12a - REVISED STATEMENT OF WORK 19OCT23.doc
DOC document 252 KB Posted
- Attached to
- SECTOR LAKE MICHIGAN SNOW PLOWING
- Solicitation number
- 37240PR230000079
About this file
This statement of work outlines snow removal and de-icing services required at the United States Coast Guard Sector Lake Michigan facility over the 2023-2024 winter season. The contractor will be responsible for plowing approximately 2.7 acres of paved surfaces and sidewalks when snow accumulation reaches or exceeds one inch. Additional requirements include shoveling sidewalks and entrances, applying de-icing salt as needed, and removing snow to designated pile areas. The contractor must monitor weather conditions and be prepared to respond to snow events day or night throughout the contract period from November 1st through April 30th. The contractor will provide all necessary labor, equipment and materials to complete the work while ensuring safety of personnel and protecting government property.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 12a - SF 30 - AMENDMENT OF SOLICITATION 2.pdf | ||
| 12a - RFI VENDOR QUESTION AND ANSWER 2.docx | DOCX document | |
| 12a - RFI VENDOR QUESTION AND ANSWER - EXAMPLE.docx | DOCX document | |
| 12A - SF 30 - AMENDMENT OF SOLICITATION.pdf | ||
| 12a - SITE VISIT INFORMATION.pdf | ||
| PAST PERFORMANCE EVALUATION.docx | DOCX document | |
| STATEMENT OF WORK.doc | DOC document | |
| WAGE DETERMINATION.pdf | ||
| FAR MATRIX - SERVICE.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
FOR
USCG SECTOR LAKE MICHIGAN
Snow Removal/De-Icing Winter Season 2023/2024
1.0 GENERAL
The United States Coast Guard (USCG) is seeking a qualified contractor to provide annual snow removal and de-icing services at USCG Sector Lake Michigan located at 2420 S. Lincoln Memorial Drive, Milwaukee, Wisconsin.
Any measurements included in this document are estimates for reference purposes only. Bidders are responsible for visiting the site to field-verify existing conditions and determine actual dimensions and the nature of the work required.
The USCG Sector Lake Michigan Facility Engineering Officer will be the USCG’s Onsite Representative for this project. Arrange pre-bid site visits to verify existing conditions by sending an email to: Jason.M.Smith@uscg.mil
2.0 BACKGROUND
USCG Sector Lake Michigan has approximately 2.7 acres of paved surfaces and sidewalks that must be kept free of snow and ice during the winter. Figure 1 shows the areas that must be kept clear as well as acceptable snow pile areas.
Figure 1: USCG Sector Lake Michigan
3.0 OBJECTIVE
Maintain all paved surfaces and sidewalks free of snow and ice for the duration of the winter snow season.
4.0 SCOPE
1. The Contractor shall provide all labor, materials and equipment needed for snow plowing, shoveling, and de-icing (salt application) services for USCG Sector Lake Michigan.
2. The work area includes all paved surfaces and sidewalks within the fence line at the site as well as the entrance and exit driveways and the horseshoe drive/parking area in the front of the building along S. Lincoln Memorial Drive.
3. The Contractor shall install markers as needed to prevent damage to curbs, hydrants, or landscaping.
4. The Contractor shall monitor weather conditions in Milwaukee and shall commence snow clearing operations when accumulation is anticipated to or reaches/exceeds one inch (1”). Paved surfaces and sidewalks will be maintained free of snow and ice for the duration of each snow event. Depending on the duration of the snowfall, the Contractor may need to clear snow multiple times during a single snow event.
5. Snow shall be cleared to a 95% standard at the conclusion of a snow event.
6. Sidewalks, doors/entrances, gates, and areas in front of fire hydrants will be shoveled clear of snow.
7. Cleared snow shall be moved to the snow pile areas indicated in figure 1.
8. Snow shall not be pushed into Lake Michigan.
9. The Contractor shall apply de-icing agents (salt) as needed to prevent slippery conditions. Care shall be taken to apply only the minimal amount of de-icing agent needed. Over-use of de-icing agent is not permitted.
10. Special precautions shall be taken to ensure that de-icing agents or material or debris generated during the performance of this contract do not enter Lake Michigan.
11. No snow is to be piled or allowed to accumulate in any fire lane, near fire hydrants, or adjacent to any building within the plowing area.
12. Work shall not proceed when weather conditions are detrimental to execution of the work.
13. The Contractor shall ensure precautions are taken prior to and during snow removal to ensure the safety of Contractor personnel and USCG personnel and property.
14. The Contractor shall be responsible for restoring any damaged property or equipment caused by the contractor or the contractor’s employees. The restoration shall be to its original condition at no additional cost to the Government. It is recommended that Contractor inspect the grounds prior to the start of work and document any pre-existing damage.
15. Cleanup. Upon completion of this contract, the Contractor is responsible for the clean-up of the grounds where excess salt, dirt and debris has built up from winter plowing. Reseeding and leveling of any areas where plowing may have damaged shall be completed before final payment is made. The Contractor shall remove all markers and equipment at the conclusion of this contract.
5.0 CONTRACTOR PERSONNEL
1. Contractor shall provide a list of employee names to the Coast Guard On Site Representative for access to the base.
2. All Contractor Employees shall present valid ID to the Officer of the Day at the entrance to the base.
6.0 QUALIFIED PERSONNEL
The Contractor shall provide qualified personnel to perform all requirements specified in this SOW.
7.0 CONTINUITY OF SUPPORT
The Contractor shall ensure that the contractually required level of support for this requirement is maintained at all times.
8.0 EMPLOYEE CONDUCT
Contractor’s employees shall comply with all applicable Government regulations, policies, and procedures (e.g., fire, safety, sanitation, environmental protection, security, “off limits” areas, wearing of parts of DHS uniforms, and possession of weapons) when visiting or working at Government facilities. The Contractor shall ensure Contractor employees present a professional appearance at all times and that their conduct shall not reflect discredit on the United States or the Department of Homeland Security. The Contractor shall ensure Contractor employees understand and abide by Department of Homeland Security established rules, regulations and policies concerning safety and security.
9.0 REMOVING EMPLOYEES FOR MISCONDUCT OR SECURITY REASONS
The Government may, at its sole discretion (via the Contracting Officer*), direct the Contractor to remove any Contractor employee from DHS facilities for misconduct or security reasons. Removal does not relieve the Contractor of the responsibility to continue providing the services required under the contract. The Contracting Officer will provide the Contractor with a written explanation to support any request to remove an employee.
10.0 PERIOD OF PERFORMANCE
The period of performance for this contract shall be the entire winter snow season, from November 1st through April 31st, unless otherwise approved by the contracting officer.
11.0 PLACE OF PERFORMANCE
USCG Sector Lake Michigan
2420 South Lincoln Memorial Dr.
Milwaukee, WI 53207
12.0 HOURS OF OPERATION
24 hours per day: Snow removal may be required any time of day or night for the duration of the contract. The duration and level of services required for each snow event will vary.
13.0 GOVERNMENT FURNISHED RESOURCES
The Government will not furnish any resources to the Contractor in support of this contract.
14.0 CONTRACTOR FURNISHED PROPERTY
The Contractor shall furnish all facilities, materials, equipment, and services necessary to fulfill the requirements of this contract.
15.0 GOVERNMENT ACCEPTANCE PERIOD
The COR will review any deliverables prior to acceptance and provide the contractor with an e-mail that provides documented reasons for non-acceptance. If the deliverable is acceptable, the COR will send an e-mail to the Contractor notifying it that the deliverable has been accepted.
The COR will have the right to reject or require correction of any deficiencies found in the deliverables that are contrary to the information contained in the Contractor’s accepted proposal. In the event of a rejected deliverable, the Contractor will be notified in writing by the COR of the specific reasons for rejection. The Contractor may have an opportunity to correct the rejected deliverable and return it per delivery instructions.
The Contractor shall have 10 business days to make corrections and redeliver.