3c_Statement of Work.pdf
PDF 872 KB Posted
- Solicitation number
- 75110PR270000104
- Issued by
- Not on record
About this file
This is a Statement of Work (SOW) for gas leak detection, repair, valve installation, and asphalt patching services at the United States Coast Guard Training Center Birmingham Southern, located at 900 Arkadelphia Road, Birmingham, AL 35204.
The Contractor must complete excavation and repair of an identified gas leak in the parking lot within a firm-fixed-price contract structure. Specific tasks include: saw-cutting and excavating a 6-foot by 6-foot hole to locate and access the leaking gas line; hauling off all excavated spoils; providing and placing clean gravel backfill; furnishing and installing a new gas valve suitable for the existing gas service and compliant with applicable codes; pressure-testing or verifying the integrity of the repaired line and valve; and patching the asphalt surface to match existing pavement specifications with proper compaction and finishing. All work must be completed within ten (10) business days from the date of contract award. The SOW excludes private line locating, rock removal, slab x-ray, underground utility work beyond the specified gas leak repair, sewer or water main fees, and landscaping. The Government will furnish line locating services performed by others prior to excavation; the Contractor must furnish all other facilities, materials, equipment, tools, labor, and services.
The Contractor must designate a Project Manager serving as the single point of contact, available via telephone between 0700-1700 Central Time Monday through Friday with four-hour response time for technical issues. The Contractor must provide daily progress updates via email to the Government Technical Representative (GTR) and submit a final completion report within two business days after final acceptance. A Post Award Conference must occur within two business days of award to discuss technical objectives, review the proposed schedule, confirm line-locate status, and coordinate site access. Work must generally occur between 0700-1700 Central Time, Monday through Friday, except Federal holidays, unless otherwise approved by the GTR. The GTR will conduct a final walk-through inspection and has two business days to complete final inspection after contractor notification of completion. All deliverables, including the completed physical work and final completion report, must be submitted in electronic format compatible with Microsoft Office applications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 7m_Wage Determination.pdf | ||
| 12a_Provision and Clauses.pdf | ||
| 12a_Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
October 28, 2026 | Page 1 of 8
STATEMENT OF WORK (SOW)
FOR
GAS LEAK DETECTION, REPAIR, VALVE INSTALLATION, AND ASPHALT
PATCHING SERVICES
1.0 GENERAL
1.1 Background
A gas leak has been identified in the parking lot at United Stated Coast Guard Training Center
Birmingham Southern, 900 Arkadelphia Road, Birmingham, AL. Immediate repair is required to ensure safety, prevent further damage or hazard, and restore normal operations of the gas line and parking area. This requirement is for a firm-fixed-price construction-type services effort consisting of excavation, gas valve installation, backfill, and asphalt restoration.
This project is pursued to eliminate the safety hazard associated with the gas leak and to return the affected parking lot area to full operational use.
1.2 Scope
The Contractor must perform all labor, supervision, materials, equipment, tools, and services necessary to complete the following work under this firm-fixed-price contract:
• After line locate performed by others, saw-cut and excavate a 6-foot by 6-foot hole in the parking lot to locate the gas leak;
• Haul off all spoils from the site;
• Bring in and place gravel to backfill the excavation;
• Install a gas valve in the parking lot;
• Patch the asphalt surface upon completion of the underground work.
This SOW does not include private line locating, rock removal, slab x-ray, any underground utility work for electrical, gas, or irrigation systems beyond the specified gas leak repair and valve installation, sewer impact fees, water main fees, or landscaping. The Contractor is not responsible for any damage to unmarked utilities.
1.3 OBJECTIVE
The objective of this firm-fixed-price requirement is to safely locate and repair the gas leak, install a gas valve, restore the excavated area with gravel backfill, and complete asphalt patching so that the parking lot surface and gas system are fully operational, safe, and ready for use. All work under this contract must be completed no later than ten (10) business days after the date of contract award.
1.4 APPLICABLE DOCUMENTS
The Contractor must comply with all applicable federal, state, and local laws, codes, ordinances, and regulations governing excavation, gas-line repair, pressure testing, and asphalt paving work, including but not limited to Occupational Safety and Health Administration (OSHA) standards and the applicable Alabama state and local plumbing and gas codes.
October 28, 2026 | Page 2 of 8
2.0 SPECIFIC REQUIREMENTS/TASKS
The Contractor must perform the following tasks. This is a firm-fixed-price contract. The
Contractor is solely responsible for the means, methods, techniques, sequences, and procedures of construction and for coordinating all portions of the work. The Government will not supervise or direct the Contractor’s employees. Performance will be measured by successful completion of the defined tasks and acceptance of the completed work.
2.1 TASK ONE. Excavation to Locate and Access Gas Leak
a. Saw-cut a clean, straight cut in the parking lot asphalt;
b. Excavate a 6-foot by 6-foot hole of sufficient depth to locate and fully expose the leaking gas line;
c. Haul off all excavated spoils from the site;
d. Provide and place clean gravel backfill material suitable for the subsequent asphalt patch.
2.2 TASK TWO. Gas Valve Installation
The Contractor must furnish and install a new gas valve in the parking lot at the location of the repair. The valve must be of a type and rating suitable for the existing gas service, installed in accordance with applicable codes, and left in a fully operational condition. The Contractor must pressure-test or otherwise verify the integrity of the repaired line and valve as required by applicable codes before backfill is completed.
2.3 TASK THREE. Asphalt Patching
After successful installation, testing, and gravel backfill, the Contractor must patch the asphalt surface of the 6-foot by 6-foot excavated area. The patch must be of material and thickness matching the existing parking lot pavement, properly compacted, and finished flush with the surrounding surface to provide a smooth, durable, and safe driving surface.
2.4 TASK FOUR. Site Cleanup and Demobilization
The Contractor must remove all debris, excess materials, equipment, and temporary facilities from the site and leave the work area in a clean, orderly condition acceptable to the
Government Technical Representative (GTR)
3.0 CONTRACTOR PERSONNEL
This requirement is task-oriented and is not a personal services contract. The Contractor must provide qualified personnel to perform all requirements specified in this SOW. The Government will not supervise, direct, or control the Contractor’s employees. The Contractor retains full responsibility for the direction, supervision, and control of its workforce.
3.1 QUALIFIED PERSONNEL
The Contractor must provide personnel who are qualified, licensed (as required by the State of
Alabama), and experienced in gas-line excavation, repair, valve installation, and asphalt patching to perform all requirements specified in this SOW.
3.2 CONTINUITY OF SUPPORT
October 28, 2026 | Page 3 of 8
The Contractor must maintain the contractually required level of support necessary to complete all work within the period of performance. If any Contractor personnel become unavailable, the
Contractor must provide a fully qualified replacement at no additional cost to the Government so that the schedule is not impacted.
3.3 PROJECT MANAGER
The Contractor must designate a Project Manager (or on-site supervisor) who must serve as the single point of contact for the Contracting Officer and the GTR for the duration of the work. The name and contact information of the Project Manager must be provided to the Government at the Post Award Conference. The Project Manager must be available during working hours and must have authority to make decisions on behalf of the Contractor concerning the work.
The Project Manager must be available to the GTR via telephone between the hours of 0700 and 1700 Central Time, Monday through Friday, and must respond to a request for discussion or resolution of technical problems within four (4) hours of notification.
3.4 EMPLOYEE IDENTIFICATION
Contractor employees working on-site must identify themselves as Contractor personnel and must display company identification while on the premises.
3.5 EMPLOYEE CONDUCT
Contractor employees must comply with all applicable Government and site regulations, policies, and procedures concerning safety, security, and conduct. The Contractor must ensure that its employees present a professional appearance and that their conduct does not reflect discredit on the United States or the Department of Homeland Security / United States Coast
Guard.
3.6 REMOVING EMPLOYEES FOR MISCONDUCT OR SECURITY REASONS
The Government may, at its sole discretion (via the Contracting Officer), direct the Contractor to remove any Contractor employee from the work site for misconduct or security reasons.
Removal does not relieve the Contractor of the responsibility to continue providing the services required under the contract. The Contracting Officer will provide the Contractor with a written explanation to support any request to remove an employee.
4.0 OTHER APPLICABLE CONDITIONS
4.1 SECURITY
Contractor access to classified information is not required under this SOW.
4.2 Period of Performance
The period of performance for this firm-fixed-price contract must not exceed ten (10) business days from the date of award. All work, including final cleanup and demobilization, must be completed within this period.
4.3 PLACE OF PERFORMANCE
October 28, 2026 | Page 4 of 8
The primary place of performance is the parking lot at Coast Guard Training Center Birmingham
Southern, 900 Arkadelphia Road, Birmingham, AL 35204.
4.4 HOURS OF OPERATION
Contractor employees must generally perform work between the hours of 0700 and 1700
Central Time, Monday through Friday (except Federal holidays), unless otherwise approved in advance by the GTR. Work outside these hours may be required for safety or operational reasons and must be coordinated with the GTR.
4.5 POST AWARD CONFERENCE
The Contractor must attend a Post Award Conference with the Contracting Officer and the GTR no later than two (2) business days after the date of award. The purpose of the Post Award
Conference is to discuss technical and contracting objectives, review the Contractor’s proposed schedule, confirm line-locate status, and coordinate site access. The Post Award Conference may be held at the place of performance, at a Government facility, or via teleconference as determined by the Contracting Officer.
4.6 PROGRESS REPORTS
The Project Manager must provide a daily progress update (e-mail is acceptable) to the GTR summarizing work performed, any issues encountered, and the projected completion date. A final completion report summarizing the work performed, materials used, and any as-built information must be submitted within two (2) business days after final acceptance.
4.7 PROGRESS MEETINGS
The Project Manager must be available to meet with the GTR upon request (on-site or by telephone) to discuss progress, exchange information, and resolve any technical issues. At a minimum, a final walk-through inspection will be conducted prior to acceptance.
4.8 GENERAL REPORT REQUIREMENTS
The Contractor must provide all written reports in electronic format compatible with Microsoft
Office applications.
5.0 GOVERNMENT FURNISHED RESOURCES
Line locating services will be performed by others (Government or host facility) prior to excavation. The Contractor must not begin excavation until the line locate has been completed and marked. The Government will not furnish any other property, equipment, materials, or supplies. The Contractor must furnish all facilities, materials (including the gas valve, gravel, and asphalt), equipment, and services necessary to fulfill the requirements of this contract.
The Contractor must use any Government-furnished information only for performance of work under this contract.
6.0 CONTRACTOR FURNISHED PROPERTY
October 28, 2026 | Page 5 of 8
The Contractor must furnish all facilities, materials, equipment, tools, labor, and services necessary to fulfill the requirements of this contract, except for the line locating services identified in Section 5.0.
7.0 GOVERNMENT ACCEPTANCE PERIOD
The GTR will review the completed work and deliverables prior to acceptance and will provide the Contractor with documented reasons for non-acceptance if applicable. If the work is acceptable, the GTR will notify the Contractor in writing (e-mail is acceptable) that the work has been accepted.
7.1 The GTR will have the right to reject or require correction of any deficiencies found in the work that are contrary to the requirements of this SOW or applicable codes. In the event of rejected work, the Contractor will be notified in writing of the specific reasons for rejection. The Contractor must correct the rejected work at no additional cost to the Government and re-present it for acceptance within the period of performance or as otherwise directed.
7.2 The GTR will have two (2) business days to complete the final inspection after notification by the Contractor that the work is complete. The Contractor must correct any punch-list items within two (2) business days of notification.
7.3 Final acceptance of the completed gas-leak repair, valve installation, and asphalt patch constitutes the primary acceptance of the contract effort.
8.0 DELIVERABLES
The Contractor must consider items in BOLD as having mandatory due dates. The completed physical work (repaired gas line, installed valve, and asphalt patch) is the primary deliverable.
ITEM SOW
REFERENCE DELIVERABLE / EVENT DUE BY DISTRIBUTION
1 4.5 Post Award Conference No later than 2 business days after award
GTR, Contracting Officer
2 4.5 Draft Project Schedule At Post Award Conference GTR, Contracting Officer
3 4.5 Final Project Schedule 1 business day after Post Award Conference
GTR, Contracting Officer
4 4.6 Daily Progress Updates Daily during performance GTR
5 2.0–2.4 Completed Gas Leak Repair, Valve Installation, Gravel Backfill, and Asphalt Patch
Within 10 business days after award
GTR (via final inspection)
6 4.6 Final Completion Report Within 2 business days after final acceptance
GTR, Contracting Officer
7 7.0 Final Walk-through / Acceptance Inspection Upon Contractor notification of completion
GTR, Contracting Officer
October 28, 2026 | Page 6 of 8
9.0 Location – Approximate Location of Gas Line
October 28, 2026 | Page 7 of 8
October 28, 2026 | Page 8 of 8