4-4. Boulder County Bid Tabulation.pdf

PDF 163 KB Posted

Attached to
28th Street Hub - Drywall Installation and Finishing
Solicitation number
BID-230-26
Issued by
Boulder County, Colorado

About this file

This is a bid tabulation form from Boulder County Building Services, a division of Public Works in Colorado, for drywall installation and finishing work on the 28th Street Community Hub project located at 2525 28th Street, Boulder, Colorado. The scope of work includes drywall (gypsum board) installation and finishing services, with metal stud framing excluded from the contractor's responsibilities. All necessary equipment, materials, and installation services must be provided by the contractor. The project is scheduled to begin in the second quarter of 2026 and be completed by the end of 2026. The bid tabulation requests pricing for Item #1: Drywall & Drywall Finishing, Insulation and Sealants, with contractors required to provide both a cost in dollars and the duration in working days.

Contractors submitting bids may propose alternates on a separate page and may request substitutions for equipment or materials not listed in the specifications, provided the proposed products meet all quality and capacity requirements; certain materials designated as "Basis-of-Design" products cannot be substituted. The architect will respond to substitution requests within seven working days (Monday through Friday) of receipt, and Boulder County Public Works will release an addendum confirming acceptance or rejection. Both a payment bond and a performance bond, each equal to 100 percent of the proposed cost, are required for this project and must be included in the total proposed cost. Boulder County reserves the right to award the contract based on best value to the County, to waive any informalities, or to reject any or all bids.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Boulder County Bid Tabulation

Provide a price for one and/or each item as listed below. Work shall be awarded based on the most responsible Bid that best satisfies the requirements of the project. Boulder County reserves the right to make the award based on the Bid deemed the best value to the County, to waive any informalities, or to reject any or all Bids.

All work described in the Drawings, Specifications and Addenda for this project:

ITEM #1: Drywall & Drywall Finishing, Insulation and Sealants -dollars ($ )

Duration Working Days

See next page for Alternate, Substitution requests and Payment and Performance Bond information.

Alternates: Provide a separate page for any proposed alternates, with description of alternate and any impact on cost or timing of work.

Substitution Requests:

If you wish to submit a bid that would include equipment not listed in equipment schedules or specifications, please submit a substitution request along with bid questions. A substitution request form is not required. Proposed product substitutions must still meet all requirements for quality, capacity, etc., as the listed products. Please note that some materials are “Basis-of- Design” products and cannot be substituted. Refer to the appropriate sections of the specification manual for more information.

Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within 7 working days (M-F) of receipt of a request for substitution. Architect will notify Contractor of acceptance or rejection of proposed substitution within 7 working days (M-F) of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.

Boulder County Public works will release an addendum with acceptance or rejection of proposed substitutions.

Payment and Performance Bond: Both a payment and a performance bond are required for this project and must each equal 100% of the proposed cost. Please include the cost of this bond in the total proposed cost.

dollars:
undefined:
Working Days: