36E77618R0054-00001001.pdf

PDF 69 KB Posted

Attached to
Prepare Digital Radiography Rooms Site Prep Design Build - Fargo
Solicitation number
36E77618R0054
Issued by

About this file

36E77618R0054 00001 Technical Questions Tracking Spreadsheet - Fargo - 4-25-2018.pdf

View the file

Other files

File Type Posted
36E77618R0054-00001000.docx DOCX document
36E77618R0054-008.zip ZIP file
36E77618R0054-010.pdf PDF
36E77618R0054-013.docx DOCX document
36E77618R0054-003.docx DOCX document
36E77618R0054-005.pdf PDF
36E77618R0054-006.pdf PDF
36E77618R0054-007.pdf PDF
36E77618R0054-002.docx DOCX document
36E77618R0054-011.docx DOCX document
36E77618R0054-004.docx DOCX document
36E77618R0054-009.pdf PDF
36E77618R0054-012.docx DOCX document
36E77618R0054-001.docx DOCX document
36E77618R0054-000.docx DOCX document
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36E77618R0054 PREPARE DR ROOMS SITE PREP - FARGO TECHNICAL QUESTIONS AND VA RESPONSE TRACKING SHEET

ITEM

NO.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

1. 04-16-2018 4-25-2018 Due to the lack of design-build opportunities throughout the region, it is nearly impossible for a SDV company to reflect previous project experience as a complete design build team. Will the VA accept project experience from both the SDV general contractor and the designer even if they were not part of a single team in lieu of the above stated requirement (and not result in lower rating).

Additionally, will the VA consider allowing the inclusion of non-design build projects (still meeting the $200k threshold) from a SDV company in the project experience factor due to the overall lack of opportunities made available?

The VA will consider previous design-build experience of the proposed team (SDV general contractor and designer) as individual firms or individuals who have worked at firms that have done design/build projects and assisted with working on the design/build projects even if they were not part of a single design/build team working together. Previous teamwork experience from teams that have worked together shall still be rated higher than non-previous experience (individual firm or individual experience) teams proposed design/build experience if the proposed experienced team meets the rating factor experience requirements listed in the solicitation.

VA will not consider non-design/build SDV company experience managing projects over $200k.

2. 4-19-2018 4-20-2018 What are the project criteria for the PPQs? 1) Completion dates requirements 2) construction cost requirements 3) how many projects required?

Please refer to solicitation Attachment 1, page 7 Factor 3 Past Performance Evaluation criteria for answers to all three of these questions.

3. 4-19-2018 4-20-2018 Is this a public bid opening or drop off only? Per solicitation Attachment 1, Pages 5 and 6, Phase I Proposals are due vial email to Donald.marsh2@va.gov. Only email proposals will be accepted and there is no public bid opening.

4. 4-19-2018 4-20-2018 Can you provide experience of your mentor from a Mentor-Protege agreement if a JV is not in place?

Per Phase I Factor, Experience, provide experience of the Prime design-build firm.

5.

mailto:Donald.marsh2@va.gov

ITEM

NO.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

6.

7.

8.

9.

10.

11.

12.

13.

14.

15.

16.

17.

18.

19.

20.

21.

22.

23.

ITEM

File details come from the government source that posted it.