Addendum #1 to Refuse Removal, Disposal and Recycling Services Contract for LaGuardia Airport
This is Addendum #1 to Bid #6000003139 issued by the Port Authority of New York and New Jersey's Procurement Department for refuse removal, disposal, and recycling services at LaGuardia Airport. The addendum modifies the pre-response meeting requirements and incorporates Standard Contract Terms and Conditions dated February 2026 as binding contract provisions. The pre-response meeting, originally scheduled as an in-person event, has been changed to a virtual meeting via Microsoft Teams on Wednesday, May 27, 2026, at 9:30 A.M. Interested parties must email Shanta Nelson at snelson@panynj.gov no later than 2:00 PM ET the business day before the meeting to receive a Microsoft Teams invitation. The bid submission deadline remains June 1, 2026, no later than 11:00 AM, via Bonfire. The contract is for a two-year term. Bidders must initial the Standard Contract Terms and Conditions and annex them to their bid upon submission; failure to physically attach and initial this document will not invalidate the bid, as it will be deemed incorporated.
The Standard Contract Terms and Conditions establish comprehensive requirements governing contractor performance, including facility compliance, non-discrimination, indemnification, safety and cleanliness standards, environmental protection, security protocols, record-keeping obligations, and Port Authority authority to terminate for default or convenience. The conditions require contractors to assume all operational risks, maintain proper insurance and bonding, comply with all federal, state, and local laws, obtain necessary permits and licenses, and implement extensive security procedures including background screening through the Secure Worker Access Consortium (S.W.A.C.) for personnel accessing secure areas. Contractors must utilize only Port Authority-approved materials and supplies, maintain detailed records for three years post-contract, and indemnify the Port Authority against third-party claims arising from contractor operations. The addendum specifies that the Port Authority may terminate the contract without cause upon five days' written notice and retains rights to withhold payments for performance deficiencies or third-party claims. All questions regarding the addendum should be directed to Shanta Nelson at (212) 435-4661 or snelson@panynj.gov.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2-QBSPDOC 6000003139.pdf | ||
| 1-AD 6000003139 QBSP.pdf | ||
| 3-QEPDOC 6000003139.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PS11All
PROCUREMENT DEPARTMENT
4 WORLD TRADE CENTER
150 GREENWICH STREET, 21ST FL.
NEW YORK, NY 10007
5/22/2026
ADDENDUM #1
To prospective Bidder(s) on Bid #6000003139 – Refuse Removal, Disposal and Recycling Services for Laguardia Airport (LGA) – Two-Year Contract
Due 6/1/26, no later than 11:00 AM, via Bonfire
I. CHANGES/MODIFICATIONS
The following changes/modifications are hereby made to the solicitation documents:
a) Part II, section 8 entitled “Pre-Response Meeting”, delete in its entirety and replace with the following:
Date and Time: Wednesday, May 27, 2026, 9:30 A.M.
The Port Authority will conduct a virtual Pre-Response Meeting via Microsoft Teams on Wednesday, May 27, 2026, at 9:30 A.M. to discuss the solicitation documents and requirements. Parties interested in attending the Microsoft Teams Pre-Response Meeting shall email the Shanta Nelson, at snelson@panynj.gov no later than 2:00 PM ET the business day before the meeting. You will receive a Microsoft Teams invitation via email, which you must “Accept” in order to participate in the Pre-Response Meeting
b) “Standard Contract Terms and Conditions” dated February 2026 is hereby made part of this Contract.
This communication should be initialed by you and annexed to your Bid upon submission.
In case any Bidder fails to conform to these instructions, its Bid will nevertheless be construed as though this communication had been so physically annexed and initialed.
PS11All
THE PORT AUTHORITY OF NY & NJ
SHANTA NELSON, PROGRAM DIRECTOR
COMMODITIES AND SERVICES DIVISION
PROCUREMENT DEPARTMENT
BIDDER'S FIRM NAME: _________________________________________________
INITIALED: ____________________________________________________________
DATE: _________________________________________________________________
QUESTIONS CONCERNING THIS ADDENDUM MAY BE ADDRESSED TO
SHANTA NELSON, WHO CAN BE REACHED AT (212) 435-4661 OR AT
SNELSON@PANYNJ.GOV.
Standard Contract Terms and Conditions - PA PA BID (2.2026)
STANDARD CONTRACT TERMS AND CONDITIONS
PART I GENERAL DEFINITIONS
PART II GENERAL PROVISIONS
1. Facility Rules and Regulations of The Port Authority
2. Contractor Not An Agent
3. Contractor's Warranties
4. Personal Non-Liability
5. Non-Discrimination Requirements
6. Rights and Remedies of the Port Authority
7. Rights and Remedies of the Contractor
8. Submission To Jurisdiction
9. Harmony
10. Claims of Third Persons
11. No Third Party Rights
12. Provisions of Law Deemed Inserted
13. Costs Assumed By The Contractor
14. Default, Revocation or Suspension of Contract
15. Sales or Compensating Use Taxes
16. No Estoppel or Waiver
17. Records and Reports
18. General Obligations
19. Assignments and Subcontracting
20. Indemnification and Risks Assumed By The Contractor
21. Approval of Methods
22. Safety and Cleanliness
23. Accident Reports
24. Trash Removal
25. Lost and Found Property
26. Property of the Contractor
27. Modification of Contract
28. Invalid Clauses
29. Approval of Materials, Supplies and Equipment
30. Intellectual Property
31. Contract Records and Documents – Passwords and Codes
32. Designated Secure Areas
33. Notification of Security Requirements
34. Construction In Progress
35. Permit-Required Confined Space Work
36. Signs
37. Vending Machines, Food Preparation
38. Confidential Information/Non-Publication
39. Time is of the Essence
40. Holidays
41. Personnel Standards
42. General Uniform Requirements for Contractor’s Personnel
43. Labor, Equipment and Materials Supplied by the Contractor
Standard Contract Terms and Conditions - PA PA BID (2.2026)
44. Contractor’s Vehicles – Parking - Licenses
45. Manager’s Authority
46. Reserved
47. Sustainable Packaging
48. MBE/WBE/SDVOB Enterprises
49. Code of Ethics for Port Authority Vendors
PART III CONTRACTOR'S INTEGRITY PROVISIONS
1. Certification of No Investigation (criminal or civil anti-trust), Indictment, Conviction, Debarment, Suspension, Disqualification and Disclosure of Other Information
2. Non-Collusive Bidding, and Code of Ethics Certification, Certification of No Solicitation Based On Commission, Percentage, Brokerage, Contingent or Other Fees
3. Bidder Eligibility for Award of Contracts - Determination by an Agency of the State of New York or New Jersey Concerning Eligibility to Receive Public Contracts
4. Contractor Responsibility, Suspension of Work and Termination
5. No Gifts, Gratuities, Offers of Employment, Etc
6. Obligation to Report
7. Conflict of Interest
8. Integrity Monitor
9. Right to Audit
10. Definitions
Standard Contract Terms and Conditions PA BID (2.2026)
STANDARD CONTRACT TERMS AND CONDITIONS
PART I GENERAL DEFINITIONS
To avoid undue repetition, the following terms, as used in this Agreement, shall be construed as follows:
Authority or Port Authority - means the Port Authority of New York and New Jersey.
Contract, Document or Agreement - means the writings setting forth the scope, terms, conditions and Specifications for the procurement of Goods and/or Services, as defined hereunder and shall include, but not be limited to: Invitation for Bid (IFB), Request for Quotation (RFQ), Request for Proposal (RFP), Purchase Order (PO), Cover Sheet, executed Signature Sheet, AND PRICING SHEETS with Contract prices inserted," "STANDARD CONTRACT TERMS AND CONDITIONS," and, if included, attachments, endorsements, schedules, exhibits, or drawings, the Authority's acceptance and any written addenda issued by an authorized member of the Procurement Department.
Days or Calendar Days - means consecutive calendar days, Saturdays, Sundays, and Holidays, included.
Week - unless otherwise specified, means seven (7) consecutive calendar days, Saturdays, Sundays, and Holidays.
Month - unless otherwise specified, means a calendar month.
Hazardous Substance(s) - shall mean any pollutant, contaminant, toxic or hazardous waste, dangerous substance, noxious substance, toxic substance, flammable, explosive or radioactive material, urea formaldehyde foam insulation, asbestos, polychlorinated biphenyls (“PCBs”), chemicals known to cause cancer, endocrine disruption or reproductive toxicity, petroleum and petroleum products and other substances which have been or in the future shall be declared to be hazardous or toxic, or the removal, containment or restriction of which have been or in the future shall be required, or the manufacture, preparation, production, generation, use, maintenance, treatment, storage, transfer, handling or ownership of which have or in the future shall be restricted, prohibited, regulated or penalized by any federal, state, county, or municipal or other local statute or law now or at any time hereafter in effect as amended or supplemented and by the regulations adopted and publications promulgated pursuant thereto.
Holiday(s) – means any holiday which is observed at the Site, as further detailed in the section of these Standard Contract Terms and Conditions entitled “Holidays.”
Director - means the Director of the Department which operates the facility of the Port Authority at which the services hereunder are to be performed, for the time being, or his/her successor in duties for the purpose of this Contract, or one of his/her authorized representatives for the purpose of this Contract.
Environmental Requirements - shall mean all common law and all past, present and future laws, statutes, enactments, resolutions, regulations, rules, directives, ordinances, codes, licenses, permits, orders, memoranda of understanding and memoranda of agreement, guidances, approvals, plans, authorizations, concessions, franchises, requirements and similar items of all governmental agencies, departments, commissions, boards, bureaus or instrumentalities of the United States, states and political subdivisions thereof, all pollution prevention programs, “best management practices plans”, and other programs adopted and agreements made by the Port Authority with any governmental agencies (whether adopted or made with or without consideration or with or without compulsion), with any government agencies, departments, commissions, boards, bureaus or instrumentalities of the United States, states and political subdivisions thereof, and all judicial, administrative, voluntary and regulatory decrees, judgments, orders and agreements relating to the protection of human health or the environment, and in the event that there is more than one compliance standard, the standard for any of the foregoing to be that which requires the lowest level of a Hazardous Substance, the foregoing to include without limitation:
(1) all requirements pertaining to reporting, licensing, permitting, investigation and Remediation of emissions, discharges, releases or threatened releases of Hazardous Substances into the air, surface water, groundwater or land, or relating to the manufacture, processing, distribution, use, treatment, storage, disposal, transport or handling of Hazardous Substances, or the transfer of property on which Hazardous Substances exist;
(2) all requirements pertaining to the protection from Hazardous Substances of the health and safety of employees or the public; and
(3) all Governmental Approvals applicable to the facility and issued pursuant to Applicable Laws governing health, safety and the protection of the environment;
(4) the Atomic Energy Act of 1954, 42 U.S.C. Section 2011 et seq.; the Clean Water Act also known as the Federal Water Pollution Control Act, 33 U.S.C. Section 1251 et seq.; the Clean Air Act, 42 U.S.C. Section 7401 et seq.; the Federal Insecticide, Fungicide, and Rodenticide Act, 7 U.S.C. Section 136 et seq.; the Comprehensive Environmental Response, Compensation, and Liability Act, 42 U.S.C. Section 9601 et seq.; the Superfund Amendments and Reauthorization Act of 1986 (“SARA”), Section 2701 et seq.; the Emergency Planning and Community Right to Know Act, 42 U.S.C. Section 11001 et seq.; the Occupational Safety and Health Act, 29 U.S.C. Section 651 et seq.; the Hazardous Materials Transportation Act, 49 U.S.C. Section 5101 et seq.; the Solid Waste Disposal Act, as amended by the Resource Conservation and Recovery Act, 42 U.S.C. Section 6901 et seq.; the Toxic Substances Control Act, 15 U.S.C. Section 2601 et seq.; the Safe Drinking Water Act of 1974, 42 U.S.C. Sections 300f-300h-11 et seq.; the New Jersey Spill Compensation and Control Act (N.J.S.A. 58:10-23.11 et seq.) (“Spill Act”); the Industrial Site Recovery Act ("ISRA")(N.J.S.A. 13:1K and N.J.A.C. 7:26B); Solid Waste Management Act (N.J.S.A. 13:1E-1 to 48); and Water Pollution Control Act (N.J.S.A. 58:10A-1 to 60); the New York State Environmental Conservation Law; the New York State Navigation Law; together, in each case, together, in each case, with any amendment thereto, and the regulations adopted, guidances, memoranda and publications promulgated thereunder and all substitutions thereof; and
(5) all requirements and conditions (including all mitigation) to be satisfied under the Environmental
Assessment and NEPA Documents.
Manager - means the Manager of the Facility for the time being, or his successor in duties for the purpose of this Contract, or his duly authorized representative for the purpose of this Contract.
No person shall be deemed a representative of the Director or Manager except to the extent specifically authorized in an express written notice to the Contractor signed by the Director or Manager, as the case may be. Further, no person shall be deemed a successor in duties of the Director unless the Contractor is so notified in writing signed by the Authority’s Procurement Department. No person shall be deemed a successor in duties of the Manager unless the Contractor is so notified in a writing signed by the Director.
Minority shall mean (a) a Black person who is part of a Black African racial group; or (b) an Hispanic person of Native American or Latin American origin descended from persons from Puerto Rico, Mexico, the Dominican Republic, Cuba, or a country of Central or South America; or (c) an Asian person or Pacific Islander descended from persons who have an origin in Asia (including the Far East, Southeast Asia and the Indian Subcontinent) or the Pacific Islands; or (d) an American Indian or Alaskan Native descended from persons who have an origin in North America so long as the Minority person maintains identifiable tribal affiliations through membership and participation in a tribe or maintains a tribal community identification.
Minority Business Enterprise or MBE shall mean any business enterprise which is at least fifty-one percent (51%) owned by, or in the case of a corporation, at least fifty-one percent (51%) of the stock of which is owned by one (1) or more Minority group member; and whose management and daily business operations are controlled by one or more such individuals who are citizens or permanent resident aliens and such ownership is real, substantial and continuing.
Service-connected shall mean a disability incurred or an injury aggravated in the line of duty in the active U.S. military, naval or air service.
Service-disabled Veteran shall mean a Veteran with a Service-connected disability, each as defined by 38 U.S.C. 101.
Service-disabled Veteran Owned Business or SDVOB shall mean any business enterprise which is at least 51% owned by, or in the case of a corporation, at least 51% of the stock of which is owned by one (1) or more Service-disabled Veterans; and whose management and daily business operations are controlled by one (1) or more such individuals with a verifiable service connected disability and such ownership is real, substantial and continuing.
Veteran shall mean a person who served in the active U.S. military, naval, or air service, and who was discharged or released therefrom under conditions other than dishonorable.
Women-owned Business Enterprise or WBE shall mean any business enterprise which is at least fifty-one percent (51%) owned by, or in the case of a corporation, at least fifty-one percent (51%) of the stock of which is owned by one (1) or more woman; and whose management and daily business operations are controlled by one or more women who are citizens or permanent resident aliens and such ownership is real, substantial and continuing.
Site of the Work - or words of similar import mean the Facility and all buildings and properties associated therewith as described in this Contract.
Small Business Enterprise (SBE) - The criteria for a Small Business Enterprise are:
o The principal place of business must be located in New York or New Jersey;
o The firm must have been in business for at least three years with activity;
o Average gross income limitations by industry as established by the Port Authority.
Subcontractor - means anyone who performs work (other than or in addition to the furnishing of materials, plant or equipment) in connection with the services to be provided hereunder, directly or indirectly for or on behalf of the Contractor (and whether or not in privity of contract with the Contractor), but shall not include any person who furnished merely his own personal labor or his own personal services. "Subcontractor", however, shall exclude the Contractor or any subsidiary or parent of the Contractor or any person, firm or corporation which has a substantial interest in the Contractor or in which the Contractor or the parent or the subsidiary of the Contractor, or an officer or principal of the Contractor or of the parent of the subsidiary of the Contractor has a substantial interest, provided, however, that for the purpose of the clause hereof entitled "Assignments and Subcontracts" the exclusion in this paragraph shall not apply to anyone but the Contractor itself.
Work - means all services, equipment and materials (including materials and equipment, if any, furnished by the Authority) and other facilities and all other things necessary or proper for, or incidental to the services to be performed or goods to be furnished in connection with the service to be provided hereunder.
PART II GENERAL PROVISIONS
1. Facility Rules and Regulations of The Port Authority
a. The Contractor shall observe and obey (and compel its officers, employees, guests, invitees, and those doing business with it, to observe and obey) the facility Rules and Regulations of the Port Authority now in effect, and such further reasonable Rules and Regulations which may from time to time during the term of this Agreement be promulgated by the Port Authority for reasons of safety, health, preservation of property or maintenance of a good and orderly appearance and efficient operation of the Facility. The Port Authority agrees that, except in case of emergency, it shall give notice to the Contractor of every Rule and Regulation hereafter adopted by it at least five days before the Contractor shall be required to comply therewith.
b. A copy of the facility Rules and Regulations of the Port Authority shall be available for review by the Contractor at the Office of the Secretary of the Port Authority.
2. Contractor Not An Agent
This Agreement does not constitute the Contractor the agent or representative of the Port Authority for any purpose whatsoever except as may be specifically provided in this Agreement. It is hereby specifically acknowledged and understood that the Contractor, in performing its services hereunder, is and shall be at all times an independent Contractor and the officers, agents and employees of the Contractor shall not be or be deemed to be agents, servants, employees or “special employees” of the Port Authority.
3. Contractor's Warranties
The Contractor represents and warrants:
a. That it is financially solvent, that it is experienced in and competent to perform the requirements of this
Contract, that the facts stated or shown in any papers submitted or referred to in connection with the solicitation are true, and, if the Contractor be a corporation, that it is authorized to perform this Contract;
b. That it has carefully examined and analyzed the provisions and requirements of this Contract, and that from its own investigations it has satisfied itself as to the nature of all things needed for the performance of this Contract, the general and local conditions and all other matters which in any way affect this Contract or its performance, and that the time available to it for such examination, analysis, inspection and investigation was adequate;
c. That the Contract is feasible of performance in accordance with all its provisions and requirements and that it can and will perform it in strict accordance with such provisions and requirements;
d. That no Commissioner, officer, agent or employee of the Port Authority is personally interested directly or indirectly in this Contract or the compensation to be paid hereunder;
e. That, except only for those representations, statements or promises expressly contained in this Contract, no representation, statement or promise, oral or in writing, of any kind whatsoever by the Port Authority, its Commissioners, officers, agents, employees or consultants has induced the Contractor to enter into this Contract or has been relied upon by the Contractor, including any with reference to: (1) the meaning, correctness, suitability, or completeness of any provisions or requirements of this Contract; (2) the nature, quantity, quality or size of the materials, equipment, labor and other facilities needed for the performance of this Contract; (3) the general or local conditions which may in any way affect this Contract or its performance; (4) the price of the Contract; or (5) any other matters, whether similar to or different from those referred to in (1) through (4) immediately above, affecting or having any connection with this Contract, the bidding thereon, any discussions thereof, the performance thereof or those employed therein or connected or concerned therewith.
Moreover, the Contractor accepts the conditions at the Site of the Work as they may eventually be found to exist and warrants and represents that it can and will perform the Contract under such conditions and that all materials, equipment, labor and other facilities required because of any unforeseen conditions (physical or otherwise) shall be wholly at its own cost and expense, anything in this Contract to the contrary notwithstanding.
Nothing in the Specifications or any other part of the Contract is intended as or shall constitute a representation by the Port Authority as to the feasibility of performance of this Contract or any part thereof.
The Contractor further represents and warrants that it was given ample opportunity and time and by means of this paragraph was requested by the Port Authority to review thoroughly all documents forming this Contract prior to opening of Bids on this Contract in order that it might request inclusion in this Contract of any statement, representation, promise or provision which it desired or on which it wished to place reliance; that it did so review said documents, that either every such statement, representation, promise or provision has been included in this Contract or else, if omitted, that it expressly relinquishes the benefit of any such omitted statement, representation, promise or provision and is willing to perform this Contract without claiming reliance thereon or making any other claim on account of such omission.
The Contractor further recognizes that the provisions of this numbered clause (though not only such provisions) are essential to the Port Authority's consent to enter into this Contract and that without such provisions, the Authority would not have entered into this Contract.
4. Personal Non-Liability
Neither the Commissioners of the Port Authority nor any of them, nor any officer, agent or employee thereof, shall be charged personally by the Contractor with any liability, or held personally liable to the Contractor under any term or provision of this Agreement, or because of its execution or attempted execution, or because of any breach, or attempted or alleged breach, thereof.
5. Non-Discrimination Requirements
The Contractor shall take all necessary and reasonable steps to ensure non-discrimination in the performance and administration of all aspects of this Contract.
A. Contractor hereby agrees that no person on the ground of race, color, national origin, creed/religion, sex, age or handicap/disability shall be excluded from participation in, denied the benefits of, or be otherwise subjected to discrimination in the furnishing of goods or services or in the selection and retention of subcontractors and/or vendors under this Contract. Contractor shall also ascertain and comply with all applicable federal, state and local laws, ordinances, rules, regulations, and orders that pertain to equal employment opportunity, and non-discrimination in employment.
B. Contractor agrees that these “Non-Discrimination Requirements” are a binding part of this Contract.
Without limiting the generality of any other term or provision of this Contract, in the event the Authority, or a state or federal agency finds that the Contractor or any of its subcontractors or vendors has not complied with these “Non-Discrimination Requirements”, the Authority may cancel, terminate or suspend this Contract in accordance with Section 14 of these Standard Terms and Conditions entitled “Default, Revocation, or Suspension of Contract.”
C. Contractor agrees to cooperate fully with the Authority’s investigation of allegations of discrimination. Cooperation includes, but is not limited to, allowing the Authority to question employees during the investigation of allegations of discrimination, and complying with directives that the Authority or the State or Federal government deem essential to ensure compliance with these “Non-Discrimination Requirements.”
6. Rights and Remedies of the Port Authority
The Port Authority shall have the following rights in the event the Contractor is deemed guilty of a breach of any term whatsoever of this Contract:
a. The right to take over and complete the Work or any part thereof as agent for and at the expense of the Contractor, either directly or through others.
b. The right to cancel this Contract as to any or all of the Work yet to be performed.
c. The right to specific performance, an injunction or any appropriate equitable remedy.
d. The right to money damages.
For the purpose of this Contract, breach shall include but not be limited to the following, whether or not the time has yet arrived for performance of an obligation under this Contract: a statement by the Contractor to any representative of the Port Authority indicating that the Contractor cannot or will not perform any one or more of its obligations under this Contract; any act or omission of the Contractor or any other occurrence which makes it improbable at the time that it will be able to perform any one or more of its obligations under this Contract; any suspension of or failure to proceed with any part of the Work by the Contractor which makes it improbable at the time that it will be able to perform any one or more of its obligations under this Contract.
The enumeration in this numbered clause or elsewhere in this Contract of specific rights and remedies of the Port Authority shall not be deemed to limit any other rights or remedies which the Authority would have in the absence of such enumeration; and no exercise by the Authority of any right or remedy shall operate as a waiver of any other of its rights or remedies not inconsistent therewith or to estop it from exercising such other rights or remedies.
7. Rights and Remedies of the Contractor
Inasmuch as the Contractor can be adequately compensated by money damages for any breach of this Contract which may be committed by the Port Authority, the Contractor expressly agrees that no default, act or omission of the Port Authority shall constitute a material breach of this Contract, entitling the Contractor to cancel or rescind this Contract or to suspend or abandon performance.
8. Submission To Jurisdiction
The Contractor hereby irrevocably submits itself to the jurisdiction of the Courts of the State of New York and New Jersey, in regard to any controversy arising out of, connected with, or in any way concerning this Contract.
The Contractor agrees that the service of process on the Contractor in relation to such jurisdiction may be made, at the option of the Port Authority, either by registered or certified mail addressed to it at the address of the Contractor indicated on the signature sheet, or by actual personal delivery to the Contractor, if the Contractor is an individual, to any partner if the Contractor be a partnership or to any officer, director or managing or general agent if the Contractor be a corporation.
Such service shall be deemed to be sufficient when jurisdiction would not lie because of the lack of basis to serve process in the manner otherwise provided by law. In any case, however, process may be served as stated above whether or not it might otherwise have been served in a different manner.
9. Harmony
a. The Contractor shall not employ any persons or use any labor, or use or have any equipment, or permit any condition to exist which shall or may cause or be conducive to any labor complaints, troubles, disputes or controversies at the Facility which interfere or are likely to interfere with the operation of the Port Authority or with the operations of lessees, licensees or other users of the Facility or with the operations of the Contractor under this Contract.
The Contractor shall immediately give notice to the Port Authority (to be followed by written notices and reports) of any and all impending or existing labor complaints, troubles, disputes or controversies and the progress thereof. The Contractor shall use its best efforts to resolve any such complaint, trouble, dispute or controversy. If any type of strike, boycott, picketing, work stoppage, slowdown or other labor activity is directed against the Contractor at the Facility or against any operations of the Contractor under this Contract, whether or not caused by the employees of the Contractor, and if any of the foregoing, in the opinion of the Port Authority, results or is likely to result in any curtailment or diminution of the services to be performed hereunder or to interfere with or affect the operations of the Port Authority , or to interfere with or affect the operations of lessees, licensees, or other users of the Facility or in the event of any other cessation or stoppage of operations by the Contractor hereunder for any reason whatsoever, the Port Authority shall have the right at any time during the continuance thereof to suspend the operations of the
Contractor under this Contract, and during the period of the suspension the Contractor shall not perform its services hereunder and the Port Authority shall have the right during said period to itself or by any third person or persons selected by it to perform said services of the Contractor using the equipment which is used by the Contractor in its operations hereunder as the Port Authority deems necessary and without cost to the Port Authority. During such time of suspension, the Contractor shall not be entitled to any compensation. Any flat fees, including management fees, shall be prorated. Prior to the exercise of such right by the Port Authority, it shall give the Contractor notice thereof, which notice may be oral.
No exercise by the Port Authority of the rights granted to it in the above subparagraph shall be or be deemed to be a waiver of any rights of termination or revocation contained in this Contract or a waiver of any rights or remedies which may be available to the Port Authority under this Contract or otherwise.
b. During the time that the Contractor is performing the Contract, other persons may be engaged in other operations on or about the worksite including Facility operations, pedestrian, bus and vehicular traffic and other Contractors performing at the worksite, all of which shall remain uninterrupted.
The Contractor shall so plan and conduct its operations as to work in harmony with others engaged at the site and not to delay, endanger or interfere with the operation of others (whether or not specifically mentioned above), all to the best interests of the Port Authority and the public as may be directed by the Port Authority.
10. Claims of Third Persons
The Contractor undertakes to pay all claims lawfully made against it by subcontractors, suppliers and workers, and all claims lawfully made against it by other third persons arising out of or in connection with or because of the performance of this Contract and to cause all subcontractors to pay all such claims lawfully made against them.
11. No Third Party Rights
Nothing contained in this Contract is intended for the benefit of third persons, except to the extent that the Contract specifically provides otherwise by use of the words "benefit" or "direct right of action."
12. Provisions of Law Deemed Inserted
Each and every provision of law and clause required by law to be inserted in this Contract shall be deemed to be inserted herein and the Contract shall be read and enforced as though it were included therein, and if through mistake or otherwise any such provision is not inserted, or is not correctly inserted, then upon the application of either party, the Contract shall forthwith be physically amended to make such insertion.
13. Costs Assumed By The Contractor
It is expressly understood and agreed that all costs of the Contractor of whatever kind or nature and whether imposed directly upon the Contractor under the terms and provisions hereof or in any other manner whatsoever because of the requirements of the operation of the service or otherwise under this Agreement shall be borne by the Contractor or without compensation or reimbursement from the Port Authority, except as specifically set forth in this Agreement. The entire and complete cost and expense of the Contractor's services and operations hereunder shall be borne solely by the Contractor and under no circumstances shall the Port Authority be liable to any third party (including the Contractor's employees) for any such costs and expenses incurred by the Contractor and under no circumstances shall the Port Authority be liable to the Contractor for the same, except as specifically set forth in this Section.
14. Default, Revocation or Suspension of Contract
a. If one or more of the following events shall occur:
1. If fire or other cause (including a cyber security event) shall destroy all or a substantial part of the Facility, asset or infrastructure (including technological infrastructure, data or records) necessary to perform the work required by the Contract;
2. If any governmental agency shall condemn or take a temporary or permanent interest in all or a substantial part of the Facility, or all of a part of the Port Authority's interest herein;
then upon the occurrence of such event or at any time thereafter during the continuance thereof, the Port Authority shall have the right on twenty-four (24) hours written notice to the Contractor to revoke this Contract, such revocation to be effective upon the date and time specified in such notice.
In such event this Contract shall cease and expire on the effective date of revocation as if said date were the date of the expiration of this Contract. Such revocation shall not, however, relieve the Contractor of any liabilities or obligations hereunder which shall have accrued on or prior to the effective date of revocation.
b. If one or more of the following events shall occur:
1. The Contractor shall become insolvent, or shall take the benefit of any present or future insolvency statute, or shall make a general assignment for the benefit of creditors, or file a voluntary petition in bankruptcy or a petition or answer seeking an arrangement or its reorganization or the readjustment of its indebtedness under the federal bankruptcy laws or under any other law or statute of the United States or of any State thereof, or consent to the appointment of a receiver, trustee, or liquidator of all or substantially all its property; or
2. By order or decree of a court the Contractor shall be adjudged bankrupt or an order shall be made approving a petition filed by any of the creditors, or, if the Contractor is a corporation, by any of the stockholders of the Contractor, seeking its reorganization or the readjustment of its indebtedness under the federal bankruptcy laws or under any law or statute of the United States or of any State thereof; or
3. A petition under any part of the federal bankruptcy laws or an action under any present or future insolvency law or statute shall be filed against the Contractor and shall not be dismissed within thirty (30) days after the filing thereof; or
4. The interest of the Contractor under this Contract shall be transferred to, passed to or devolve upon, by operation of law or otherwise, any other person, firm or corporation, or
5. The Contractor, if a corporation, shall, without the prior written approval of the Port Authority, become a surviving or merged corporation in a merger, a constituent corporation in a consolidation, or a corporation in dissolution; or
6. If the Contractor is a partnership, and the said partnership shall be dissolved as the result of any act or omission of its copartners or any of them, or by operation of law or the order or decree of any court having jurisdiction, or for any other reason whatsoever; or
7. By or pursuant to, or under authority of any legislative act, resolution or rule, or any order or decree of any court or governmental board, agency or officer having jurisdiction, a receiver, trustee, or liquidator shall take possession or control of all or substantially all of the property of the Contractor and such possession or control of all or substantially all of the property of the Contractor and shall continue in effect for a period of fifteen (15) days;
then upon the occurrence of any such event or at any time thereafter during the continuance thereof, the Port Authority shall have the right upon five (5) days notice to the Contractor to terminate this Contract and the rights of the Contractor hereunder; termination to be effective upon the date and time specified in such notice as if said date were the date of the expiration of this Contract. Termination shall not relieve the Contractor of any liabilities or obligations hereunder which have accrued on or prior to the effective date of termination.
c. If any of the following shall occur:
1. The Contractor shall cease, abandon any part of the service, desert, stop or discontinue its services in the premises for any reason whatsoever and regardless of the fault of the Contractor;
or
2. The Contractor shall fail to keep, perform and observe each and every other promise, covenant and agreement set forth in this Contract on its part to be kept, performed or observed, within five (5) days after receipt of notice of default thereunder from the Port Authority (except where fulfillment of its obligations requires activity over a greater period of time, and the Contractor shall have commenced to perform whatever may be required for fulfillment within five (5) days after receipt of notice and continues such performance without interruption except for causes beyond its control);
then upon the occurrence of any such event or during the continuance thereof, the Port Authority shall have the right on twenty four (24) hours notice to the Contractor to terminate this Contract and the rights of the Contractor hereunder, termination to be effective upon the date and time specified in such notice. Termination shall not relieve the Contractor of any liabilities which shall have accrued on or prior to the effective date of termination.
d. If any of the events enumerated in this Section shall occur prior to commencement date of this
Contract the Port Authority upon the occurrence of any such event or any time thereafter during the continuance thereof by twenty-four (24) hours notice may terminate or suspend this Contract and the rights of the Contractor hereunder, such termination or suspension to be effective upon the date specified in such notice.
e. No payment by the Port Authority of any monies to the Contractor for any period or periods after default of any of the terms, covenants or conditions hereof to be performed, kept and observed by the Contractor and no act or thing done or omitted to be done by the Port Authority shall be deemed to be a waiver of the right of the Port Authority to terminate this Contract or of any other right or remedies to which the Port Authority may be entitled because of any breach thereof. No waiver by the Port Authority of any default on the part of the Contractor in the performance of any of the terms, covenants and conditions hereof to be performed, kept or observed by the Contractor shall be or be construed to be a waiver by the Port Authority of any other subsequent default in the performance of any of the said terms, covenants and conditions.
f. In addition to all other rights of revocation or termination hereunder and notwithstanding any other provision of this Contract the Port Authority may terminate this Contract and the rights of the Contractor hereunder without cause at any time upon five (5) days written notice to the Contractor and in such event this Contract shall cease and expire on the date set forth in the notice of termination as fully and completely as though such dates were the original expiration date hereof and if such effective date of termination is other than the last day of the month, the amount of the compensation due to the Contractor from the Port Authority shall be prorated when applicable on a daily basis. Such cancellation shall be without prejudice to the rights and obligations of the parties arising out of portions already performed but no allowance shall be made for anticipated profits.
g. Any right of termination contained in this paragraph, shall be in addition to and not in lieu of any and all rights and remedies that the Port Authority shall have at law or in equity consequent upon the Contractor's breach of this Contract and shall be without prejudice to any and all such other rights and remedies. It is hereby specifically agreed and understood that the exercise by the Port Authority of any right of termination set forth in this paragraph shall not be or be deemed to be an exercise by the Port Authority of an election of remedies so as to preclude the Port Authority from any right to money damages it may have for the period prior to the effective date of termination to the original expiration date of the Contract, and this provision shall be deemed to survive the termination of this Contract as aforesaid.
h. If (1) the Contractor fails to perform any of its obligations under this Contract or any other agreement between the Port Authority and the Contractor (including its obligation to the Port Authority to pay any claim lawfully made against it by any supplier, subcontractor or worker or other person which arises out of or in connection with the performance of this Contract or any other agreement with the Port Authority) or (2) any claim (just or unjust) which arises out of or in connection with this Contract or any other agreement between the Port Authority and the Contractor is made against the Port Authority or (3) any subcontractor under this Contract or any other agreement between the Port Authority and the Contractor fails to pay any claims lawfully made against it by any supplier, subcontractor, worker or other third person which arises out of or in connection with this Contract or any other agreement between the Port Authority and the Contractor or if in the opinion of the Port Authority any of the aforesaid contingencies is likely to arise, then the Port Authority shall have the right, in its discretion, to withhold out of any payment (final or otherwise) such sums as the Port Authority may deem ample to protect it against delay or loss or to assure the payment of just claims of third persons, and to apply such sums in such manner as the Port Authority may deem proper to secure such protection or satisfy such claims. All sums so applied shall be deducted from the Contractor's compensation. Omission by the Port Authority to withhold out of any payment, final or otherwise, a sum for any of the above contingencies, even though such contingency has occurred at the time of such payment, shall not be deemed to indicate that the Port Authority does not intend to exercise its right with respect to such contingency. Neither the above provisions for rights of the Port Authority to withhold and apply monies nor any exercise or attempted exercise of, or omission to exercise, such rights by the Port Authority shall create any obligation of any kind to such supplier, subcontractors, worker or other third persons. If, however, the payment of any amount due the Contractor shall be improperly delayed, the Port Authority shall pay the Contractor interest thereon at the rate of 6% per annum for the period of the delay, it being agreed that such interest shall be in lieu of and in liquidation of any damages to the Contractor because of such delay.
i. If the Port Authority has paid any sum or has incurred any obligation or expense which the Contractor has agreed to pay or reimburse the Port Authority, or if the Port Authority is required or elects to pay any sum or sums or incurs any obligations or expense by reason of the failure, neglect or refusal of the Contractor to perform or fulfill any one or more of the conditions, covenants, or agreements contained in this Contract, or as a result of an act of omission of the Contractor contrary to the said conditions, covenants and agreements, the Contractor shall pay to the Port Authority the sum or sums so paid or expense so incurred, including all interests, costs and damages, promptly upon the receipt of the Port Authority's statement therefore. The Port Authority may, however, in its discretion, elect to deduct said sum or sums from any payment payable by it to the Contractor.
j. If the Port Authority pays any installment to the Contractor without reducing said installment as provided in this Contract, it may reduce any succeeding installment by the proper amount, or it may bill the Contractor for the amount by which the installment paid should have been reduced and the Contractor shall pay to the Port Authority any such amount promptly upon receipt of the Port Authority's statement therefore.
k. The Port Authority shall also have the rights set forth above in the event the Contractor shall become insolvent or bankrupt or if his affairs are placed in the hands of a receiver, trustee or assignee for the benefit of creditors.
15. Sales or Compensating Use Taxes
Purchases of services and tangible personal property by the Port Authority in the States of New York and New Jersey are generally exempt from state and local sales and compensating use taxes, and from most federal excises (Taxes). Therefore, the Port Authority's purchase of the Contractor's services under this Contract is exempt from Taxes. Accordingly, the Contractor must not include Taxes in the price charged to the Port
Authority for the Contractor's services under this Contract. The Contractor certifies that there are no such taxes included in the prices for this Contract. The Contractor shall retain a copy of this Contract to substantiate the exempt sale.
The compensation set forth in this Agreement is the complete compensation to the Contractor, and the Port Authority will not separately reimburse the Contractor for any taxes unless specifically set forth in this Agreement.
16. No Estoppel or Waiver
The Port Authority shall not be precluded or estopped by any payment, final or otherwise, issued or made under this Contract, from showing at any time the true amount and character of the services performed, or from showing that any such payment is incorrect or was improperly issued or made; and the Port Authority shall not be precluded or estopped, notwithstanding any such payment, from recovering from the Contractor any damages which it may sustain by reason of any failure on its part to comply strictly with this Contract, and any moneys which may be paid to it or for its account in excess of those to which it is lawfully entitled.
No cancellation, rescission or annulment hereof, in whole or as to any part of the services to be provided hereunder, or because of any breach hereof, shall be deemed a waiver of any money damages to which the Port Authority may be entitled because of such breach. Moreover, no waiver by the Authority of any breach of this Contract shall be deemed to be a waiver of any other or any subsequent breach.
17. Records and Reports
The Contractor shall set up, keep and maintain (and shall cause its subcontractors to set up, keep and maintain) in accordance with generally accepted accounting practice during the term of this Agreement and any extensions thereof and for three years after the expiration, termination or revocation thereof, records, payroll records and books of account (including, but not limited to, records of original entry and daily forms, payroll runs, cancelled checks, time records, union agreements, contracts with health, pension and other third party benefit providers) recording all transactions of the Contractor(and its subcontractors), at, through or in any way connected with or related to the operations of the Contractor (and its subcontractors) hereunder, including but not limited to all matters relating to the charges payable to the Contractor hereunder, all wages and supplemental benefits paid or provided to or for its employees (and its subcontractors’ employees) and such additional information as the Port Authority may from time to time and at any time require, and also including, if appropriate, recording the actual number of hours of service provided under the Contract, and keeping separate records thereof. All Contractor records shall be kept in the Port District or in lieu thereof, Contractor may make the records available to the Port Authority in electronic form. The Contractor shall permit (and cause its subcontractors to permit) in ordinary business hours during the term of this Agreement including any extensions thereof and for three years thereafter the examination and audit by the officers, employees and representatives of the Port Authority of such records and books of account and also any records and books of account of any company which is owned or controlled by the Contractor, or which owns or controls the Contractor if said company performs services similar to those performed by the Contractor anywhere in the Port District. However, if within the aforesaid three year period the Port Authority has notified the Contractor in writing of a pending claim by the Port Authority under or in connection with this Contract to which any of the aforesaid records and documents of the Contractor or of its subcontractors relate either directly or indirectly, then the period of such right of access shall be extended to the expiration of six years from the date of final payment with respect to the records and documents involved.
Upon request of the Port Authority, the Contractor shall furnish or provide access to the federal Form I-9 (Employment Eligibility Verification) for each individual performing work under this Contract. This includes citizens and noncitizens.
The Contractor (and its subcontractors) shall, at its own expense, install, maintain and use such equipment and devices for recording the labor hours of the service as shall be appropriate to its business and necessary or desirable to keep accurate records of the same and as the general manager or the Facility Manager may from time to time require, and the Contractor (and its subcontractors) shall at all reasonable times allow inspection by the agents and employees of the Port Authority of all…