36E77619B0013-0004001.pdf

PDF Posted

Attached to
Repair Roofs on Buildings 1, 3, 4 Roofs Salisbury
Solicitation number
36E77619B0013
Issued by

About this file

36E77619B0013 0004 S05 - Technical Questions.pdf

View the file

Other files

File Type Posted
36E77619C0083-000.docx DOCX document
36E77619B0013-0005000.docx DOCX document
36E77619B0013-0005000.docx DOCX document
36E77619B0013-0004000.docx DOCX document
36E77619B0013-0004002.pdf PDF
36E77619B0013-0004000.docx DOCX document
36E77619B0013-0004001.pdf PDF
36E77619B0013-0004002.pdf PDF
36E77619B0013-0003002.pdf PDF
36E77619B0013-0003001.pdf PDF
36E77619B0013-0003000.docx DOCX document
36E77619B0013-0003000.docx DOCX document
36E77619B0013-0003002.pdf PDF
36E77619B0013-0003001.pdf PDF
36E77619B0013-0002000.docx DOCX document
36E77619B0013-0002000.docx DOCX document
36E77619B0013-0001001.pdf PDF
36E77619B0013-0001001.pdf PDF
36E77619B0013-0001000.docx DOCX document
36E77619B0013-0001000.docx DOCX document
36E77619B0013-005.pdf PDF
36E77619B0013-003.docx DOCX document
36E77619B0013-004.pdf PDF
36E77619B0013-006.docx DOCX document
36E77619B0013-002.docx DOCX document
36E77619B0013-008.pdf PDF
36E77619B0013-007.docx DOCX document
36E77619B0013-002.docx DOCX document
36E77619B0013-003.docx DOCX document
36E77619B0013-007.docx DOCX document
36E77619B0013-005.pdf PDF
36E77619B0013-008.pdf PDF
36E77619B0013-006.docx DOCX document
36E77619B0013-004.pdf PDF
36E77619B0013-001.docx DOCX document
36E77619B0013-001.docx DOCX document
36E77619B0013-000.docx DOCX document
36E77619B0013-000.docx DOCX document
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION # 36E77619B0013 PROJECT NAME: Roof Replacement Buildings 1,3, & 4 - Salisbury VA

TEC HNICAL QUESTIONS AND VA RESPONSE TRACKING SHEET

ITEM

NO.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

1. 8/28/19 Could the government provide an asbestos report?

N/A-no asbestos has been discovered in other on-going roofing projects on the campus

2. 8/28/19 With the size of the project, and the amount of coordination that will be needed, we do not feel 120 calendar days will be adequate. Could performance period be extended to 150 calendar days?

P.O.P to be increased to 150 calendar days

3. 8/28/19 In reference to the stainless steel flashings on the parapets, will we be able to extend our membrane over the substrate and demo the stainless steel flashing? If not, could the government provide a detail for the stainless steel flashing?

Existing flashing can be removed as required for a warranted re-roof project.

4. 8/28/19 Could the government provide the location of the lay down area we will be able to utilize during this project?

Will be determined.

ITEM