHQUAKE DESIGN DATA:
1. RISK CATEGORY II
2. Ie = 1.00
3. Ss = 0.545g, S1 = 0.216g
4. SITE CLASS: D
5. Sds = 0.495g, Sd1 = 0.311g
6. SEISMIC DESIGN CATEGORY: D
7. BASIC SEISMIC-FORCE-RESISTING SYSTEM(S):
= PER METAL BUILDING MFR.
8. DESIGN BASE SHEAR = PER METAL BUILDING MFR.
9. RESPONSE MODIFICATION COEFFICIENT(S), PER METAL BUILDING MFR.
10. ANALYSIS PROCEDURE USED: EQUIVALENT LATERAL FORCE
DIVISION 01
SUMMARY OF WORK
1. IT SHALL BE THE CONTRACTOR'S DIRECT RESPONSIBILITY TO COMPLY WITH TYPICAL DETAILS AND GENERAL NOTES AS DELINEATED OR DEFINED ON THE TYPICAL DETAIL DRAWINGS OF THESE CONTRACT DOCUMENTS REGARDLESS OF SPECIFIC FLAGGING OR REFERENCE TO APPLICABLE NOTE OR DETAIL.
2. IT SHALL BE THE CONTRACTOR'S RESPONSIBILITY TO COORDINATE WITH ALL TRADES REGARDING
UTILITIES PASSING THROUGH AND UNDER FOOTINGS. STRUCTURAL REQUIREMENTS FOR THESE
CONDITIONS ARE DELINEATED IN TYPICAL DETAILS.
3. TOP OF FOOTING ELEVATIONS NOTED ARE MINIMUM. SEE NOTE 2 FOR ADDITIONAL REQUIREMENTS.
4. CONTRACTOR SHALL VERIFY AND COORDINATE ALL LOCATIONS AND SIZES OF OPENINGS IN SLABS, SLAB
DEPRESSIONS, AND CURBS FOR ALL RELATED CONSTRUCTION PRIOR TO FLOOR LAYOUT OR
CONSTRUCTION. CONTRACTOR SHALL THEN USE APPROPRIATE DETAIL(S) OR WALL SECTION FOR EACH
APPLICABLE CONDITION.
5. CONTRACTOR SHALL VERIFY WITH APPROPRIATE SUB-CONTRACTORS THE EXACT LOCATION, WEIGHT, AND INTENDED METHOD OF ATTACHMENT OF ALL ITEMS TO BE SUSPENDED FROM OR IN ANY WAY ATTACHED
TO ANY ROOF FRAMING OR OTHER STRUCTURAL MEMBER UNLESS SUCH ITEM(S) ARE CLEARLY
ADDRESSED BY THE STRUCTURAL CONSTRUCTION DOCUMENTS. THIS INFORMATION SHALL BE
TRANSMITTED IN WRITING TO THE APPROPRIATE FRAMING MANUFACTURER VIA THE STRUCTURAL
ENGINEER PRIOR TO FINAL DESIGN OR FABRICATION OF STRUCTURAL FRAMING MEMBERS.
6. CONTRACTOR SHALL VERIFY ALL DIMENSIONS WITH ENGINEER PRIOR TO CONSTRUCTION.
7. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS AND DIMENSIONS AND NOTIFY THE STRUCTURAL
ENGINEER IN WRITING OF ANY DISCREPANCIES.
8. THE CONTRACTOR AND ALL SUB-CONTRACTORS HE/SHE INTENDS TO USE (INCLUDING AGENTS AND
SUPPLIERS) ARE AWARE OF AND ACKNOWLEDGE THAT CLOSE COORDINATION AMONG ARCHITECTURAL, MECHANICAL, PLUMBING, ELECTRICAL, AND STRUCTURAL DRAWINGS IS REQUIRED FOR THE FOLLOWING:
a. DETERMINATION OF ALL COLUMN LOCATIONS AND SIZES.
b. DETERMINATION OF TOP OF FLOOR, TOP OF STEEL, WALL PLATES, AND TOP OF BEAM ELEVATIONS.
c. VERIFICATION OF ALL DIMENSIONS.
d. VERIFICATION OF ALL TOP OF FOOTINGS.
9. THE CONTRACTOR AND ALL SUB-CONTRACTORS HE/SHE INTENDS TO USE (INCLUDING AGENTS AND SUPPLIERS) SHALL MAKE CONSIDERATION FOR AND INCLUDE MONIES FOR THE ABOVE, IN PREPARATION OF THEIR BIDS. THIS REQUIREMENT SHALL SUPERSEDE ANY CONTAINED IN THE AISC "MANUAL OF STEEL
CONSTRUCTION"
DIVISION 01
FOUNDATION PERFORMANCE REQUIREMENTS
1. FOUNDATION DESIGN BASED ON 2018 IBC TABLE 1806.2, SOIL CLASS 5. FOOTING DESIGN BASED ON ALLOWABLE SOIL BEARING PRESSURE OF 1500 psf DEAD PLUS LIVE LOADS AND 1995 psf TOTAL LOAD
(INCLUDING WIND OR SEISMIC).
2. THE CONTRACTOR SHALL PROVIDE FOR PROPER DE-WATERING OF EXCAVATIONS FROM SURFACE WATER, GROUND WATER, SEEPAGE, ETC.
3. THE CONTRACTOR SHALL PROVIDE FOR DESIGN AND INSTALLATION OF ALL CRIBBING, SHEATHING, AND
SHORING REQUIRED TO SAFELY AND ADEQUATELY RETAIN THE EARTH BANKS.
4. EXCAVATIONS FOR FOOTINGS SHALL BE APPROVED BY THE SOILS ENGINEER PRIOR TO PLACING THE CONCRETE AND REINFORCING. THE CONTRACTOR SHALL NOTIFY THE SOILS ENGINEER WHEN INSPECTION OF EXCAVATIONS ARE READY. THE SOILS ENGINEER SHALL SUBMIT A LETTER OF COMPLIANCE TO THE
OWNER.
5. ALL EXCAVATIONS SHALL BE PROPERLY BACKFILLED. DO NOT PLACE BACKFILL BEHIND RETAINING WALLS
BEFORE CONCRETE HAS ATTAINED FULL DESIGN STRENGTH. THE CONTRACTOR SHALL BRACE OR
PROTECT ALL BUILDING PIT WALLS BELOW GRADE FROM LATERAL LOADS UNTIL ATTACHING FLOORS ARE COMPLETELY IN PLACE AND HAVE ATTAINED FULL STRENGTH. THE CONTRACTOR SHALL PROVIDE FRO
DESIGN, PERMITS, AND INSTALLATION OF SUCH BRACING.
6. FOOTINGS SHALL BE PLACED AND ESTIMATED ACCORDING TO DEPTHS SHOWN ON DRAWINGS. SHOULD
SOIL ENCOUNTERED AT THESE DEPTHS NOT BE APPROVED BY THE SOILS ENGINEER, FOOTING
ELEVATIONS OR FOOTING DESIGN WILL BE ALTERED BY CHANGE ORDER.
7. FOOTING BACKFILL AND UTILITY TRENCH BACKFILL WITHIN BUILDING AREA SHALL BE MECHANICALLY COMPACTED IN LAYERS, TO THE APPROVAL OF THE SOILS ENGINEER. FLOODING WILL NOT BE PERMITTED.
8. ALL ABANDONED FOOTINGS, UTILITIES, ETC. THAT INTERFERE WITH NEW CONSTRUCTION SHALL BE
REMOVED.
DIVISION 03
CONCRETE
1. ALL PHASES OF WORK PERTAINING TO THE CONCRETE CONSTRUCTION SHALL CONFORM TO THE "BUILDING CODE REQUIREMENTS FOR REINFORCED CONCRETE", AMERICAN CONCRETE INSTITUTE 318 (ACI
318) AND THE "SPECIFICATIONS FOR STRUCTURAL CONCRETE FOR BUILDINGS" (ACI 301), LATEST APPROVED ADDITIONS, WITH MODIFICATIONS AS NOTED IN THE DRAWINGS OR SPECIFICATIONS.
2. REINFORCED CONCRETE DESIGN IS BY THE "ULTIMATE STRENGTH DESIGN METHOD."
3. CONCRETE MIXES SHALL BE DESIGNED BY A QUALIFIED TESTING LABORATORY AND APPROVED BY THE
STRUCTURAL ENGINEER. CALCIUM CHLORIDE SHALL NOT BE USED.
a. PROPOSED MIX DESIGNS SHALL BE NO MORE THAN ONE (1) YEAR OLD, AND HAVE AFFIXED
ON EACH SUBMITTED COPY THE ORIGINAL SEAL OF THE REVIEWING ENGINEER. THE REVIEWING
ENGINEER SHALL BE REGISTERED IN THE STATE OF NEVADA.
b. EACH DESIGN MIX SHALL INDICATE THE PROJECT NAME AND ADDRESS. THE CONTRACTOR
SHALL DESIGNATE THE LOCATION OF USE FOR EACH PROPOSED MIX DESIGN.
c. EACH MIX DESIGN SHALL INCLUDE THE SLUMP, BEFORE AND AFTER ADDING PLASTICIZER, AIR
ENTRAINMENT, TYPE OF AGGREGATE, TYPE OF CEMENT, AND ADMIXTURES TO BE USED.
4. SCHEDULE OF STRUCTURAL CONCRETE - 28 DAY STRENGTHS:
LOCATION IN STRUCTURE STRENGTH (psi) TYPE
1) FOOTINGS 3,000* NORMAL WT. 145 ± 5 pcf
2) SLABS 4,000* NORMAL WT. 145 ± 5 pcf
3) GRADE BEAMS 3,000* NORMAL WT. 145 ± 5 pcf
4) OTHER 3,000* NORMAL WT. 145 ± 5 pcf
PROVIDE 6%±1% AIR ENTRAINMENT IN EXTERIOR CONCRETE AND ANY CONCRETE EXPOSED TO FREEZING, U.N.O.
* SEE NOTE 5 BELOW, FOR CONCRETE IN CONTACT WITH SOIL.
5. PORTLAND CEMENT SHALL CONFORM TO ASTM C-150, TYPE II. VERIFY w/ SOILS ENGINEER; USE TYPE V CEMENT w/ MAX. WATER TO CEMENT RATIO 0.45 AND F'c = 4,500 psi FOR CONCRETE IN CONTACT w/ SOIL IF
DIRECTED BY THE SOILS ENGINEER.
a. PANELS: MIN. 5-1/2 SACK CEMENT CONTENT, PLACED AT 3" MAX. SLUMP.
b. SLABS ON GRADE: MIN. 5-1/2 SACK CEMENT CONTENT, PLACED AT 3" MAX. SLUMP.
c. FOOTINGS: MIN. 5-1/4 SACK PER CUBIC YARD CEMENT CONTENT, 4" MAX. SLUMP.
6. MAXIMUM WATER TO CEMENT RATIO SHALL BE AS FOLLOWS:
a. EXTERIOR SLABS AND ALL EXTERIOR CONCRETE: 0.45
b. INTERIOR SLABS: 0.54
7. AGGREGATE FOR NORMAL WEIGHT CONCRETE SHALL CONFORM TO ALL REQUIREMENTS AND TEST OF ASTM C-33 AND PROJECT SPECIFICATIONS. EXCEPTIONS MAY BE USED ONLY WITH PERMISSION FROM THE STRUCTURAL ENGINEER. MAXIMUM AGGREGATE SIZE SHALL CONFORM WITH THE FOLLOWING: 1/5 DISTANCE BETWEEN FORMS, 3/4 DISTANCE BETWEEN REINFORCING BARS, AND 1/3 THICKNESS OF SLAB.
8. CONCRETE MIXING OPERATIONS, ETC. SHALL CONFORM TO ASTM C-94.
9. PLACEMENT OF CONCRETE SHALL CONFORM TO ACI 318 REQUIREMENTS AND PROJECT SPECIFICATIONS.
SANDBLAST ALL CONCRETE SURFACES AGAINST WHICH CONCRETE IS TO BE PLACED.
10. IF COLUMNS AND WALLS ARE PLACED WITH FLOOR, TWO HOURS MUST ELAPSE BETWEEN THE END OF
COLUMN OR WALL POUR AND THE BEGINNING OF THE FLOOR POUR.
11. CLEAR COVERAGE OF CONCRETE OVER OUTER REINFORCING BARS SHALL BE AS FOLLOWS:
a. CONCRETE CAST AGAINST AND
PERMANENTLY EXPOSED TO EARTH 3"
b. CONCRETE EXPOSED TO WEATHER:
No. 6 THROUGH No. 18 BARS 2" No. 5 BAR, W31 OD D31 WIRE, AND SMALLER 1 1/2"
c. CONCRETE NOT EXPOSED TO WEATHER OR
IN CONTACT WITH GROUND:
No. 14 AND No. 18 BARS 1 1/2" No. 11 BARS AND SMALLER 3/4"
12. ALL REINFORCING BARS, ANCHOR BOLTS, AND OTHER CONCRETE INSERTS SHALL BE SECURED IN THEIR
FINAL POSITION PRIOR TO PLACING CONCRETE.
13. PROVIDE SLEEVES FOR PLUMBING AND ELECTRICAL OPENINGS IN CONCRETE BEFORE PLACEMENT. DO NOT CUT ANY REINFORCING WHICH MAY CONFLICT. CORING CONCRETE IS NOT PERMITTED, EXCEPT AS
SHOWN. NOTIFY THE STRUCTURAL ENGINEER IN ADVANCE OF CONDITIONS NOT SHOWN ON THE
DRAWINGS.
14. CONDUITS SHALL NOT BE RUN IN SLABS OR PLACED IN BASE MATERIAL. CONCENTRATED RUNS OF
CONDUITS OR PIPES SHALL BE AVOIDED, EXCEPT WHERE DETAILED OPENINGS ARE PROVIDED.
15. PROJECTING CORNERS OF BEAMS, WALLS, COLUMNS, ETC. SHALL BE FORMED WITH A 1/2" CHAMFER, UNLESS NOTED OTHERWISE ON ARCHITECTURAL DRAWINGS.
16. CURING COMPOUNDS USED ON CONCRETE THAT IS TO RECEIVE A RESILIENT TILE FINISH SHALL BE
APPROVED BY THE TILE MANUFACTURER BEFORE USE.
17. SHRINKAGE OF CONCRETE, WHEN TESTED IN ACCORDANCE WITH ASTM C-157, SHALL NOT EXCEED 0.00065 INCHES/INCH FOR HARD ROCK CONCRETE AND 0.00055 INCHES/INCH FOR LIGHT WEIGHT CONCRETE.
18. PLACE AND PROTECT CONCRETE IN COMPLIANCE WITH ACI 305 AND 306, RESPECTIVELY, DURING HOT AND
COLD EXPOSURE CONDITIONS.
DIVISION 03
REINFORCING STEEL
1. ALL REINFORCING STEEL SHALL BE DETAILED AND PLACED IN CONFORMANCE WITH THE "BUILDING CODE REQUIREMENTS FOR REINFORCED CONCRETE" (ACI 318, LATEST APPROVED EDITION), AND THE "MANUAL OF STANDARD PRACTICE FOR REINFORCED CONCRETE CONSTRUCTION" (LATEST EDITION), BY THE C.R.S.I.
AND THE W.C.R.S.I., AS MODIFIED BY THE PROJECT DRAWINGS AND SPECIFICATIONS.
2. DEFORMED REINFORCING BARS SHALL BE ASTM A-615 GRADE 60, EXCEPT TIES, STIRRUPS, SLAB DOWELS, AND REINFORCING BARS IN NON-STRUCTURAL CONCRETE SUCH AS, SLABS ON GRADE, WHICH MAY BE GRADE 40, UNLESS NOTED OTHERWISE. USE ASTM A-706 REINFORCING BARS THAT ARE REQUIRED TO BE
WELDED.
3. DEFORMED REINFORCING BARS FOR MOMENT FRAMES SHALL CONFORM TO THE 2012 INTERNATIONAL
BUILDING CODE (IBC), CHAPTER 19.
4. WELDING OF REINFORCING BARS SHALL BE WITH LOW HYDROGEN ELECTRODES IN CONFORMANCE WITH "RECOMMENDED PRACTICES FOR WELDING REINFORCING STEEL", AMERICAN WELDING SOCIETY, AWS-D1.4
(SEE SPECIFICATIONS).
5. ALL REINFORCING BARS BENDS SHALL BE MADE COLD.
6. WELDED WIRE FABRIC (WWF) SHALL CONFORM TO ASTM A-185.
7. MINIMUM LAP OF WELDED WIRE FABRIC SHALL BE 6" OR 1-1/2 FULL MESH, WHICH EVER IS GREATER.
8. REINFORCING SPLICES SHALL BE MADE ONLY WHERE INDICATED ON THE DRAWINGS.
9. DOWELS BETWEEN FOOTINGS AND WALLS OR COLUMNS SHALL BE THE SAME GRADE, SIZE, AND SPACING
OR NUMBER AS THE VERTICAL REINFORCING, RESPECTIVELY.
10. ALL BARS SHALL BE MARKED SO THEIR IDENTIFICATION CAN BE VERIFIED WHEN THE FINAL IN-PLACE
INSPECTION IS PERFORMED.
11. THE CONTRACTOR SHALL PROVIDE FOR AN ALLOWANCE OF TWO TONS OF REINFORCING BARS TO BE
FURNISHED, FABRICATED, AND PLACED DURING PROGRESS OF WORK AS MAY BE DIRECTED BY THE
STRUCTURAL ENGINEER, IN ADDITION TO ALL STEEL INDICATED ON THE DRAWINGS.
12. SEE TYPICAL DETAILS FOR REINFORCEMENT SPLICES IN CONCRETE. SPLICE ALL REINFORCING BARS 2'-6"
MINIMUM, U.N.O.
13. ALL REINFORCING BARS SHALL BE TIED IN PLACE BEFORE CONCRETE OR GROUT.
14. DO NOT SPLICE REINFORCING STEEL IN THE MIDDLE THIRD OF WALLS.
DIVISION 01
SPECIAL INSPECTION AND DEFERRED SUBMITTALS
1. SPECIAL INSPECTIONS SHALL BE IN COMPLIANCE WITH IBC SECTION 1704.
2. AT THE USFWS'S DISCRETION, OPTION AND/OR OPTION B NOTED BELOW WOULD BE NEED:
OPTION A: THE CONTRACTOR SHALL ENGAGE AND SUBCONTRACT WITH A QUAILIFIED TESTING AGENCY TO PERFORM TESTS AND INSPECTIONS AND PROVIDE A QUALITY ASSURANCE AND QUALITY CONTROL PROGRAM QA-QCP AS NOTED IN IBC SECTION 1705, 1706, 1707, AND 1708. THE CONTRACTOR'S TESTING
AGENCY UNDER SUBCONTRACT SHALL WORK WITH THE ENGINEER OF RECORD IN DEVELOPING A
QAULITY ASSURANCE AND QUALITY CONTROL PLAN.
OPTION B: THE OWNER (USFWS) SHALL CONTRACT WITH A QUALIFIED TESTING AGENCY TO PERFORM TESTS AND INSPECTIONS AND PROVIDE QUALITY ASSURANCE AND QUALITY CONTROL PROGRAM QA- QCP AS NOTEDIBC SECTION 1705, 1706, 1707, AND 1708. THE TESING AGENCY SHALL WORK WITH THE
ENGINEER OF RECORD IN DEVELOPING A QAULITY ASSURANCE AND QUALITY CONTROL PLAN
3. THE USFWS WOULD ELECT TO EITHER CHOOSE OPTIONA, OPTION B OR BOTH IN COMBINATION.
4. STATEMENT OF SPECIAL INSPECTION PER IBC SECTION 1705.
4. STRUCTURAL OBSERVATIONS. THE OWNER (USFWS) SHALL EMPLOY THE ENGINEER OR ARCHITECT RESPONSIBLE FOR THIS STRUCTURAL DESIGN, OR ANOTHER ENGINEER OR ARCHITECT DESIGNATED BY THE ENGINEER OR ARCHITECT RESPONSIBLE FOR THE STRUCTURAL DESIGN, TO PERFORM STRUCTURAL OBSERVATION AS DEFINED IN SECTION 202. THE USFWS WILL EITHER REQUEST THE CONSTRUCTION
CONTRACTOR ENGAGE AND SUBCONTRACT WITH A STRUCTURAL OBSERVER OR THE USFWS WILL
CONTRACT WITH A STRUCTURAL OBSERVER. OBSERVED DEFICIENCIES SHALL BE REPORTED IN WRITING TO THE OWNER'S (USFWS) REPRESENTATIVE, SPECIAL INSPECTOR, CONTRACTOR & THE BUILDING OFFICIAL. THE STRUCTURAL OBSERVER SHALL SUBMIT TO THE BUILDING OFFICIAL A WRITTEN STATEMENT THAT THE SITE VISITS HAVE BEEN MADE & IDENTIFYING ANY REPORTED DEFICIENCIES THAT, TO THE BEST
OF THE STRUCTURAL OBSERVER'S KNOWLEDGE, HAVE NOT BEEN RESOLVED. STRUCTURAL
OBSERVATIONS SHALL BE PERFORMED AT THE FOLLOWING STAGES OF CONSTRUCTION PRIOR TO
PLACEMENT OF CONCRETE:
a. N/A STRUCTURAL OBSERVATION DOES NOT WAIVE NOR REPLACE RESPONSIBILITY FOR THE INSPECTIONS REQUIRED OF THE BUILDING INSPECTOR OR THE DEPUTY INSPECTOR. STRUCTURAL OBSERVATION IS NOT
INSPECTION. IT IS FAMILIARIZATION WITH THE PROGRESS AND QUALITY OF THE WORK AND
CLARIFICATION OF THE DOCUMENTS AND GENERAL CONFORMANCE TO DESIGN INTENT. SEE "INSPECTION NOTES" FOR INSPECTION CRITERIA AND NOTE THAT CONTINUOUS SPECIAL INSPECTION PERFORMED BY A QUALIFIED DEPUTY IS REQUIRED FOR ALL PRIMARY STRUCTURAL ELEMENTS, ETC. THE CONTRACTOR AND INSPECTOR WILL ASSURE THAT CERTIFIED RECORD OF CONTINUOUS SPECIAL INSPECTION OF THE WORK TO BE OBSERVED IS MADE AVAILABLE TO THE OBSERVER BEFORE REQUESTING OBSERVATION.
THE STRUCTURAL OBSERVER SHALL PERFORM SITE VISITS AT THOSE STEPS IN THE PROGRESS OF THE
WORK THAT ALLOW FOR CORRECTION OF DEFICIENCIES WITHOUT SUBSTANTIAL EFFORT OR
UNCOVERING OF THE WORK INVOLVED.
5. DEFERRED SUBMITTALS. THE FOLLOWING DEFERRED SUBMITTALS SHALL FIRST BE SUBMITTED TO THE
PROJECT ENGINEER OF RECORD/ARCHITECT FOR REVIEW AND COORDINATION. FOLLOWING THE
COMPLETION OF THE REVIEW AND COORDINATION BY THE ENGINEER OF RECORD/ARCHITECT, A
SUBMITTAL WOULD THEN BE MADE TO THE CITY BUILDING DEPARTMENT FOR REVIEW AND APPROVAL. THE SUBMITTAL WILL INCLUDE A LETTER STATING THAT THIS REVIEW AND COORDINATION IS COMPLETED AND
PLANS AND CALCULATIONS FOR THE DEFERRED ITEMS ARE FOUND TO BE ACCEPTABLE WITH NO
EXCEPTIONS.
a. N/A
CONTINUOUS PERIODIC
CONCRETE
1. INSPECTION OF REINFORCING STEEL, INCLUDING PLACEMENT. X-
2. INSPECT BOLTS TO BE INSTALLED IN CONCRETE PRIOR TO AND DURING
PLACEMENT OF CONCRETE WHERE ALLOWABLE LOADS HAVE BEEN
INCREASED.
-X
3. VERIFY USE OF REQUIRED DESIGN MIX. X-
4. AT THE TIME FRESH CONCRETE IS SAMPLED TO FABRICATE SPECIMENS FOR
STRENGTH TEST, SLUMP AND IR CONTENT TESTS, AND DETERMINE THE
TEMPERATURE OF THE CONCRETE. -X
5. INSPECTION OF CONCRETE PLACEMENT FOR PROPER APPLICATION
TECHNIQUES.
-X
6. INSPECTION FOR MAINTENANCE OF SPECIFIED CURING TEMPERATURE
AND TECHNIQUES.
X-
7. INSPECT FORMWORK FOR SHAPE, LOCATION, AND THE DIMENSIONS
OF THE CONCRETE MEMBER BEING FORMED.
X-
FOUNDATION LEGEND
CFX.X
EDGE OF SLAB
CONT. FOOTING
SEE SCHEDULE FOR SIZE & REINFORCEMENT
CFX.X
CONT. FOOTING
SEE SCHEDULE FOR SIZE & REINFORCEMENT
FX.X PAD FOOTING,
SEE SCHEDULE FOR SIZE & REINFORCEMENT
T.O. FOOTING ELEVATION (B.F.F.), IF PROVIDED-2'-0"
DRAWN CHECKED DATE DRAWING NO.DESIGNED
OFSHEET
VERIFY SCALE
THIS BAR IS ONE INCH
ON ORIGINAL DRAWING
ADJUST SCALES
ACCORDINGLY, IF NOT
ONE INCH ON THIS
SHEET
0" 1"
VME BAM 05/24/2021
S001
VME
MODOC
GENERAL NOTES
5364 COUNTY ROAD 115
ALTURAS, CA 96101
SUBSETSHTNO
2 4
MODOC METAL BUILDING
REV. DATE DESCRIPTION BY
1 7/30/21 PLAN REVIEW XX
zspruell
8R-CA-10000-X-121 - Page 2.0
P E
R L
O C
A L C
O D
E
M
IN
M
IN
FINISH GRADE
FOOTING, PER PLAN
(MAY VARY)
FIRM, UNDISTURBED
NATIVE SOIL
REFERENCE FOUNDATION
NOTES ON SHEET S001 FOR ALL SOIL
AND FOUNDATION REQUIREMENTS
SLOPE AWAY
FROM BUILDING
FOOTING, PER PLAN
(MAY VARY)
CONTRACTOR SHALL LOCATE
BOTTOM OF FOOTING ELEVATION
TO AVOID SURCHARGING
EXISTING SUBGRADE UTILITIES
FINISH GRADE
BOTTOM OF FOOTING ELEVATION
EXISTING UTILITY, SEE CIVIL
DRAWINGS FOR SIZE AND
LOCATION
10'-0" MIN.
1' - 6" MIN.
EXCAVATION
TRENCH
SEE GENERAL NOTES AND SOILS REPORT,
FOR BACKFILL REQUIREMENTS, TYP.
FINISH GRADE
FOOTING, PER PLAN
(MAY VARY)
BOTTOM OF TRENCH
EXCAVATION SHALL NOT
EXTEND BELOW THIS LINE
NOTE:
THE CONTRACTOR SHALL COORDINATE ALL
EXCAVATION OPERATIONS WITH BUILDING
FOUNDATION REQUIREMENTS.
D d d
D
D
4" M
IN.
6d
90° STD. HOOK 180° STD. HOOK 135° STD. HOOK MAX. OFFSET BEND
PRINCIPAL REINFORCING
STIRRUPS AND TIES
NOTES:
1. ALL BENDS SHALL BE MADE COLD.
2. #14 AND #18 BARS SHALL BE BEND TESTED
AND LAB APPROVED PRIOR TO BENDING.
D = 6d FOR #3 TO #8 D = 8d FOR #9 TO #11 D = 10d FOR #14 AND #18
MIN. D = 1 1/2" FOR #3
MIN. D = 2" FOR #4
MIN. D = 2 1/2" FOR #5
MIN. D = 4 1/2" FOR #6
MIN. D = 5 1/4" FOR #7
MIN. D = 6" FOR #8
d
4" MIN.
6d
D
M
IN
d4" MIN.
6d
D = 6 BAR DIA. FOR #3 TO #8
D = 8 BAR DIA. FOR #9 TO #11
STANDARD HOOKS
BAR OFFSET
TIES AND STIRRUPS
4" M
IN
.6d
D D
M
IN
d
6" MIN.
12d
4" M
IN
.6d d
D
135°
90° 90°
135°
MIN. LAP LENGTH AT SPLICES (f'c = 3000 psi MIN. NORMAL WEIGHT CONCRETE)
SIZE OF REINF.
CONCRETE
CMU - SINGLE CURTAIN OF REINFORCEMENT
TYPICAL
w/ SPLICE AT
MID SPAN OR HEIGHT
CMU - DOUBLE CURTAIN OF REINFORCEMENT
TYPICAL
w/ SPLICE AT
MID SPAN OR HEIGHT
#3 #4 #5 #6 #7 #8 #9 #10 #11
22" 29" 36" 43" 63" 72" 81" 91" 112"
18" 24" 30" 36" 42" 48" - - -
27" 36" 45" 54" 63" 72" - - -
24" 31" 39" 47" 55" 63" - - -
35" 47" 59" 70" 82" 94" - - -
NOTES:
1. USE FOR SINGLE CURTAIN OR DOUBLE CURTAIN REINFORCEMENT
w/ SPLICES STAGGERED 24"
2. USE FOR (2) OR MORE BARS SPACED 3" OR CLOSER TOGETHER.
IF SPLICES ARE STAGGERED, USE SINGLE CURATIN LAP LENGTHS.
3. INCREASE 20% FOR BUNDLED BARS.
4. NOT FOR USE WITH EPOXY COATED BARS.
5. INCREASE 30% FOR TOP BARS (HORIZONTAL BARS NOT IN WALLS)
PLACED WITH MORE THAN 12" OF FRESH CONCRETE BELOW.
4" M
IN
.6d d d d
'-0
9" . 9"
D + 1'-6"
D OF SLEEVE
w/ STANDARD HOOKS @ 14" O.C.
SLEEVES, MIN. 1" CLR.
ALL AROUND PIPES, CONDUIT,
DUCTS, ETC.
EXTEND FOOTING
AROUND THE
SLEEVES(S)
FOOTING
PIPES THROUGH
STEMWALL
FOR PIPES IN THIS AREA,
STEP FOOTING SO THAT
PIPE PASSES THROUGH
STEMWALL
NOTES:
1. FOR PIPES 3'-0" OR LESS BELOW BOTTOM OF
FOOTINGS, PROVIDE SLEEVE AND CONCRETE
AS SHOWN. GREATER THAN 3'-0" USE STEPPED
FOOTING TO STAY WITHIN 3'-0" LIMIT.
ADD #5 BARS
DRAWN CHECKED DATE DRAWING NO.DESIGNED
OFSHEET
VERIFY SCALE
THIS BAR IS ONE INCH
ON ORIGINAL DRAWING
ADJUST SCALES
ACCORDINGLY, IF NOT
ONE INCH ON THIS
SHEET
0" 1"
VME BAM 05/24/2021
S002
VME
MODOC
GENERAL FOUNDATION DETAILS
5364 COUNTY ROAD 115
ALTURAS, CA 96101
SUBSETSHTNO
3 4
MODOC METAL BUILDING
3/4" = 1'-0"
1 TYPICAL SOIL PREPARATION
3/4" = 1'-0"
2 FOOTING PARALLEL TO EXISTING UTILITY
3/4" = 1'-0"
3 EXCAVATION PARALLEL TO FOOTING
3/4" = 1'-0"
4 BAR ENDS
3/4" = 1'-0"
6 REBAR CONFIGURE AND LAPS
3/4" = 1'-0"
TYP. PIPES AND SLEEVES THROUGH
STEMWALLS
REV. DATE DESCRIPTION BY
zspruell
8R-CA-10000-X-121 - Page 3.0
A
B
2 3 4 5
P1 P1 P1 P1
P1P1P1
X -B
R A
C
IN
G
F4.0
F4.0 F6.5 F6.5 F6.5
F4.0
F4.0 F6.5 F6.5F6.5
X -B
R A
C
IN
G
X-BRACING
PORTAL FRAME
F4.0F4.0
P1
P1P1
P1
P1
CF1.0
S101
S101
S101
FOUNDATION NOTES
1. VERIFY ALL DIMENSIONS AND LOADING WITH METAL BUILDING DRAWINGS PRIOR TO
CONSTRUCTION.
2. VERIFY SIZE AND LOCATION OF ANCHOR BOLTS WITH METAL BUILDING MANUFACTURER.
3. SEE GENERAL NOTES FOR ADDITIONAL INFORMATION.
ANCHOR BOLTS:
1. ANCHOR BOLTS SHALL BE ASTM F1554 GR. 36 THREADED ROD WITH AN MINIMUM EMBED OF 18"
PROVIDE 3"x3"x 1/4" PLATE WASHER WITH DOUBLE NUTS AT BOLT EMBEDMENT TYP. U.N.O.
2. ANCHOR BOLT DIAMETER, PER METAL BUILDING MANUFACTURER. CONTRACTOR TO COORDINATE
WITH MTL. BLDG. ANCHOR BOLT LAYOUT AND ANCHOR BOLT SIZES.
GENERAL NOTES
1. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS AND DIMENSIONS PRIOR TO
CONSTRUCTION.
2. IT SHALL BE THE CONTRACTORS DIRECT RESPONSIBILITY TO COMPLY WITH TYPICAL
DETAILS AND GENERAL NOTES AS DELINEATED OR DEFINED ON THE TYPICAL DETAIL
DRAWINGS OF THESE CONTRACT DOCUMENTS REGARDLESS OF SPECIFIC FLAGGING
OR REFERENCE TO APPLICABLE NOTE OR DETAIL.
3. IT SHALL BE THE CONTRACTORS RESPONSIBILITY TO COORDINATE WITH ALL TRADES
REGARDING UTILITIES PASSING THROUGH AND UNDER FOOTINGS. STRUCTURAL
REQUIREMENTS FOR THESE CONDITIONS ARE DELINEATED IN THE TYPICAL DETAILS.
4. CONTRACTOR SHALL VERIFY AND COORDINATE ALL LOCATIONS AND SIZES OF
OPENINGS IN SLAB, SLAB DEPRESSIONS, AND CURBS FOR ALL RELATED
CONSTRUCTION PRIOR TO SLAB LAYOUT OR CONSTRUCTION. CONTRACTOR SHALL
THEN USE APPROPRIATE WALL SECTION FOR EACH APPLICABLE CONDITION.
5. DRAWINGS ARE DIAGRAMMATIC IN NATURE AND ARE NOT INTENDED TO INDICATE
EVERY OPENING OR PENETRATION IN SLAB OR OTHER STRUCTURE.
FOOTING SCHEDULE
MARK SIZE REINFORCEMENT
F4.0 48" x 48" x 12" (4) #5 EA WAY T&B
F6.5 78" x 78" x 12" (6) #5 EA WAY T&B
REMARKS
CF1.0 12" WIDE x 18" x CONT. (2) #4 CONT. T&B
PEDESTAL SCHEDULE
MARK SIZE REINFORCEMENT
P1 24"x24" (8) #6 VERT., #4 TIES @ 8" O.C.
REMARKS
T Y
P
C L R
PER PLAN
REINF. PER FOOTING
SCHEDULE
COLUMNS AND BASE PLATE
PER METAL BUILDING MFR.
(2) #4 TIES AT 1 1/2" O.C. AT TOP
VERIFY ANCHOR BOLT PLACEMENT
w/ METAL BUILDING MFR.
(2) #4 HAT BARS EA. ANCHOR
BOLT GROUP w/ STD. HOOK AT
BOTTOM OF FTG.
BLDG. MFR.
PER MTL.
PLATE WASHER w/ DBL. NUT
PER PLAN
ANCHOR BOLTS PER METAL
BUILDING MFR.P
E R
P L A
N
E M
B E
D M
E N
T
F.G.
#3 TIES
NOTE: LOCATE HAT BARS ADJACENT ANCHOR
BOLTS
2 1/2"
M
IN
F.G.
NOTE:
ADJUST COLUMN PEDESTAL ELEVATION
FOR LEVELNESS PER SITE TOPOGRAPHY
M A
X
M
IN
PER PLAN
BASE ANGLE BY MFR. w/ 1/4" ⌀ x 2
3/4" TITEN SCREWS @ 48" O.C.
P E
R P
L A
N
CONT. FTG. WHERE OCCURS
REINF. NOT SHOWN FOR CLARITY
T Y
P
C L R
PER PLAN
REINF. PER FOOTING SCHEDULE
COLUMNS AND BASE PLATE
PER METAL BUILDING MFR.
(2) #4 TIES AT 1 1/2" O.C. AT TOP
VERIFY ANCHOR BOLT PLACEMENT
w/ METAL BUILDING MFR.
(2) #4 HAT BARS EA. ANCHOR
BOLT GROUP w/ STD. HOOK AT
BOTTOM OF FTG.
BLDG. MFR.
PER MTL.
PLATE WASHER w/ DBL. NUT PER PLAN
ANCHOR BOLTS PER METAL
BUILDING MFR.
F.G.
#3 TIES
NOTE: LOCATE HAT BARS ADJACENT ANCHOR
BOLTS
2 1/2"
M
IN
F.G.
NOTE:
ADJUST COLUMN PEDESTAL ELEVATION
FOR LEVELNESS PER SITE TOPOGRAPHY
M A
X
M
IN
PER PLAN
BASE ANGLE BY MFR. w/ 1/4" ⌀ x 2
3/4" TITEN SCREWS @ 48" O.C.
P E
R P
L A
N
CONT. FTG. WHERE OCCURS
REINF. NOT SHOWN FOR CLARITY
P E
R P
L A
N
E M
B E
D M
E N
T
SEE PLAN
M
IN
M
IN
F.G.
REINF. PER PLAN
CONT. THRU
PEDESTALS
#3 TIES @ 48" O.C.
OMIT AT PEDESTALS
TYP.
3" CLR.
BASE ANGLE BY MFR. w/ 1/4" ⌀ x 2
3/4" TITEN SCREWS @ 48" O.C.
DRAWN CHECKED DATE DRAWING NO.DESIGNED
OFSHEET
VERIFY SCALE
THIS BAR IS ONE INCH
ON ORIGINAL DRAWING
ADJUST SCALES
ACCORDINGLY, IF NOT
ONE INCH ON THIS
SHEET
0" 1"
VME BAM 05/24/2021
S101
VME
MODOC
FOUNDATION PLAN
5364 COUNTY ROAD 115
ALTURAS, CA 96101
SUBSETSHTNO
4 4
MODOC METAL BUILDING
1/8" = 1'-0"
1 FOUNDATION PLAN
2 FOUNDATION ISO
REV. DATE DESCRIPTION BY
1 7/30/21 PLAN REVIEW XX
3/4" = 1'-0"
4 4' FTG. AT COLUMNS
3/4" = 1'-0"
5 6'-6" FTG. AT COLUMNS
3/4" = 1'-0"
3 CONT. FTG. SECTION
zspruell Text Box 8R-CA-10000-X-121 - Page 4.0 zspruell
Continuous Perimeter Footing / Stem Wall shall be constructed and installed at a Final Height Above Ground Level of 6-Inches. To allow for placement and compaction of a layer of gravel within the structure footprint.
| Sheets |
| G000 - TITLE SHEET |
| S001 - GENERAL NOTES |
| S002 - GENERAL FOUNDATION DETAILS |
| S101 - FOUNDATION PLAN |
File details come from the government source that posted it. Updated .