4. Supplemental Specifications.pdf
PDF 435 KB Posted
- Solicitation number
- 127EAW24R0003
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is a Supplemental Specification for the construction of a federal timber structure contract. It outlines the detailed requirements for furnishing, fabricating, erecting, and painting structural timber, including all required yard lumber and hardware.
The key details include: material requirements and compliance certifications, construction specifications for treated and untreated timber, workmanship and hardware requirements, and measurement and payment terms. Specific requirements are provided for items such as timber framing, bracing, stringers, decking, trusses, drains, and painting. This supplemental specification would be included as part of a larger federal contract opportunity for the Fern Fall Trail Bridge Replacement project on the Plumas National Forest, with an estimated construction value between $100,000 and $250,000 under a total small business set-aside.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI Official Responses - 1.pdf | ||
| A00001 - RFI Responses.pdf | ||
| 1. Statement of Work.pdf | ||
| 5. Fire Plan.pdf | ||
| 127EAW24R0003 Fern Fall Trail Bridge Replacement.pdf | ||
| 2. Schedule.docx | DOCX document | |
| 7. RFI Form.docx | DOCX document | |
| 3. Project Drawings.pdf | ||
| 6. Davis-Bacon Act WD # CA20240007.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table of Contents
Table of Contents
Preface
101 - Terms, Format, and Definitions
101.01 Meaning of Terms
101.03 Abbreviations
101.04 Definitions
102 - Bid, Award, and Execution of Contract
102 Bid, Award, and Execution of Contract
103 - Scope of Work
Deletions
104 - Control of Work
Deletions
104.06 Use of Roads by Contractor
105 - Control of Material
105.02 Material Sources
105.02(a) Government-provided sources
105.05 Use of Material Found in the Work
106 - Acceptance of Work
106.01 Conformity with Contract Requirements…………………………………………..… 15
106.07 Delete
107 - Legal Relations and Responsibility to the Public
107.05 Responsibility for Damage Claims
107.06 Contractor’s Responsibility for Work
107.09 Legal Relationship of the Parties
107.10 Environmental Protection
107.02 Protection and Restoration of Property and Landscape
108 - Prosecution and Progress
108 Delete
109 - Measurement and Payment
109 Deletions
109.02 Measurement Terms and Definitions
152 - Construction Survey and Staking
152.02 General
Table 152-1 Tolerances for reestablishing P-line, traverse, and elevations
Table 152-2 Cross section and slope stake tolerances
154 - Contractor Sampling and Testing
155 - Schedules for Construction Contracts
155 Delete
157 - Soil Erosion Control
157.03 General
208 - Structure Excavation and Backfill for Selected Major Structures
208.04 General
557 - Timber Structures
625 - Turf Establishment
625.03 General
625.04 Preparing Seedbed
625.05 Watering
625.06 Fertilizing
625.07 Seeding
625.08 Mulching
625.09 Protecting and Caring for Seeded Areas
625.11 Measurement
714 - Geotextile and Geocomposite Drain Material……………………………………………………………. … 43
714.03 Geogrids…………………………………………………………………………………………………………. ….. 43
Preface
Preface_wo_03_15_2004_m
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-003 for construction of
National Forest System Roads.
101 - Terms, Format, and Definitions
101.00_nat_us_07_25_2005
101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association
Mine Safety and Health Administration
National Institute of Standards and Technology
National Electrical Safety Code
West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
mp Milepost ppm Part Per Million
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
http://www.nist.gov/
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition
Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or
“design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96
Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S.
Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the
Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36
CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract
102.00_nat_us_02_16_2005
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work
103.00_nat_us_02_16_2005
Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work
104.00_nat_us_06_16_2006
Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a) Government-provided sources.
Add the following:
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work
106.01_nat_us_07_31_2007
106.01 Conformity with Contract Requirements.
Delete Subsection 106.01 and substitute the following:
Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.
References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.
Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.
Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.
Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.
When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.
The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the Government tests work, copies of test reports are furnished to the Contractor upon request. Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the
Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.
Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections
106.02 to 106.05 inclusive. The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.
Remove and replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted, at no cost to the Government.
(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:
(1) Sampling method;
(2) Number of samples;
(3) Sample transport;
(4) Test procedures;
(5) Testing laboratories;
(6) Reporting;
(7) Estimated time and costs; and
(8) Validation process.
If the evaluation requires additional sampling or testing be performed, mutually agree with the
Government on witnessing procedures and on sampling and testing by a third party laboratory.
Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.
The CO will review the proposed resolution protocol and may modify it before final approval and execution.
The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol. If the validity of the
Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.
(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:
(1) Have the work accepted at a reduced price; or
(2) Be given permission to perform corrective measures to bring the work into conformity.
The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.
106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public
107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
• Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
• Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
• Exact time and location of spill including a description of the area involved.
• Containment procedures.
• Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
• Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
107.10_05_us_05_04_2007
107.02 Protection and Restoration of Property and Landscape
Meet the requirements chapters 10, 11, and 12.2 in their entirety of “Water Quality Management for National Forest System Lands in California Best Management Practices” dated September
108 - Prosecution and Progress
108.00_nat_us_02_16_2005
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment
109.00_nat_us_02_17_2005
109 Deletions
Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
152 - Construction Survey and Staking
152.00_nat_us_08_05_2005
Description
152.01(c) Material.
Use required stake dimensions and materials. Pre-paint the top 2 inches of all stakes and lath, or mark them with plastic flagging. Use designated colors for paint or flagging. Mark all stakes with a stake pencil that leaves a legible imprint, or with waterproof ink.
Do not use aerosol spray paints.
Use moisture-resistant paper for survey notes. Keep notes in books with covers that will protect the contents and retain the pages in numerical sequence.
Construction Requirements
152.02 General.
Delete the first two sentences.
Add the following:
When indicated on the plans, a preliminary survey line has been established on the ground. The project location line is established by offsets from this preliminary line.
Delete second sentence in second paragraph and replace with the following:
Reestablish missing reference, control lines, or stakes as necessary to control subsequent construction staking operations
152.03 Survey and Staking Requirements.
(b) Roadway cross-sections.
Replace the first two sentences with the following:
Take roadway cross-sections normal to centerline. When the centerline curve radius is less than or equal to 200 feet, take cross-sections at a maximum centerline spacing of 25 feet. When the centerline curve radius is greater that 200 feet take cross-sections at a maximum centerline spacing of 80 feet.
c) Slope Stakes & References:
Replace section with the following:
Slope stakes and references. When required, locate slope stakes on designated portions of the road. Locate the slope stake catch points and use them to establish clearing limits and slope stake references.
Mark slope stakes with the station, the amount of cut or fill, the horizontal distance to centerline, and the slope ratios.
Place slope reference stakes at least 10 feet outside the clearing limit and mark with the offset distance to the slope stake. Place sight stakes when required.
Prior to clearing and grubbing operations, move the slope stake outside the clearing limit to the slope reference stake. After clearing and grubbing and before excavation, reset the slope stakes in their original position.
Use the designated method to establish the slope stake catchpoint.
• Method I—Computed Method. Use the template information shown in the plans or other
Government-provided data to calculate the actual location of the catchpoint. The slope stake “catchpoint distance” provided may be used as a trial location to initiate slope staking. Recatch slope stakes on any section that does not match the staking report within the tolerances established in Table 152-2.
• Method II—Catchpoint Measurement Method. Determine the location of slope stake catchpoints by measuring the catchpoint distances shown in the plans or other
Government-provided data.
(d) Clearing and grubbing limits.
Add the following:
Establish clearing limits on each side of the location line by measuring the required horizontal or slope distances shown in the stake notes. Mark the clearing limits with flagging or tags on trees to be left standing, or on lath. Make markings intervisible, and no more than 90 feet apart.
After establishing clearing limits, move the location line stake outside the clearing limits for station identification purposes, and mark it with horizontal distance to location line
(e) Centerline reestablishment.
Replace with the following:
Reestablish centerline from instrument control points. The maximum spacing between centerline points is 25 feet when the centerline curve radius is less than or equal to 200 feet. When the centerline curve radius is greater than 200 feet, the maximum distance between centerline points is 80 feet.
(g) Culverts.
Replace subsection with the following:
Set culvert reference stakes at all culvert locations. Set a culvert reference stake on the centerline of the culvert 10 feet from each end or beyond the clearing limit, whichever is greater. Record the following on culvert reference stakes:
(1) Diameter, actual field measured length, and type of culvert.
(2) The vertical and horizontal distance from the reference stake to the invert at the ends of the culvert.
(3) Station of actual point where culvert intersects centerline.
When required, stake headwall for culverts by setting a hub with a guard stake on each side of the culvert on line with the face of the headwall. Perform this work after clearing is completed.
152.03 (l) Miscellaneous Survey and Staking.
(11) Cattleguards
(12) Drain Dips
(13) Erosion Control Measures
Replace Table 152-1 with the following two tables:
Table 152-1 Tolerances for reestablishing P-line, traverse, and elevations.
Precision
Class
Minimum
Position
Closure Angular Accuracy (±)
L-Line Tangent
Control Pointsa
Vertical Closureb
A
(Bridges) 1/10,000
2 sets, direct/reverse
10 second rejection limit
N/A
0.02 ft or
0.02ft/1000ftc
B 1/5,000
2 sets, direct/reverse
20 second rejection limit
0.1 ft
0.02 ft or
0.02ft/1000ftc
C 1/1,000 1 set, direct/reverse
1 minute rejection limit
0.2 ft 0.5ft/1000ftc
D 1/300
Foresight and backsight; 15 minute rejection limitc
0.4 ft 1.0ft/1000ftc
E 1/100
Foresight and backsight; 30 minute rejection limitc
0.8 ft 1.0ft/1000ftc
a. Accuracy of offset measurement.
b. Determine vertical closures at intervals not to exceed 2000 ft as measured along centerline.
c. Use greater value.
Table 152-2 Cross section and slope stake tolerances.
Item Tolerances
A B C D E
Allowable deviation of cross-section line projection from a true perpendicular to tangents, a true bisector of angle points, or a true radius of curves
(±)2o (±)3o (±)3o (±)5o (±)5o
Take cross-sections topography measurements so that variations in ground from a straight line connecting the cross-section points will not exceed
0.5 ft 1.0 ft 2.0 ft 2.0 ft 3.0 ft
Horizontal and vertical accuracy for cross-sections, in feet or percentage of horizontal distance measured from traverse line, whichever is greater.
0.1 ft or
0.4%
0.15 ft or 0.6%
0.2 ft or
1.0%
0.2 ft or
1.0%
0.3 ft or
1.0%
Horizontal and vertical accuracy for slope stake, slope stake references, and clearing limits. In feet or percentage of horizontal distance measured from centerline or reference stake, whichever is greater.
Slope reference stakes and slope stakes. 0.1 ft or
0.4%
0.15 ft or 0.6%
0.2 ft or
1.0%
0.2 ft or
1.0%
0.3 ft or
1.0%
Clearing limits 1.0 ft 1.0 ft 1.0 ft 1.5 ft 2.5 ft
154 - Contractor Sampling and Testing
154.01_nat_us_05_24_2005
154.01 Description
Delete the last sentence of the first paragraph.
155 - Schedules for Construction Contracts
155.00_nat_us_05_11_2004
155 Delete.
Delete Section 155 in its entirety.
157 - Soil Erosion Control
157.03_nat_us_02_24_2005
157.03 General
Delete the entire subsection and replace with the following:
Prior to the start of construction, submit a written plan that provides permanent and temporary erosion control measures to minimize erosion and sedimentation during and after construction.
Do not begin work until the necessary controls for that particular phase of work have been implemented. Do not modify the type, size, or location of any control. An alternate erosion control plan with all necessary permits may be submitted 30 days before intended use.
Incorporate all permanent erosion control features into the project at the earliest practicable time, as outlined in the approved plan.
When erosion control measures are not functioning as intended, immediately take corrective action.
208 - Structure Excavation and Backfill for Selected Major Structures
208.04_nat_us_08_05_2009
Construction Requirements
208.04 General.
Add the following to the end of the second sentence of the third paragraph:
"... to the CO a minimum of 5 days prior to beginning excavation work."
Add the following to the end of the third sentence of the third paragraph:
"...to the CO a minimum of 15 days prior to installation."
208.09 Foundation Preparation.
Add the following after the first paragraph:
The foundation elevation is defined as the bottom of footings, for spread footing placement; the bottom of the pile cap, for construction of pile foundations; and the toe of the wall, for construction of retaining walls, except wingwalls at bridges.
Replace all material from any over-excavation below the designated footing elevation with concrete, compacted gravel, or foundation fill at the direction of the CO.
When boulders or irregular, fractured, or seamed bedrock precludes excavation to the designated footing elevation without further loosening of previously solid material, the CO may order removal of such loose material and allow payment for concrete, gravel, or structural backfill that is required to restore foundation material to the designated elevation
208.13 Measurement.
Add the following to the second paragraph:
(f) Material excavated to construct end walls or wing walls which lie outside the excavation limits specified above.
Add the following paragraph:
Foundation over-excavation and the resulting replacement material will not be measured for payment unless the CO determines the over-excavation was unavoidable because of the nature of the material.
Replace FP-03 Section 557 with the following Supplemental Specification:
Section 557—Timber Structures
Description
557.01 Work. Furnish, fabricate, erect, and paint structural timber, including all required yard lumber and hardware.
Materials
557.02 Requirements. Furnish material that conforms to specifications in the following section and subsections:
Hardware & Structural Steel ............................................... 716.02
Painting ............................................................................… 563
Structural Glued Laminated Timber .................................... 716.04
Treated Structural Timber & Lumber .................................. 716.03
Treated Timber Piles .......................................................… 715.02
Untreated Structural Timber & Lumber ..........................… 716.01
Furnish the following compliance certificates to the CO upon delivery of the materials to the jobsite:
(a) Verification of compliance with grading rules and species of timber and lumber. Provide certification by an agency accepted as competent by the American Lumber Standards
Committee (ALSC).
(b) Lot certification of each charge for preservative, penetration in inches, and retention in pounds per cubic foot (assay method) by a qualified independent inspection and testing agency. In addition, have the producer of the treated products provide written certification that Best Management Practices (BMP’s) in accordance with “Best
Management Practices for Treated Wood in Western Aquatic Environments,” published by the Western Wood Preservation Institute (WWPI) and Canadian Institute of Treated
Wood, were followed, including a description and appropriate documentation of the applicable BMP’s used.
(c) Certification from a qualified inspection and testing agency indicating that all glued laminated members are in accordance with the requirements of American National
Standard for Wood Products, “Structural Glued Laminated Timber” (ANSI/AITC
A190.1), modified as SHOWN ON THE DRAWINGS.
(d) Such other certifications as SHOWN ON THE DRAWINGS.
Incise all glued laminated and solid sawn members thicker than 2 inches in accordance with AWPA standard C1, unless otherwise SHOWN ON THE DRAWINGS.
Provide shop drawings for all timber 21 days in advance of fabrication when SHOWN ON THE
DRAWING. Show all dimensions and fabrication details for all cut, framed, or bored timbers.
Construction
557.03 General. Perform the work under Section 208. Furnish structural lumber and timber of the required stress grade.
Clear stacks of weeds, rubbish, or other objectionable material from the ground under and in the vicinity of all stored material. Place the bottom layer of material at least 8 inches above the ground level. Provide sufficient support to prevent sagging.
Open-stack untreated material to shed water. Stack material in layers on spacers (stickers) that extend across the full width of the stack to allow for free air circulation. Align all stickers vertically and space them at regular intervals.
Close-stack treated material to shed water.
Protect material from the weather. If covered, use sheet material such as water-resistant paper or opaque polyethylene film. Do not cover with impervious membranes, such as polyethylene film, during dry weather. Slit individual wrappings full length or puncture on the lower side to permit drainage of water.
Store and protect glued laminated timber in accordance with the recommendations for
Loading and Handling, Job Site Storage, and Erection in “Recommended Practice for Protection of Structural Glued Laminated Timber During Transit, Storage, and Erection,” published by the
American Institute of Timber Construction, AITC 111.
Use slings or other devices to protect corners of heavy construction timbers and banded packages of lighter construction timber.
557.04 Treated Timber. Fabricate timbers before treatment. Handle treated timber according to the Consumer Information Sheet published by AWPA. Do not cut, frame, or bore treated timber after treatment unless approved by the CO. Handle treated timbers carefully and do not drop, damage outer fibers, or penetrate the surface with tools. Do not use cant dogs, hooks, or pike poles. In coastal waters, do not cut or bore timber below the high water mark.
For timbers originally treated with pentachlorophenol, creosote, creosote solutions, or waterborne preservatives, field treat all cuts, abrasions, bolt holes, and recesses that occur after treatment with two liberal applications of a compatible preservative in accordance with the requirements specified in AWPA standard M4, Standard for the Care of Pressure-Treated Wood
Products.
Unless otherwise specified, copper naphthenate solutions may be used for field treatments of material originally treated with copper naphthenate, pentachlorophenol, creosote, creosote solution, or waterborne preservatives. Prepare the preservative solution by blending copper naphthenate preservative that meets P8 requirements with a solvent conforming to AWPA standard P9. Ensure that the resulting preservative solution concentration contains a minimum of 2 percent copper metal.
Plug all unused holes with preservative-treated plugs. Perform all field-applied preservative treatment with necessary precautions so as to prevent any soil and/or water contamination.
557.05 Untreated Timber. Coat the following untreated timber surfaces in accordance with
AWPA standard M4:
(a) All ends and tops, and all contact surfaces of posts, sills, and caps.
(b) All ends, joints, and contact surfaces of bracing and truss members.
(c) All surfaces of timber bumpers and the back faces of bulkheads.
(d) All other timber that will be in contact with earth.
557.06 Workmanship. Cut and form all lumber and construction timber so all joints will have even bearing over the entire contact surface. Do not use shims in making joints. Construct all joints to be closed. Drive nails and spikes to set the heads flush with the wood surface. Use the same end, face, and edge of the timber member for all layout dimensions. Bore all holes from mating faces.
557.07 Holes for Bolts, Dowels, Rods, & Lag Screws. Bore all holes before preservative treating the wood. Bore holes for round drift bolts and dowels 1/16 inch smaller in diameter than that of the bolt or dowel to be used. Ensure that the diameter of holes for square drift bolts or dowels is equal to the side dimension of the bolt or dowel.
Bore holes for machine bolts with a bit 1/16 inch larger than the diameter, except when galvanized bolts are specified. In this case, drill all holes 1/8 inch greater than the bolt size. Bore holes for lag screws with a bit not larger than the body of the screw at the base of the thread. Drill the depth of lag screw bolt holes 1 inch less than the length under the screw head and with a diameter approximately 75 percent of the shank diameter.
557.08 Hardware. Furnish the hardware as SHOWN ON THE DRAWINGS, as specified below.
(a) Bolts & Washers. Finally tighten all nuts to provide proper bearing, and cut off excess bolt lengths of more than 1 inch. After final tightening, check or burr all bolts effectively with a pointing tool to prevent loosening of the nuts.
Use malleable iron washers with a diameter approximately three times the bolt diameter under all bolt heads or nuts in contact with wood. Use cast-iron washers when the timber is in contact with the ground. Use square washers only when SHOWN ON THE DRAWINGS or with the approval of the CO.
(b) Galvanizing. Unless otherwise SHOWN ON THE DRAWINGS, ensure that all hardware for timber structures is galvanized, except for the glued laminated deck panel dowels.
Ensure that all fasteners, including nails, spikes, bolts, washers, and timber connectors, other than malleable iron, are galvanized.
557.09 Countersinking. Countersink nuts and bolt heads where SHOWN ON THE
DRAWINGS. Paint recesses formed for countersinking with an approved preservative, except in railing. After bolts or screws are in place, fill the holes with hot pitch or other approved filler.
557.10 Framing. Do not slab or trim treated piles for fitting sway or sash braces. Fill all gaps that occur between braces and piles with treated blocks so that the bracing is securely fastened to the piles.
557.11 Framing Bents. Bed mud sills firmly, evenly, and level to solid bearing, and tamp in place.
When concrete is cast and dowels are used for anchoring sills and posts, install dowels (3/4 inch minimum diameter) that project at least 6 inches above the tops of the pedestals. Carefully finish concrete pedestals supporting framed bents so that sills or posts bear evenly on the pedestals.
Provide firm, uniform bedding for mud sills. Make sills bear true and even on mud sills, piles, or pedestals. Drift bolt sills with bolts that extend into the mud sills or piles for at least 6 inches. Where possible, remove all earth in contact with sills for circulation of air around the sills.
557.12 Posts. Fasten posts to pedestals with dowels not less than 3/4 inch in diameter that extend at least 6 inches into the posts, or with other types of connectors as
SHOWN ON THE DRAWINGS. Fasten posts to sills using one of the following methods, as
SHOWN ON THE DRAWINGS:
(a) With dowels not less than 3/4 inch in diameter that extend at least 6 inches into posts and sills.
(b) With drift bolts not less than 3/4 inch in diameter driven diagonally through the base of the post and extending at least 7 inches into the sill. Drive drift bolts into holes at a 45° angle to enter the post at least 6 inches above the post base.
(c) With other types of connectors as SHOWN ON THE DRAWINGS.
557.13 Pile Bents. Treat, furnish, and drive piles in accordance with Section 551.
557.14 Caps for All Bents. Make timber caps bear even and uniform over the tops of the supporting posts or piles, with their ends in alignment. Secure all caps with drift bolts and set approximately at the center of and extending into the posts or piles at least 9 inches.
557.15 Bracing. Bolt the ends of bracing through the pile, post, cap, or sill. Brace intermediate intersections with posts or piles with bolts or spikes, as required. In all cases, use galvanized spikes in addition to bolts.
Make all bracing bear firmly against the pile or cap to which it is bolted. Provide and place shims as necessary to prevent bending the bracing more than 1 inch out of line when bracing bolts are tightened.
Where the space between the bracing and cap or pile is less than 1 inch, shims need not be used.
Where the space between the bracing and the cap or pile is 1 1/2 ± 3/8 inch, place two ogee washers, with their narrow faces together, or other approved washers on each bolt that passes through the space.
Where the space between the bracing and the cap or pile is over 2 inches, use wooden shims of the proper thickness. Fabricate the wooden shims from White Oak or from other approved hardwood. Do not use built-up wooden shims. Make wooden shims from a single piece of lumber with the width not less than 4 inches, and the length not less than the width of the bracing measured along the cap or pile. Do not adze, trim, or cut any treated member to avoid the use of shims.
557.16 Stringers. Place solid sawn stringers in position so that knots near edges are in the top portions of the stringers.
Outside stringers may have butt joints with the ends cut on a taper. Lap interior stringers to take bearing over the full width of the floor beam or cap at each end. Separate the lapped ends of untreated stringers by at least 1/2 inch for air circulation. Securely fasten the lapped ends with drift bolts, as required. Stagger the joints where stringers are two panels in length.
Install cross-bridging between stringers as SHOWN ON THE DRAWINGS. If timber cross-bridging members are used, cut for a full bearing at each end against the sides of the stringers.
Place cross-bridging at the center of each span or as SHOWN ON THE
DRAWINGS.
557.17 Plank Floors. Use plank that is surfaced on four sides (S4S).
Single-ply timber floors consist of a single thickness of planks supported on stringers. Lay the planks heart side down with 1/4 inch space between them for seasoned material, and with tight joints for unseasoned material. Spike each plank securely to each stringer. Carefully grade the planks as to thickness and lay so that no two adjacent planks vary in thickness by more than
1/16 inch.
Two-ply timber floors consist of two layers of flooring supported on stringers. Pressure treat the lower layer with creosote oil or with another preservative as SHOWN ON THE DRAWINGS.
Lay the top layer either diagonal or parallel to the centerline of roadway as required. Securely fasten each floor piece to the lower layer. Stagger joints at least 3 feet. Where the top layer is placed parallel to the centerline of the roadway, use special care to securely fasten the ends of the flooring. Bevel the ends of top layer members at each end of the structure.
557.18 Transversely Nail-Laminated Decks. Use 2 inch nominal thickness laminations; surface one edge hit or miss 1/8 inch scant (SIE–H or M 1/8 inch scant), and one side hit or miss 1/8 inch scant (SIS–H or M 1/8 inch scant).
Place the laminations on edge and at right angles to the centerline of the roadway. Spike each piece to the preceding piece at each end and at approximately 18-inch intervals, with the galvanized spikes driven alternately near the top and bottom edges. Use spikes of sufficient length to pass through two pieces and at least halfway through the third piece.
Where timber stringers are used, toenail every other piece to every other stringer. Use the size spikes specified. When steel stringers are used, securely attach the pieces using approved galvanized metal clips.
Use pieces of sufficient length to bear on at least four stringers. Do not splice pieces between stringers. Space end joints on any one stringer no closer than every third piece. Space end joints in adjoining pieces no closer than every second stringer.
557.19 Glued Laminated Panel Decks. Do not drag or skid panels. When lifted, support panels in the weak-moment plane at a sufficient number of points to avoid overstressing, and protect the edges from damage.
When dowels are SHOWN ON THE DRAWINGS between deck panels, use a template or drilling jig to ensure that dowel holes are accurately spaced and drilled parallel to one another and to the horizontal surfaces of the panel. Drill holes to a depth 1/4 inch greater than one-half the dowel length, and of a diameter that is 1/16 inch greater than the dowel, unless otherwise SHOWN ON THE DRAWINGS. Use a temporary dowel as a check for snug fit prior to production drilling. Use dowels of the size SHOWN ON THE
DRAWINGS, with the tips slightly tapered or rounded. Use an approved lubricant to facilitate the connection process.
Start the tips of all dowels partially and equally into the holes of the two panels being joined.
Draw the panels together keeping the edges parallel, until the panels abut tightly. Securely fasten each panel to each stringer as SHOWN ON THE DRAWINGS.
Assemble and match-mark panels prior to delivery to the construction site when SHOWN ON
THE DRAWINGS. Follow erection procedures given in FPL–263, Forest Service, Forest
Products Laboratory (FPL), Madison, Wisconsin.
557.20 Wheel Guards & Railings. Surface (S4S) wheel guards, rails, and posts. Place wheel guards in sections not less than 12 feet in length. Squarely butt joint all rails at posts.
557.21 Trusses. Fabricate trusses to show no irregularities of line when completed. Fabricate chords straight and true from end to end in horizontal projection. In vertical projection, fabricate chords to a smooth chorded curve through panel points conforming to the correct camber. Do not make uneven or rough cuts at the points of bearing.
557.22 Drains. Hot-dip galvanize drains, including anchorages, after fabrication.
557.23 Painting. Paint in accordance with Section 563.
Measurement
557.24 Method. Use the method of measurement that is DESIGNATED IN THE SCHEDULE
OF ITEMS.
Measure untreated and treated structural timber and lumber by the thousand feet board measure
(MFBM) of lumber and timber in place in the completed structure. Compute the quantities from nominal dimensions and actual lengths, except for transversely naillaminated decks. Measure transversely nail-laminated decks in place after dressing.
Measure timber piles under Subsection 551.
Measure timber bridge rail under Subsection 556.
Payment
557.25 The accepted quantities will be paid at the contract price per unit of measurement for the
Section 557 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
625 - Turf Establishment
625.03_nat_us_07_02_2007
625.03 General.
Delete this subsection and replace with the following:
Apply turf establishment to prepared ground or any disturbed area between (September 30, 2015) and (October 30, 2015 ). Apply turf establishment to the areas shown on the plans or worklists within 10 days after completion of ground disturbing activities. Unless otherwise specified in writing by the CO apply turf establishment after each NA foot section of road has been constructed to template lines. Seeded areas damaged by construction activities shall be reseeded within 10 days of the damage. Do not seed during windy weather or when the ground is excessively wet, frozen, or snow covered.
Assure that all seed and mulch used in the work conforms to the weed free requirements of
Section 713.
625.04 Preparing Seedbed.
Delete entire subsection and replace with the following:
Ensure that the surface soil is in a roughened condition favorable for germination and growth.
625.05 Watering
Delete entire subsection.
625.06 Fertilizing.
Delete entire subsection and replace with the following:
Apply fertilizer having a chemical analysis as listed below by the following methods.
(a) Dry Method. Apply the fertilizer with approved mechanical equipment. Hand operated methods are satisfactory on areas inaccessible to mechanical equipment.
(b) Hydraulic method. Use hydraulic-type equipment capable of providing a uniform application using water as the carrying agent. Add fertilizer to the slurry and mix before adding seed. Add the tracer material when designated by the CO.
Fertilizer. Apply fertilizer at the rate of NA pounds per acre. Insure that the fertilizer meets the following chemical analysis:
Nutrient Percent
Nitrogen, N . . . . . . . . . . . . . NA
Phosphorus, P205 . . . . . . . . . NA
Potassium, K . . . . . . . . . . . . . NA
625.07 Seeding.
Delete the first sentence and add the following.
Apply seed mix by the following methods:
(a) Dry method. Delete the third sentence.
Add the following after subsection (b).
Seed Mix. Furnish and apply the following kinds and amounts of pure live seed:
Quantity of Pure
Type of Seed Live Seed (Lbs/Acre)
1. Blue Wildrye- Elymus glaucus_______ ½ acre
2. California brome- Bromus carinatus var. carinatus ½ acre
Total __1 acre________________
Determine the pounds of seed to be furnished per acre by dividing the pounds of pure live seed required per acre by the product of the percent purity and percent germination.
625.08 Mulching.
Delete the entire subsection and replace with the following:
Apply Mulch within NA hours after seeding by the following methods.
(a) Dry Method. Apply mulch with a hand spreader or a spreader utilizing forced air at a rate of NA pounds per acre. Anchor the mulch with an approved stabilizing emulsion tackifier at a rate of NA gallons per acre. Do not mark or deface structure, pavements, utilities, or plant growth with tackifier.
(b) Hydraulic Method. Apply mulch in a separate application from the seed using hydraulic-type equipment according to Subsection 625.07(b).
Apply wood fiber or grass straw cellulose fiber mulch at a rate of NA pounds per acre.
Apply bonded fiber matrix hydraulic mulch at a minimum rate of NA pounds per acre.
Apply so no hole in the matrix is greater than 0.04 inches. Apply so that no gaps exist between the matrix and the soil.
Inaccessible areas may be mulched by hand. Apply mulch uniformly over the entire disturbed area.
625.09 Protecting and Caring for Seeded Areas
Delete the first sentence and add the following:
Protect and care for seeded areas until final acceptance.
625.11 Measurement.
Delete the entire Subsection and replace with the following:
Measure the Section 625 items listed in the bid schedule according to Subsection 109.02.
714 - Geotextile and Geocomposite Drain Material 714.03_nat_us_02_25_2005
Tables 714-1 and 714-4.
Add the following note to both tables:
(4) Woven slit film will not be allowed.
714.03 Geogrids.
Furnish geogrids consisting of polymeric materials such as polypropylene, polyethylene, or polyester formed into a stable network of bars or straps fixed at their junctions such that the bars retain their relative position to each other.
Elevate and protect rolls with a waterproof cover if stored outdoors.
(a) Physical requirements. Furnish geogrid treated to resist ultraviolet degradation, and conforming to the physical strength requirements shown in table 714-7 according to ASTM D 4595 for the specified geogrid category. Strength values shown in table 714-7 represent minimum average roll values and are for the direction of primary reinforcement. Ensure that the aperture size for all geogrids is between ¾ to 3 inches.
(b) Evaluation procedures. Geogrids will be evaluated under Subsection 106.03. Furnish a certification and a sample of the geogrid.
Table 714-7—Physical strength requirements for geogrids.
Category Minimum Ultimate Strength at Breakage (lbs/ft)
1 890
2 1985
3 2875
4 4110
5 5475
6 8215