About this file

This Performance Work Statement outlines requirements for hydrostatic testing and recharging of fire extinguisher cylinders for the Naval Station Norfolk Regional Maintenance Center (MARMC). The work involves testing and recharging 81 CO2 portable cylinders (15lb), 14 AFFF portable cylinders (2.5lb), and 36 CO2 50lb cylinders with actuators.

The vendor must perform hydrostatic testing, recharging, and valve rebuilding services across 10 Contract Line Item Numbers (CLINs), including 1,398 units of CO2 gas and environmental disposal of chemical/battery waste. The procedures require Ship Force (S/F) personnel to discharge and deliver the cylinders to the vendor's facility with proper documentation and Maintenance Requirement Cards. The vendor must provide QA documentation, notify the ship of any failed tests, mark failed items as UNSAT or OOC, and inform when items are ready for pickup. MARMC does not have internal capability for these services, necessitating use of an outside vendor.

View the file

Other files for this federal contract opportunity

Other files attached to Hydrostatic Testing and Recharge of CO2 Bottles, newest first.
File Type Posted
Attachment 1 - Clauses and Provisions.pdf PDF
Attachment 3 - Performance Work Statement.pdf PDF
Attachment 2 - Clauses and Provisions to be signed .pdf PDF
4.03b - Attachment 2 - Clauses and Provisions to be signed.pdf PDF
4.03a - Attachment 1 - Clauses and Provisions.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Work Statement 15LB C02 Bottle, 2.5lb AFFF bottle and 50LB C02 Bottle Hydrostatic Testing and Refill

Ref: (a) COMFLTFORCOMINST 4790.3, (Series), Joint Fleet Maintenance Manual (JFMM) VOL VI, CH 9.

(b) MIP Series: 6641 MRC: A3 C4TC Y Periodicity: M-9R and MIP Series: 5553 MRC: 83 6RWX N Periodicity: S-3

1. Purpose: To submit eighty one (81) CO2 portable cylinders, fourteen (14) AFFF portable cylinders and thirty six

(36) CO2 50lb cylinders for hydrostatic testing and recharge in accordance with references (a) through (b). To perform hydrostatic test and recharge of eighty one (81) CO2 portable cylinders, fourteen (14) AFFF portable cylinders and thirty six (36) CO2 50lb cylinders Actuators.

2. Background: Naval Station Norfolk Regional Maintenance Center (MARMC) does not have the capability to hydrostatic test or refill CO2 cylinders or actuators. In accordance with reference (b), Ship Force (S/F) shall deliver their CO2/AFFF bottles and actuators to an outside entity for testing. Vendor shall have the capability to conduct hydrostatic testing and recharge of CO2 and AFFF cylinders and actuators.

3. Items: The following outlines cylinder hydrostatic testing and recharge of CO2.

CLIN 0001: (Qty: 36) HYDRO TEST CO2 EXTINGUISHER 50-100LB

CLIN 0002: (Qty: 36) RECHARGE CO2 50LB STORED PRESSURE EXTINGUISHER

CLIN 0003: (Qty: 36) ½’’ VALVE REBUILD KITS

CLIN 0004 (Qty: 81) HYDRO TEST CO2 EXTINGUISHER 2.5-26LB

CLIN 0005: (Qty: 81) RECHARGE CO2 15LB STORED PRESSURE EXTINGUISHER

CLIN 0006: (Qty: 95) SERVICE MATERIALS FOR FIRE EXTINGUISHER

CLIN 0007: (Qty:1398) CO2 GAS

CLIN 0008 (Qty: 14) HYDRO TEST FFFP FOAM EXTINGUISHER 2.5LB

CLIN 0009 (Qty: 14) ENVIRONMENTAL DISPOSAL CHEMICAL/BATTERY WASTE

CLIN 0010 (Qty: 2) LABOR EXTINGUISHER REPAIR REGULAR HOURS

4. Procedures: The following outlines the procedures and responsibilities to accomplish testing and setting requirements.

A. S/F personnel shall perform the following:

(1) S/F shall discharge C02/AFFF Cylinder and Actuators in preparation of hydrostatic testing and deliver them to vendor’s facility with a Ship to Shore tag and all documents in accordance with reference (b).

(2) S/F shall ensure Maintenance Requirement Card (MRC)’s and all applicable technical information are provided to vendor when CO2/AFFF Cylinder and Actuators are dropped off at vendor’s facility.

(3) Once completed, S/F shall return to pick up CO2/AFFF Cylinders and Actuators and ensure the correct Ship to shore tags are attached.

B. Vendor shall perform the following:

(1) Receive all Cylinders and Actuators, with attached technical documents and sign the Ship to Shop tag.

(2) Perform the applicable hydrostatic testing and recharge of CO2 and AFFF Cylinders and Actuators in accordance with the applicable MRC’s.

(3) Provide QA documentation reflecting satisfactory testing.

(4) In the event CO2/AFFF Cylinder or Actuator fails, vendor shall inform the ship and wait for further instructions. If issue cannot be corrected, vendor shall return the item clearly marked as UNSAT or

OOC.

(5) Inform the ship when CO2/AFFF Cylinders/Actuators are ready to be picked up.