This Scope of Work document, issued by the State of Utah Division of Purchasing in collaboration with the State of Utah's Watershed Restoration Initiative and the U.S. Fish and Wildlife Service, details a pond excavation project in Corinne, Utah. The project involves constructing a 1-acre island surrounded by a 7-acre pond, requiring the movement of approximately 18,800 cubic yards of soil. The pond will average 2 feet in depth with graduated edge depths of 6 inches, 12 inches, and 24 inches. Contractors are required to attend a mandatory pre-bid site visit on April 30, 2026, from 10:00 a.m. to 12:00 p.m. MST at Bear River Valley Country Store, located at 2780 N 4800 W, Corinne, UT 84307, with latecomers prohibited from bidding. The project execution is scheduled from May 2026 through June 30, 2026, with extension likely beyond that date. A pre-work conference meeting with the landowner is mandatory prior to beginning work.

Contractors must possess five years of active experience excavating dirt to defined grades in Utah and own or be able to rent the required equipment, including a scraper/ejector (approximately 16 feet wide), laser slope transit, and tractor with offset disc or disc ripper. Equipment must include data logging GPS capability for tracking excavation locations, and all contractors must maintain insurance in the State of Utah. Soil will be deposited at four designated locations with specific height and slope requirements, with priorities determined by soil moisture conditions. The contract will be awarded to the lowest cost responsive and responsible vendor, with vendors required to guarantee pricing throughout the project's entirety. Fire precaution restrictions prohibit equipment parking on tall dry grass, with staging sites to be determined at the pre-bid meeting.

View the file

Other files

File Type Posted
3-Attachment B Scope of Work.docx DOCX document
1-Vendor Prerequisites - IFB Agency.pdf PDF
2-Att.-A-PO-Terms-and-Conditions (1).docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment B Scope of Work

NC26-68, WRI 7568

Pond Excavation, Corinne, UT Execution: May 2026 – June 30, 2026 (extension likely after June 30, 2026)

Description of Project A private landowner in Corinne, UT, in collaboration with the State of Utah’s Watershed Restoration Initiative and the U.S. Fish and Wildlife Service, is seeking qualified and experienced contractors with the ability and equipment necessary to excavate a new pond. The contractor must own or be able to obtain the equipment necessary to complete the work as specified below.

Project area is 7600 W. 6800 N., Corinne, UT. The contractor will coordinate with the landowner to create a new pond. Contractor must provide a scraper/ejector (approx. 16 ft. width), a laser slope transit, and a tractor with an offset disc or disc ripper. The disc will facilitate the breakup of 2-3” heavy clay soil for each pass. Contractors will be required to have close communication with the landowner during this work and will be required to have a pre-work conference meeting prior to beginning work.

Contractor requirements

· Have been actively working and excavating dirt to defined grades in Utah for the last five years.

· Own the equipment mentioned above or be able to rent the equipment needed to excavate a pond.

· Have data logging GPS equipment capable of tracking excavation locations.

· Be insured in the State of Utah.

· Due to fire precaution - No equipment will be allowed to park on the tall dry grass. Staging sites will be determined during the pre-bid meeting.

Mandatory Site Visit Due to the complexity of this project, attending the pre-bid meeting is crucial for contractors to visually identify work locations, staging areas, and the specific sites for dirt work, ensuring a clear understanding of the project's requirements and logistics.

· Attend a pre-bid Mandatory Site Visit meeting at the project site prior to work. Purpose will be to review required workload, specifications, schedule and payment timeline of the contract. Please arrive early. All latecomers will be asked to leave and will not be allowed to bid.

· Thursday April 30, 2026, 10 am – 12 pm MST

· Meet at Bear River Valley Country Store, on the north side of the parking lot. 2780 N 4800 W, Corrine, UT 84307

Work Description Pond Excavation A 1-acre Island surrounded by a 7-acre pond will be constructed. Approximately 18,800 cubic yards of soil will be moved. The pond will average 2 feet in depth with most of the outside edges starting at 6“of soil removal (approx. 16 ft. wide) and then an adjacent step down to a 12” depth (16 feet wide). A map delineating the 6”, 12” and 24” depths will be provided to the contractor at the pre-work meeting.

Defining a “Zero Grade “starting point. The pond area grass pasture has been mowed, and the pond/island edges disced. The contractor and landowner will use the landowners’ laser transit to take 15-20 grade shots to get an average of current topsoil grades. The average will determine the “starting grade”. A metal plate will be placed at a spot for which all grades will be determined from.

All removed soil will be placed in 4 locations. The Ingress and Egress will be defined on a map that will be given to the contractor at the pre-work meeting. Essentially there will be 1 road that leads to the soil dump sites. That road will split to allow for 2-way access to the 2 different access roads per dump site. The soil “carry” distance, approx. Cubic yards and soil dump site design/contours are as follows:

Priority #1) Island: 5 ft. dirt height. Outside edge will have a required 4-to-1 slope. Approx.6500 cu. Yds.

· Island Ingress/egress not limited. Access on any side in any manner.

Priority #2) East hill: 100 ft. East of main pond. “U” shaped. about 450 ft in length and 40 ft. wide. Required that this reaches an 8 ft. HEIGHT for about 100 feet on the northern end. Approx. 3000 cu. Yds.

Priority #3) West Hill: 400 ft from west pond edge. This 16 ft. wide “U” shaped hill is sloped to a 7 ft. ht. at its’ apex. Add 2 ft of dirt across most of the hill. Approx. 400 cu. Yds. This will bring the western most 100 ft. up to 9 ft. Required ht. (This hill has had all GRADES shot for Verification) Landowner will verify 9 ft. height before dirt moved to #4 is allowed.

Priority #4) Northwest Hill: 1400 ft. from pond center to center of dogleg hill. All remaining dirt. Approx. 8500-9500 cu. Yds. Dogleg Hill is approx. 60 ft. width and approx. 600 ft. in total length. This hill will easily top 10 ft.

DISCLAIMER: The above soil dump site quantities and priorities apply to moist soil conditions. Depending on soil moisture content there will be different priorities. Extremely dry spring soil conditions will not support elevated soil compaction and hill forming; could cause significant delays in completing the project.

Communication with landowner and project manager will be required throughout the project.