4-Cost Worksheet Exhibit B.xlsx
XLSX spreadsheet 11 KB Posted
- Attached to
- Fire Alarm System Replacement & Upgrade
- Solicitation number
- 26-04042DM
- Issued by
- Utah
About this file
This is a cost worksheet exhibit for a fire alarm system bid submitted to the Utah Transit Authority (UTA) for the systematic replacement and upgrade of conventional zoned fire alarm systems with fully addressable systems across multiple UTA campuses. The worksheet provides a standardized template for bidders to submit comprehensive pricing for fire alarm system installation projects across administrative buildings, maintenance facilities, transit centers, operations centers, warehouses, and support structures throughout Utah.
The cost worksheet is structured in seven sections to capture all project expenses: equipment and materials (including fire alarm control panels, detectors, notification devices, wiring, and hardware); labor costs across multiple categories including project management, fire alarm technicians, electricians, helpers, and programming and commissioning staff; engineering and design fees for system design, shop drawings, and permit drawings; permits and inspection fees from the Fire Department and AHJ; testing and certification costs; and additional costs such as equipment rental, mobilization, and training. Bidders are required to provide unit costs and total costs for materials, hourly rates for labor categories, and fixed costs for engineering, permits, testing, and additional services. The worksheet concludes with a cost summary section requiring subtotals for each cost category, with line items for overhead and profit percentages to calculate the final total bid price. A warranty period section is included as an optional component for professional bids.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 12-Federal Certifications and Assurances 5-21-25 Final.docx | DOCX document | |
| 11-Federal Clauses Fire Alarm Remediation.pdf | ||
| 2-Appendix V - UTAs Design Quality Procedures.pdf | ||
| 7-RFP 26-04042DM Fire Alarm System.pdf | ||
| 9-Davis Bacon - Tooele.txt | TXT text file | |
| 1-Appendix IV - UTAs Quality Management Plan.pdf | ||
| 8-Davis Bacon - SLC.txt | TXT text file | |
| 10-Davis Bacon - Tooele.txt | TXT text file | |
| 5-Cost Worksheet Exhibit B.pdf | ||
| 6-Davis Bacon - Davis.txt | TXT text file | |
| 3-Appendix VI - UTAs Construction Safety and Security Program Manual.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Fire Alarm System Bid Cost Sheet | ||||
| Client / General Contractor: | ||||
| Bid Date: | ||||
| Prepared By: | ||||
| Company Name: | ||||
| 1. Equipment & Materials | ||||
| Description | Manufacturer / Model | Qty | Unit Cost ($) | Total Cost ($) |
| Fire Alarm Control Panel (FACP) | ||||
| Remote Annunciator Panel | ||||
| Smoke Detectors | ||||
| Heat Detectors | ||||
| Manual Pull Stations | ||||
| Horn / Strobe Notification Devices | ||||
| Duct Detectors | ||||
| Monitor Modules | ||||
| Control Modules | ||||
| Addressable Modules | ||||
| Batteries | ||||
| Power Supplies | ||||
| Conduit & Fittings | ||||
| Fire Alarm Cable / Wire | ||||
| Backboxes & Mounting Hardware | ||||
| Miscellaneous Materials | ||||
| Materials Subtotal: $ | ||||
| 2. Labor Costs | ||||
| Labor Category | Hours | Rate ($/hr) | Total Cost ($) | |
| Project Manager | ||||
| Fire Alarm Technician | ||||
| Electrician / Installer | ||||
| Helper / Apprentice | ||||
| Programming & Configuration | ||||
| Testing & Commissioning | ||||
| Labor Subtotal:$ | ||||
| 3. Engineering & Design | ||||
| Description | Cost ($) | |||
| System Design / Shop Drawings | ||||
| Permit Drawings | ||||
| Engineering Review | ||||
| Engineering Subtotal: $ | ||||
| 4. Permits & Fees | ||||
| Description | Cost ($) | |||
| Fire Department Permit | ||||
| Inspection Fees | ||||
| Plan Review Fees | ||||
| Fees Subtotal: $ | ||||
| 5. Testing & Certification | ||||
| Description | Cost ($) | |||
| System Testing | ||||
| AHJ Inspection Support | ||||
| Final Certification | ||||
| Testing Subtotal: $ | ||||
| 6. Additional Costs | ||||
| Description | Cost ($) | |||
| Equipment Rental | ||||
| Lift / Access Equipment | ||||
| Travel / Mobilization | ||||
| Training | ||||
| Additional Costs Subtotal: | ||||
| 7. Cost Summary | ||||
| Category | Amount ($) | |||
| Materials | ||||
| Labor | ||||
| Engineering | ||||
| Permits & Fees | ||||
| Testing | ||||
| Additional Costs | ||||
| Bonds & Insurance | ||||
| Subtotal: $__________ | ||||
| Overhead (%): $__________ | ||||
| Profit (%): $__________ | ||||
| Total Bid Price: $__________ | ||||
| ✅ Optional Sections (for professional bids) |
Warranty period
File details come from the government source that posted it. Updated .