Proposal Schedule
| MODOC NATIONAL WILDLIFE REFUGE |
| CONSTRUCT AND INSTALL NEW REINFORCED CONCRETE |
| FOUNDATION SYSTEM. |
| QUOTE SCHEDULE |
| INSTRUCTIONS: |
| The Offeror shall edit this quote Schedule and may provide a detailed breakdown of their |
| quote (including support documentation) and all associated line item pricing. It is the |
| responsibility of the Offeror to ensure all requirements are met and all support documentation |
| is provided. The purpose of the quoteSchedule Document is to organize Base Bid Tasks |
| and Optional Tasks for U.S. Fish and Wildlife Service Price Evaluation. Contractor |
| shall show pricing for items. Failure to provide pricing for all items may result in quote not being |
| considered for award. |
Construction Services - Base and Option Tasks:
TASK
(Base or
| Option) | Description | Amount |
| 1 | ||
| (Base) | Field Verification Site Visit. Review of Existing Site Features and Existing Site Conditions. Document Review, Planning, Development, Preparation, and Submittal of Project Documents. |
To include but not be limited to:
Incidentals.
All Associated Electronic and Hard Copy Deliverables.
| 2 | |
| (Base) | Mobilization and De-Mobilization. |
To include but not be limited to:
Incidentals.
All Associated Electronic and Hard Copy Deliverables.
| 3 | |
| (Base) | Perform Special Inspections and Tests for the Full Duration of On-Site Work Activities and as part of the Contractor's Quality Assurance and Quality Control Program and Plan (QA-QCPP). |
Specifically, the Contractor shall engage and subcontract with a Qualified Testing Agency to perform Tests and Inspections and provide a Quality Assurance and Quality Control Program and Plan (QA-QCPP). As noted in IBC Section 1705, 1706, 1707, and 1708. The Contractor’s Testing Agency under subcontract shall work with the Engineer of Record in developing a Quality Assurance and Quality Control Plan.
To include but not be limited to:
Laboratory, Shop, and Field Inspections and Test Reports for:
- International Building Code - Special Inspections and Tests as defined in relevant IBC Chapters.
- Rebar Inspections and Inspection Reports for Rebar Size, Spacing, Quantity, and Placement in the Formwork.
- Anchor Bolts, Anchor Rods, Bolts, Nuts, and Washers Inspections and Inspection Reports for Size, Spacing, Quantity, and Placement in the Formwork.
- Concrete Cylinder Compressive Strength Tests and Test Results at the 7-Day and 28-Day Cure Times.
- Incidentals.
- All Associated Electronic and Hard Copy Deliverables.
| 4 | |
| (Base) | Construct and Install Reinforced Concrete Foundation System. |
To include but not be limited to:
Incidentals.
All Associated Electronic and Hard Copy Deliverables.
| A | |
| (Option) | Structural Observation Services. |
Specifically, the Contractor shall engage and subcontract with a Professional Engineer or Registered Architect for Structural Observation Services and at the USFWS's Option.
To include but not be limited to:
Incidentals.
All Associated Electronic and Hard Copy Deliverables.
| 5 | |
| (Base) | All Other Necessary Work for a Complete and Operable Project In Accordance With All The Requirements of the PE's Stamped and Signed Bid Documents (Drawings and Specifications) and Contractor's Manufacturer's Design Drawings and Specifications. |
| B | |
| (Option) | Placement and Compaction of Approximate 6-Inch Thick Layer of Base Course Aggregate Driving Surface Material. |
To include but not be limited to:
Incidentals.
All Associated Electronic and Hard Copy Deliverables.
| Total (Base Tasks 1, 2, 3, 4, and 5). | $0.00 |
| Total (Base Tasks 1, 2, 3, 4, 5 plus Option Task A and B) | $0.00 |
| The Offeror may provide a detailed breakdown of their bid and all associated line item pricing. |
| The above quote Schedule Description column is not intended to be comprehensive. |
| It is the responsiblilty of the Offeror to ensure all requirements are met. |
| As part of the quote Schedule, and at the Offeror's discretion, Prepare and |
| Submit Back-Up Documents for the quote Schedule including Number of Labor Categories, |
| Labor Rates, Number of Labor Hours, Material Quantities, Equipment Quantities, |
| Equipment Rates, and Required Tools. Include All Items Required and Anticipated |
| to successfully deliver the Project. |
| As the Contractor is preparing their quote, Material Quantities require Contractor assumptions. |
| The Contractor may submit their assumptions about Material Quantities as part of their Offer. |
| Whether the Contractor chooses to submit their assumptions about Material Quantities to USFWS |
| for review and as part of their Offer is at the discretion of the Contractor. |
Incomplete Bids Will Not Be Considered.
Name of Respondent and Company:
Address (Include Zip Code):
SAM UEI Number