This is a Spin-Cast Rate Sheet for RFP 26-115, On-Call Pipe Lining Services, issued by the City of Alpharetta, Georgia. The City of Alpharetta is soliciting proposals from contractors to provide trenchless stormwater systems rehabilitation services, with plans to award up to two on-call contracts—one for cured-in-place pipe (CIPP) lining and one for spincast lining—for a one-year initial term with four optional one-year renewals. The City has identified over 500 pipes requiring repair, with additional pipes added annually based on inspection results. Offerors must submit one proposal indicating whether they propose to provide CIPP services, spincast services, or both. The sample project detailed in this rate sheet includes quantities for spincast lining across multiple pipe diameters: 97 linear feet (LF) of 30-inch pipe, 340 LF of 36-inch pipe, 580 LF of 42-inch pipe, 300 LF of 48-inch pipe, 375 LF of 54-inch pipe, 87 LF of 60-inch pipe, and 30 LF of 66-inch pipe, all at 1.5-inch thickness with less than 25 percent fullness.
Bidders must complete the rate sheet by entering unit prices for 52 line items covering spincast lining services for various pipe diameters and thicknesses, drainage boxes, precast and cast-in-place concrete headwalls, rubble masonry headwalls, and miscellaneous materials including stone, concrete, and flowable fill. All unit prices must include mobilization, labor, equipment, materials, typical point repairs, pre- and post-CCTV inspections, and cleaning. Lump sum items such as erosion control, landscaping, traffic control, special repairs, pumping operations, ground penetrating radar, and pressure grouting will be determined on a project-by-project basis and provided with each purchase order. No minimum work guarantee is inferred with these contracts, as the City identifies its annual capital budget and prioritizes work based on citywide needs and demands. Bidders must certify independent price determination and acknowledge that proposals cannot be withdrawn within 120 days after the due date.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Spin-Cast Rate Sheet
| RFP 26-115, City of Alpharetta On-Call Pipe Lining Services | |||
| SPIN-CASTING PIPE LINING RATE SHEET ITEMS | |||
| Bidder Name | 0 | ||
| Instructions for Spin-Casting Pipe Lining Rate Sheet Completion: | |||
| 1. This form MUST be used to submit Spin-Casting Rate Sheet and Sample Spin-Casting Project cost. | |||
| 2. Do not include a copy of this Form in your technical proposl information. | |||
| 3. Complete all the fields. See end of this page as well for authorization and contact info. | |||
| 4. Verify all amounts entered. These forms will be used Cost Scoring. | |||
| 5. Enter Unit Price. Form will calculate the Sample Spin-Casting Cost, multiplying Sample Quantities by Unit Prices provided in this Spin-Casting Rate sheet. | |||
| ITEM # | Description | Unit | Unit Price |
| Lining Requirements | |||
| Spin Cast Lining | |||
| Includes Pre & Post TV & typical point repairs during lining | |||
| Includes Cleaning (less than 25% full) | |||
| 1 | 30" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 |
| 2 | 36" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 |
| 3 | 42" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 |
| 4 | 48" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 |
| 5 | 54" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 |
| 6 | 60" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 |
| 7 | 66" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 |
| 8 | 72" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 |
| 9 | Add Cost Per 0.5 Thickness - 30" | LF | $ - 0 |
| 10 | Add Cost Per 0.5 Thickness - 36" | LF | $ - 0 |
| 11 | Add Cost Per 0.5 Thickness - 42" | LF | $ - 0 |
| 12 | Add Cost Per 0.5 Thickness - 48" | LF | $ - 0 |
| 13 | Add Cost Per 0.5 Thickness - 54" | LF | $ - 0 |
| 14 | Add Cost Per 0.5 Thickness - 60" | LF | $ - 0 |
| 15 | Add Cost Per 0.5 Thickness - 66" | LF | $ - 0 |
| 16 | Add Cost Per 0.5 Thickness - 72" | LF | $ - 0 |
| Spin Cast Lining | |||
| Includes Pre & Post TV & typical point repairs during lining | |||
| Includes Cleaning (greater than 25% full) | |||
| 17 | 30" Centrifugal Spin- 1.5 Thickness | LF | $ - 0 |
| 18 | 36" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 |
| 19 | 42" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 |
| 20 | 48" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 |
| 21 | 54" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 |
| 22 | 60" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 |
| 23 | 66" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 |
| 24 | 72" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 |
| 25 | Add Cost Per 0.5 Thickness - 30" | LF | $ - 0 |
| 26 | Add Cost Per 0.5 Thickness - 36" | LF | $ - 0 |
| 27 | Add Cost Per 0.5 Thickness - 42" | LF | $ - 0 |
| 28 | Add Cost Per 0.5 Thickness - 48" | LF | $ - 0 |
| 29 | Add Cost Per 0.5 Thickness - 54" | LF | $ - 0 |
| 30 | Add Cost Per 0.5 Thickness - 60" | LF | $ - 0 |
| 31 | Add Cost Per 0.5 Thickness - 66" | LF | $ - 0 |
| 32 | Add Cost Per 0.5 Thickness - 72" | LF | $ - 0 |
| Spin Cast Lining for Drainage Boxes | |||
| 33 | 48" Drainage box | VF | $ - 0 |
| 34 | 60" Drainage box | VF | $ - 0 |
| 35 | 72" Drainage box | VF | $ - 0 |
| Precast Headwalls (per Alpharetta Std 232) | |||
| 36 | Precast Headwall for 18" Pipe | EA | $ - 0 |
| 37 | Precast Headwall for 24" Pipe | EA | $ - 0 |
| 38 | Precast Headwall for 30" Pipe | EA | $ - 0 |
| 39 | Precast Headwall for 36" Pipe | EA | $ - 0 |
| 40 | Precast Headwall for 42" Pipe | EA | $ - 0 |
| 41 | Precast Headwall for 48" Pipe | EA | $ - 0 |
| Cast-In_Place Concrete Headwall | |||
| 42 | Cast-n-Place Conc HW-GDOT Det 1125 | CY | $ - 0 |
| Rubble Masonry HW | |||
| 43 | Rubble Headwall for 18" Pipe | EA | $ - 0 |
| 44 | Rubble Headwall for 24" Pipe | EA | $ - 0 |
| 45 | Rubble Headwall for 30" Pipe | EA | $ - 0 |
| 46 | Rubble Headwall for 36" Pipe | EA | $ - 0 |
| Miscellaneous Items | |||
| 47 | Stone #57 | Ton | $ - 0 |
| 48 | Surge Stone | Ton | $ - 0 |
| 49 | No.3's and 4's Stone | Ton | $ - 0 |
| 50 | Reset Existing Headwall | EA | $ - 0 |
| 51 | 3000psi Concrete | CY | $ - 0 |
| 52 | Flowable Fill | CY | $ - 0 |
| NOTES | |||
| All unit prices shall include but not be limited to all mobilization, labor, equipment and materials necessary to perform the work. In addition, unit prices for pipe lining shall include typical point repairs, pre and post CCTV, and cleaning (less than 25% full & greater than 25%). |
| Lump sum items will be determined on a project by project basis and include but not be limited to erosion control, landscaping, traffic control, special internal and external point repairs, pumping operations, ground penetrating radar and pressure grouting. These items will be included with proposals prior to each purchase order for lining projects. | |
| By completing and submitting this Spin-Casting Pipe Lining rate sheet form in response to the City of Alpharetta's RFP 26-115, Contractor certifies that: | |
| A. Contractor has carefully read and understands RFP Documents and Scope of Work; | |
| B. Contractor understands that proposal may not be withdrawn within one hundred twenty (120) days after due date, and Contractor guarantees that the City has the right to waive informalities and irregularities in proposal received and to accept the proposal which, in City’s judgment, is in City’s own best interests. | |
| Certificate of Independent Price Determination: By submitting a bid in response to RFP 26-115, the authorized signer below certifies to the following: | |
| I certify that this bid is made without prior understanding, agreement, or connection with any corporation, firm, or person submitting a bid for the same materials, supplies, services, or equipment and is in all respects fair and without collusion or fraud. I understand collusive bidding is a violation of state and federal law and can result in fines, prison sentences, and civil damage awards. I agree to abide by all conditions of this bid and certify that I am authorized to sign this bid for the bidder or offeror. | |
| Bidder Name: | |
| Address: | |
| Name, Title Authorized Signer: | |
| Contact Info - Phone Number: | |
| Contact Info - Email Address: |
&P OF &N
Sample Project Cost
| SAMPLE PROJECT SPIN-CASTING PIPE LINING | |||||
| RFP 26-115, City of Alpharetta On-Call Pipe Lining Services | |||||
| Add Bidder Name | Sample Project Total | $ - 0 | |||
| ITEM # | Description | Unit | Unit Price | Quantity | Price |
| Lining Requirements | |||||
| Spin Cast Lining | |||||
| Includes Pre & Post TV & typical point repairs during lining | |||||
| Includes Cleaning (less than 25% full) | |||||
| 1 | 30" Centrifugal Spin- 1.5 Thickness | LF | $ - 0 | 97 | $ - 0 |
| 2 | 36" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 | 340 | $ - 0 |
| 3 | 42" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 | 580 | $ - 0 |
| 4 | 48" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 | 300 | $ - 0 |
| 5 | 54" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 | 375 | $ - 0 |
| 6 | 60" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 | 87 | $ - 0 |
| 7 | 66" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 | 30 | $ - 0 |
| 8 | 72" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 | 0 | $ - 0 |
| 9 | Add Cost Per 0.5 Thickness - 30" | LF | $ - 0 | 0 | $ - 0 |
| 10 | Add Cost Per 0.5 Thickness - 36" | LF | $ - 0 | 0 | $ - 0 |
| 11 | Add Cost Per 0.5 Thickness - 42" | LF | $ - 0 | 0 | $ - 0 |
| 12 | Add Cost Per 0.5 Thickness - 48" | LF | $ - 0 | 0 | $ - 0 |
| 13 | Add Cost Per 0.5 Thickness - 54" | LF | $ - 0 | 0 | $ - 0 |
| 14 | Add Cost Per 0.5 Thickness - 60" | LF | $ - 0 | 0 | $ - 0 |
| 15 | Add Cost Per 0.5 Thickness - 66" | LF | $ - 0 | 0 | $ - 0 |
| 16 | Add Cost Per 0.5 Thickness - 72" | LF | $ - 0 | 0 | $ - 0 |
| Spin Cast Lining | |||||
| Includes Pre & Post TV & typical point repairs during lining | |||||
| Includes Cleaning (greater than 25% full) | |||||
| 17 | 30" Centrifugal Spin- 1.5 Thickness | LF | $ - 0 | 0 | $ - 0 |
| 18 | 36" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 | 0 | $ - 0 |
| 19 | 42" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 | 0 | $ - 0 |
| 20 | 48" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 | 0 | $ - 0 |
| 21 | 54" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 | 0 | $ - 0 |
| 22 | 60" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 | 0 | $ - 0 |
| 23 | 66" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 | 0 | $ - 0 |
| 24 | 72" Centrifugal Spin - 1.5 Thickness | LF | $ - 0 | 0 | $ - 0 |
| 25 | Add Cost Per 0.5 Thickness - 30" | LF | $ - 0 | 0 | $ - 0 |
| 26 | Add Cost Per 0.5 Thickness - 36" | LF | $ - 0 | 0 | $ - 0 |
| 27 | Add Cost Per 0.5 Thickness - 42" | LF | $ - 0 | 0 | $ - 0 |
| 28 | Add Cost Per 0.5 Thickness - 48" | LF | $ - 0 | 0 | $ - 0 |
| 29 | Add Cost Per 0.5 Thickness - 54" | LF | $ - 0 | 0 | $ - 0 |
| 30 | Add Cost Per 0.5 Thickness - 60" | LF | $ - 0 | 0 | $ - 0 |
| 31 | Add Cost Per 0.5 Thickness - 66" | LF | $ - 0 | 0 | $ - 0 |
| 32 | Add Cost Per 0.5 Thickness - 72" | LF | $ - 0 | 0 | $ - 0 |
| Spin Cast Lining for Drainage Boxes | |||||
| 33 | 48" Drainage box | VF | $ - 0 | 0 | $ - 0 |
| 34 | 60" Drainage box | VF | $ - 0 | 0 | $ - 0 |
| 35 | 72" Drainage box | VF | $ - 0 | 0 | $ - 0 |
| Precast Headwalls (per Alpharetta Std 232) | |||||
| 36 | Precast Headwall for 18" Pipe | EA | $ - 0 | 0 | $ - 0 |
| 37 | Precast Headwall for 24" Pipe | EA | $ - 0 | 0 | $ - 0 |
| 38 | Precast Headwall for 30" Pipe | EA | $ - 0 | 0 | $ - 0 |
| 39 | Precast Headwall for 36" Pipe | EA | $ - 0 | 0 | $ - 0 |
| 40 | Precast Headwall for 42" Pipe | EA | $ - 0 | 0 | $ - 0 |
| 41 | Precast Headwall for 48" Pipe | EA | $ - 0 | 0 | $ - 0 |
| Cast-In_Place Concrete Headwall | |||||
| 42 | Cast-n-Place Conc HW-GDOT Det 1125 | CY | $ - 0 | 0 | $ - 0 |
| Rubble Masonry HW | |||||
| 43 | Rubble Headwall for 18" Pipe | EA | $ - 0 | 0 | $ - 0 |
| 44 | Rubble Headwall for 24" Pipe | EA | $ - 0 | 0 | $ - 0 |
| 45 | Rubble Headwall for 30" Pipe | EA | $ - 0 | 0 | $ - 0 |
| 46 | Rubble Headwall for 36" Pipe | EA | $ - 0 | 0 | $ - 0 |
| Miscellaneous Items | |||||
| 47 | Stone #57 | Ton | $ - 0 | 0 | $ - 0 |
| 48 | Surge Stone | Ton | $ - 0 | 0 | $ - 0 |
| 49 | No.3's and 4's Stone | Ton | $ - 0 | 0 | $ - 0 |
| 50 | Reset Existing Headwall | EA | $ - 0 | 0 | $ - 0 |
| 51 | 3000psi Concrete | CY | $ - 0 | 0 | $ - 0 |
| 52 | Flowable Fill | CY | $ - 0 | 0 | $ - 0 |
| NOTES | |||||
| All unit prices shall include but not be limited to all mobilization, labor, equipment and materials necessary to perform the work. In addition, unit prices for pipe lining shall include typical point repairs, pre and post CCTV, and cleaning (less than 25% full & greater than 25%). | |||||
| Lump sum items will be determined on a project by project basis and include but not be limited to erosion control, landscaping, traffic control, special internal and external point repairs, pumping operations, ground penetrating radar and pressure grouting. These items will be included with proposals prior to each purchase order for lining projects. |
File details come from the government source that posted it. Updated .