This is an Appendix E Contract Drawings document prepared by Keystone Consulting Engineers, Inc. for Polk Township in Monroe County, Pennsylvania, detailing the general permit drawings for the Dotters Corner Road, Southern End – Culvert Replacement Project. The project involves the replacement of an existing 4-foot round corrugated metal pipe (CMP) culvert with a new 11-foot 8-inch by 5-foot 9-inch aluminum box culvert with a length of 40.5 linear feet. The existing culvert is deteriorating, undersized, and causing flooding issues; the new culvert will provide increased flow capacity, adequate cover, and restored stream bed conditions to facilitate aquatic organism passage and stream bed continuity. The project is registered under Chapter 105 Water Obstruction and Encroachment General Permit (GP#11). A pre-construction meeting must be held at least seven days before earth disturbance activities commence, with attendance required from all involved contractors, the landowner, municipal officials, the erosion and sediment control plan preparer, and a Monroe Conservation District representative. Additionally, the Pennsylvania One Call System must be notified at least three days before earth disturbance activities begin. The project site is located along Dotters Corner Road and involves work in an Exceptional Value – Cold Water Fisheries (EV-CWF) stream section designated under Chapter 93.
The construction sequence outlined in the permit drawings includes installation of erosion and sediment control measures, stream bed preparation, culvert installation with associated headwall and wing walls, stream bed material placement with riffle crests, roadway paving, and final site stabilization and seeding. Soil disturbance involves KaB Kedron Silt Loam, which is poorly drained with high runoff and high erosion potential. The contractor is responsible for all excavation work, culvert assembly and installation, stream bed restoration, roadway paving, shoulder restoration, guide rail installation, and erosion and sediment control implementation. All disturbed areas must achieve 70 percent vegetative cover before temporary erosion and sediment control measures may be removed. The design was prepared by Keystone Consulting Engineers, Inc., located at 205 Rodenbach Lane, Brodheadsville, PA 18322, with contract documents available through PennBid, and bids scheduled to close on Thursday, September 3, 2026, at 2:00 PM, with a pre-bid meeting scheduled for Wednesday, August 19, 2026, at 11:00 AM at the project site.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ALUMINUM BOX CULVERT
11'8" X 5'9" X 40.5 LF (SEE DETAIL)
5' -9
R
IS
E
11'-8" SPAN
15'-0" HEADWALL
7' -0
9' -4
W
IN
G
W
AL
L
9' -4
W
IN
G
W
AL
L
9'-0"4'-6"
5' -9
R
IS
E
11'-8" SPAN
15'-0"
7' -0
9' -4
W
IN
G
W
AL
L
4'-6"
K E
Y S
T O
N E
C O
N S
U L
T I
N G
E N
G I
N E
E R
S
I N
C
E n g i n e e r i n g f i r m o f c h o i c e s i n c e
RE
VI
SI
O
N S
BY
D
AT
E
PO
LK
T O
W N
SH
IP
M O
N
RO
E
CO
UN
TY
, P
EN
N
SY
LV
AN
IA
G P
#1
PE
RM
IT
/E
RO
SI
O N
A N
D
SE
D
IM
EN
T
CO
N
TR
O
L
PL
A N
D O
TT
ER
S
CO
RN
ER
R O
A D
SO
U
TH
E N
TR
A
N
CE
CU
LV
ER
T
RE
PL
A
CE
M
EN
T
D
ES
IG
N
ED
B
Y:
D
RA
W N
B Y:
CH
EC
KE
D
B Y:
D
AT
E:
SC
AL
E:
JO
B N
UM
BE
R:
SH
EE
T:
KC
E
LL
H
TM
M
/1
7/
AS
S
H O
W N
PO
LK
-2 4-
O
F
R
O D
E N
B A
C H
L A
N E
B
R O
D H
E A
D S
V I
L L
E
P A
- 6
N N
PROJECT PURPOSE:
THE PURPOSE OF THIS PROJECTS IS TO REPLACE AN EXISTING 4' ROUND CMP
CULVERT WITH A NEW 11'-8"-"X 5'9" ALUMINUM BOX CULVERT. THE EXISTING
CULVERT IS DETERIORATING AND UNDER SIZED. THIS IS CAUSING FLOODING
ISSUES . THE NEW CULVERT WILL PROVIDE ADDITIONAL FLOW CAPACITY,
ADEQUATE COVER OVER THE CULVERT AND HAVE AN ASSOCIATED RESTORED
STREAM BED TO FACILITY AQUATIC ORGANISM PASSAGE AND STREAM BED
CONTINUITY. ASSOCIATED WITH THIS PLAN IS A CHAPTER 105 WATER
OBSTRUCTION AND ENCROACHMENT GENERAL PERMIT REGISTRATION,
SPECIFICALLY A GP#11, FOR THE REPLACEMENT OF AN EXISTING WATER
OBSTRUCTION.
The soil that will be disturbed by this project is:
· KaB - Kedron Silt Loam
General Soil Characteristics:
Soils: Erosion Potential Frost Action Potential Topsoil Road Fill KaB poorly drained/high runoff High Unsuitable Variable
CHAPTER 93 STREAM CLASSIFICATION
All storm water run-off generated from this site is currently (and will continue to be) directed to Dotters Creek. This section has a Chapter 93 Receiving Watercourse designation of Exceptional Value - Cold Water Fisheries (EV-CWF) and is classified as supporting Migratory Fishes (MF).
Wetland Statement:
Steven Hawk of Keystone Consulting Engineers, Inc. has determined, through field verification, State and Federally Regulated Wetlands exist within the project site's limit of disturbance. This inventory for wetland conditions was conducted according to Federal and State guidelines as described in the Regional Supplement to the Corps of Engineers Wetland Delineation Manual: Northcentral and Northeast Region, Version 2.0 as agreed to process for identifying and delineating wetlands in Pennsylvania. Wetland are shown in plan view.
SEQUENCE OF CONSTRUCTION:
AT LEAST 7 DAYS BEFORE STARTING ANY EARTH DISTURBANCE ACTIVITIES, THE CONTRACTOR
SHALL INVITE ALL CONTRACTORS INVOLVED IN THOSE ACTIVITIES, THE LANDOWNER, ALL
APPROPRIATE MUNICIPAL OFFICIALS, THE EROSION AND SEDIMENTATION CONTROL PLAN
PREPARER, AND A REPRESENTATIVE OF THE MONROE CONSERVATION DISTRICT TO A ON-SITE
PRE-CONSTRUCTION MEETING, ALSO AT LEAST 3 DAYS BEFORE STARTING ANY EARTH
DISTURBANCE ACTIVITIES, ALL CONTRACTORS INVOLVED IN THOSE ACTIVITIES SHALL NOTIFY THE PENNSYLVANIA ONE CALL SYSTEM INCORPORATED AT 1-800-242-1776 FOR BURIED UTILITY
LOCATIONS.
BELOW IS A GENERAL SEQUENCE OF CONSTRUCTION RELATIVE TO INSTALLATION OF EROSIONS
AND SEDIMENT CONTROL ASSOCIATED AND ASSOCIATED CONSTRUCTION STEPS. THE BELOW
SEQUENCE ASSUMES A BY-PASS PUMP, BY-PASSING IN-STREAM FLOWS AROUND THE ENTIRE
SECTION OF STREAM SECTION TO BE RESTORED. AT THE TIME OF CONSTRUCTION, DEPENDING
ON AVAILABLE RECOURSES, THE PROJECT CAN BE COMPLETED IN PHASES UNDER THE
DISCRETION OF THE TOWNSHIP ENGINEER AND MCCD.
1. INSTALL ALL COMPOST FILTER RUNS.
2. PROCEED ONLY WHEN STREAM BED MATERIAL IS STOCKPILED ON-SITE AND CULVERT IS
ASSEMBLED. PLACE COFFER DAM AND INSTALL PUMP. INSTALL PUMPED WATER FILTER
BAG.
3. PLACE ROCK FILTER ACROSS CHANNEL AS SHOWN ON DETAIL.
4. COMPLETE ROAD CUT AND REMOVE EXISTING CULVERT, OVER EXCAVATE FOR FOOTING
INSTALLATION.
5. INSTALL FOOTING PER SPECIFICATIONS.
6. IN CONJUNCTION WITH PREVIOUS STEP, EXCAVATE TO PREPARE FOR STREAM BED
MATERIAL PLACEMENT AND CHANNEL CONSTRUCTION. STOCKPILE EXCAVATED NATIVE
STREAMBED MATERIAL AS SHOWN ON THE PLAN. CONTACT TOWNSHIP ENGINEER TO
ASSESS STOCKPILED NATIVE MATERIAL.
7. WORKING FROM UPSTREAM, DOWNSTREAM. PLACE STREAM BED MATERIAL PER THE
SPECIFICATIONS SUPPLIED ON THIS SHEET (SEE STREAMBED MATERIAL PLACEMENT
NOTE), CONSTRUCTING THE PROPOSED RESTORED CHANNEL. INSTALL RIFFLE CRESTS
UP-SLOPE AND DOWN-SLOPE OF THE CULVERT PER THE ELEVATION SET ON THE PLAN.
8. INSTALL THE CULVERT AND ASSOCIATED HEADWALL AND WING WALLS PER THE
SPECIFICATION ON THE CULVERT INSTALLATION PLAN. COMPLETE FINAL GRADING
9. SOIL AND SEED ANY AREAS DISTURBED DURING THE CONSTRUCTION OF THE CULVERT
AND STREAM BED IN ACCORDANCE WITH THE PLANS AND SEEDING SCHEDULE.
REPLACE ANY EXISTING TOPSOIL, FROM THE STOCKPILE LOCATION, OR ADD TOPSOIL
FROM OFFSITE (IF NEEDED) TO OBTAIN A CONSISTENT 4" TOPSOIL THICKNESS. RAKE THE
TOPSOIL TO REMOVE ANY STONES AND TREAT IT WITH LIME AND FERTILIZER PRIOR TO
SEEDING AND MULCHING. AFTER PREPARING THE SOIL, IMMEDIATELY SEED THE
DISTURBED AREAS ACCORDING TO THE SEEDING CHART AS SHOWN ON THE PLANS.
ALL DISTURBED AREAS SHALL BE MATTED WITH NAG S75 SLOPE MATTING FOR
TEMPORARY STABILIZATION.
10. REMOVE COFFER DAM, PUMPS AND ROCK FILTER.
11. COMPLETE THE PAVING OF THE ROADWAY. STABILIZE, MULCH, AND SEED ALL
DISTURBED AREAS ADJACENT TO THE ROADWAY AREAS UPON COMPLETION.
12. THE CONTRACTOR SHALL REMOVE ALL THE TEMPORARY EROSION AND SEDIMENT
CONTROL MEASURES WHEN THE SITE IS PROPERLY STABILIZED. THE SITE WILL BE
CONSIDERED PROPERLY STABILIZED WHEN 70% COVER HAS BEEN ACHIEVED; ONLY AT
THIS TIME CAN THE EROSION AND SEDIMENT CONTROL MEASURES BE REMOVED.
At any time during construction operations when work on this project ceases, all disturbed areas shall be stabilized with a temporary grass seed.
0 5 10 20 40
( IN FEET )
1 inch = 10 ft.
GRAPHIC SCALE
K E
Y S
T O
N E
C O
N S
U L
T I
N G
E N
G I
N E
E R
S
I N
C
E n g i n e e r i n g f i r m o f c h o i c e s i n c e
RE
VI
SI
O
N S
BY
D
AT
E
PO
LK
T O
W N
SH
IP
M O
N
RO
E
CO
UN
TY
, P
EN
N
SY
LV
AN
IA
G P
#1
PE
RM
IT
/E
RO
SI
O N
A N
D
SE
D
IM
EN
T
CO
N
TR
O
L N
O
TE
S A
N D
D
ET
A
IL
S
D O
TT
ER
S
CO
RN
ER
R O
A D
SO
U
TH
E N
TR
A
N
CE
CU
LV
ER
T
RE
PL
A
CE
M
EN
T
D
ES
IG
N
ED
B
Y:
D
RA
W N
B Y:
CH
EC
KE
D
B Y:
D
AT
E:
SC
AL
E:
JO
B N
UM
BE
R:
SH
EE
T:
KC
E
LL
H
TM
M
/1
7/
AS
S
H O
W N
PO
LK
-2 4-
O
F
R
O D
E N
B A
C H
L A
N E
B
R O
D H
E A
D S
V I
L L
E
P A
- 6
STANDARD CONSTRUCTION DETAIL #4-1
COMPOST FILTER SOCK
STANDARD CONSTRUCTION DETAIL #11-1
EROSION CONTROL BLANKET INSTALLATION
STANDARD CONSTRUCTION DETAIL #4-14
ROCK FILTER
STANDARD CONSTRUCTION DETAIL #3-16
PUMPED WATER FILTER BAG
| POLK-24-024 GP#11 PERMIT-sheet 1 |
| Sheets and Views |
| sheet 1 |
| POLK-24-024 GP#11 PERMIT-sheet 2 |
| Sheets and Views |
| sheet 2 |
File details come from the government source that posted it. Updated .