Addenda_2.docx
DOCX document 20 KB Posted
- Attached to
- Fabrication of PIP-II GMPS CAPACITORS
- Solicitation number
- 383185-RK
About this file
This is an addenda to Solicitation No. 383185-RK issued by Fermi National Accelerator Laboratory (FNAL), a Department of Energy facility managed by Fermi Forward Discovery Group, LLC. The addenda, issued on August 18, 2026, modifies key requirements for the fabrication of PIP-II Booster GMPS Power Supply Girder Resonant Capacitors. The RFP quantity has been reduced from 700 units to 500 units, and all additional spares have been removed from the requirement. The deadline for submitting questions has been extended to August 21, 2026, at 4:00 p.m. CDT, and the proposal due date has been extended to August 28, 2026, at 2:00 p.m. CDT. Bidders must acknowledge receipt of this amendment via email to the FFDG Procurement Specialist Richard Konan at rkonan@fnal.gov or by telephone at (630) 840-2835.
Bidders are required to use the updated form contained in the revised RFP document attached to this addenda. All other terms and conditions of the original solicitation remain unchanged. This amendment is part of Fermilab's Proton Improvement Plan II (PIP-II) project, which supports the development of the world's most intense high-energy neutrino beam for the international Deep Underground Neutrino Experiment at LBNF.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDA TO SOLICITATION
| ADDENDA NO. |
| 02 |
| DATE OF AMENDMENT: AUGUST 18, 2026 |
| SOLICITATION NO. | |
| 383185-RK | |
| DATE ISSUED: | AUGUST 18, 2026 |
PROJECT NO.
PROPOSAL DUE DATE: AUGUST 28, 2026
| TITLE OF PROJECT: |
| PIP-II BOOSTER GMPS CAPACITORS |
Bidders must acknowledge this amendment immediately upon receipt by one of the following methods:
· Via email to the FFDG Procurement Specialist
1) Please note the following changes to the RFP 383185-RK:
· The RFP quantity has been reduced from 700 to 500
· The additional spares have been removed
· The last day for questions has been extended to August 21, 2026, 4p CDT
· The due date has been extended to August 28, 2026, 2p CDT
2) PLEASE USE THE UPDATED FORM FROM THE REVISED RFP DOCUMENT ATTACHED HEREIN
ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED.
Fermi National Accelerator Laboratory P.O. Box 500 Batavia, IL 60510 M.S 210
Richard Konan PIP-II Procurement Specialist III
(630) 840-2835 Email: rkonan@fnal.gov
File details come from the government source that posted it. Updated .