S02_Addendum 1 Narrative.pdf

PDF 229 KB Posted

Attached to
830CM3019: Grave Site Expansion, Bay Pines National Cemetery
Solicitation number
36C78625B0019
Issued by

About this file

This document is Addendum #1 for the Bay Pines National Cemetery Gravesite Expansion Phase 2 project, dated 27 June 2025. The addendum details multiple revisions to contract drawings and specifications across 23 separate items, focusing on modifications to site plans, road profiles, erosion control plans, and technical specifications.

Key drawing revisions include shifting Road B 12' to the northwest, adjusting project limits of disturbance, adding new storm drainage profiles, modifying road radii and elevations, and updating erosion and sedimentation control plans. Specification changes involve updates to natural stone veneer engraving requirements, joint sealant specifications, and precast columbarium unit surface finishes. The addendum also introduces a new specification section for Temporary Environmental Controls (Section 01 57 19), which provides comprehensive guidelines for environmental protection, including management of air, water, land resources, noise control, and waste disposal during construction activities.

View the file

Other files

File Type Posted
S06_36C78625B0019 Amend 0005.pdf PDF
S02_RFIs and Answers 6.30.2025.pdf PDF
S02_ Addendum 1 Part 1.pdf PDF
S02_Addendum 1 Part 2.pdf PDF
S02_ Addendum 1 Part 4.pdf PDF
S06_36C78625B0019 Amend 0004.pdf PDF
S02_Addendum 1 Part 3.pdf PDF
S06_36C78625B0019 Amend 0003.pdf PDF
S06_36C78625B0019 Amend 0002.pdf PDF
S02_Attachment - Site Visit Attendance Roster.pdf PDF
S02_Attachment - RFIs and Answers.pdf PDF
S02_Attachment - Wage Determination Building 5.23.2025.pdf PDF
S06_36C78625B0019 Amend 0001.pdf PDF
S02_Attachment - Davis-Bacon Act Poster.pdf PDF
S02_Attachment - BPNC GSE P2 BD_Plans bk2.pdf PDF
S02_Attachment - Design Narrative.pdf PDF
S02_Attachment - Stormwater Management Report.pdf PDF
S02_Attachment - Standard Form 1413.pdf PDF
S02_Attachment - Geotechnical Report.pdf PDF
S02_Attachment - Limitations on Subcontracting Cert.docx DOCX document
S02_Attachment - BPNC GSE P2 BD_Plans bk1.pdf PDF
S02_Attachment - Bid Specifications.pdf PDF
S02_Attachment - DOL Payroll Form.pdf PDF
S02_Attachment - BPNC GSE P2 BD_Plans bk3.pdf PDF
36C78625B0019.pdf PDF
S02_Attachment - BPNC GSE P2 BD_Plans bk4.pdf PDF
S02_Attachment - Wage Determination Heavy.pdf PDF
S02_Attachment - NCA Contractor Safety Checklist.pdf PDF
S02_Attachment - BPNC GSE P2 BD_Plans bk5.pdf PDF
S02_Attachment - Wage Determination Building.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

830CM3019 Bay Pines National Cemetery Gravesite Expansion Phase 2 Addendum #1 27 June 2025

1. Drawing Revisions

Item 1 - Contract Drawings – G-101 – Cover Sheet

• Revised Drawing List to add Sheet GC201 Storm Drainage Profiles.

Item 2 - Contract Drawings – CD101 Demolition Plan

• Areas of demolition have changed.

• New trees were added to be demolished.

• Keynote 8 was added to the list of keynotes and on the plans.

• A hatch was added to the area which is related to keynote 8.

• Keynote 9 was added to the list of keynotes and on the plans.

• A hatch was added to the pipes which are related to keynote 9.

o Existing storm pipes that run under the proposed roads have been added to the demolition plan. All storm pipes that run under the road are scheduled for demolition except the single 30” RCP pipe.

Item 3 - Contract Drawings – CS101 Site Plan

• Adjusted project limits of disturbance to accommodate revised work.

• Added “Wetland Impact Table & Keynotes” table for SWFWMD permitting.

• Added associated keynotes.

• Revised Legend

• Road B was shifted 12’ to the NW.

• Radii at entrance to Road B were increased to 24’.

• Radii at intersection between Road B and Road A were increased to 24’.

• Keynote 13 was added. 6” vertical curb was added to road B.

• Keynote 12 was added to address transition from 6” curb to rollover curb.

• A guardrail was added to the east side of Road B.

• Clarified Keynote 9.

• Keynote 14 was added for transition curb at loop road.

Item 4 - Contract Drawings – CP201 Road Profiles

• Road B was shifted 12’ to the NW.

• Road A elevations and slopes were decreased to minimize fill impacts.

• Road B elevations and slopes were revised.

• All crossing utilities, stations, and elevations, proposed and existing, were added to the profile for Road A.

• All crossing Utilities, stations, and elevations, proposed and existing, were added to the profile for Road B.

• A guardrail was added to the east side of Road B.

• Revised Legend

Item 5 - Contract Drawings – CG101 Erosion and Sedimentation Control Plan – Initial Phase

• Changed SHWT elevation.

• Added new 300-LF drainage ditch.

• Fixed Silt Fencing to be double silt fence in multiple locations around the site.

• Added tree protection to additional trees.

Item 6 - Contract Drawings – CG102 Erosion and Sedimentation Control Plan – Final Phase

• Changed SHWT elevation.

• Added new 300-LF drainage ditch.

• Fixed Silt Fencing to be double silt fence in multiple locations around the site.

• Added skimmer to final treatment basin.

• Revised Legend

Item 7 - Contract Drawings – CG103 Grading and Drainage

• Relocated storm profiles to CG201.

• New storm structures were added in locations where existing pipes beneath roadways are slated for demolition.

o Structure tables were updated accordingly.

• New storm pipes were added in locations where existing pipes beneath roadways are slated for demolition.

o Pipe tables were updated accordingly.

• Sheet pile wall elevations were updated to drain away from wall.

• Sheet pile wall notes were edited for clarity.

• Grading Note 6 was changed to reflect the new BMP outfall elevation.

• Site was re-graded for constructability and to reduce fill impacts.

• Call-out was added to replace railing on headwall.

• Revised Legen

Item 8 - Contract Drawings – CG104 Enlarged Columbarium Drainage Plan

• Revised Legend

Item 9 - Contract Drawings – CG201 Enlarged Columbarium Drainage Plan (NEW

SHEET)

• Added New Storm profile sheet with profiles for all proposed storm pipes and structures.

Item 10 - Contract Drawings – CG502 Erosion Control Details

• Added symbol for Temporary Seeding details.

• Added symbol for Permanent Seeding details.

Item 11 – Contract Drawings – CG503 Erosion Control Details

• Clarified detail 3.

o Updated elevations for the control structure.

o Updated pond elevations on the pond sectional view.

o Updated trash rack details.

Item 12 – Contract Drawings – CU501 Stormwater Details

• Guardrail type was specified.

Item 13 – Contract Drawings – CU503 Stormwater Details

• Added a junction box detail.

• Added a detail for ADS N-12 HDPE Pipe.

Item 14 - Contract Drawings – C-101 - Site Furnishings/Signage Plan

• Revised Road B location.

• Revised Orientation of Signs 3a and 3b.

Item 15 – Contract Drawings – C-500 Site Details

• Added a vertical curb and gutter detail.

• Added a curb transition detail.

• Modified the curb note on the typical roadway section.

• Clarified notes on Detail 2.

Item 16 - Contract Drawings – C-501 - Site Details 1

• Revised Details 1, 2 and 3 - provide more detailed description of the attachment of Granite veneer on columbarium piers.

Item 17 - Contract Drawings – C-502 - Site Details 2

• Revised Details 1,2,3, 5 and 6 - provide a more detailed description of the attachment of Granite veneer on columbarium piers.

Item 18 - Contract Drawings – C-503 - Site Details 3

• Revised Details 8 and 9 - Revisions to Columbarium Coping dimensions.

Item 19 - Contract Drawings – C-505 - Site Details 5

• Deleted Detail 10 STUCCO ASSEMBLY.

Item 20 - Contract Drawings – C-506 Site Details 6

• Details 4 and 7 - Revised Dimensions of “Do Not Drink” Plate.

Item 21 - Contract Drawings – LP101 Planting Plan

• Revised Road B location

Item 22 – Contract Drawings – S-201 - Columbarium Foundation Plan & Sections

• Revisions to Details 1, 4, 5, 6, 7 and adding detail 8 to provide more detailed description of the attachment of Granite veneer on columbarium piers.

Item 23 – Contract Drawings – LI102 – Irrigation Plan

• Adjusted irrigation lines to new Road B alignment.

2. Specification Revisions Item 1 – Contract Specifications Section 04 43 00 -Natural Stone Veneer ADD Paragraph 2.4:

2.4 ENGRAVING

A. Engraving shall be as indicated, using the highest industry standards for preparation and completion of engraving to result in crisp engraving, of the style indicated and as approved during the submittal review process, and shall include applicable staining or coloration of the engraving, as applicable and approved, as well as information as to the longevity of any such enhancement to the engraving. Engraving in the pier ID and number plaques shall be provided with the approved lithichrome stain and shall be included in the final installation as approved during the submittal process and the approved mock-up. The lithichrome stain shall be used in the columbarium wall units for the exposed concrete faces, with the color to be black, as submitted and approved in the submittals and provided on the accepted mock-up.

B. Included in the engraving shall be the procedures and materials to be used to clean the engraving before the approved stain is applied, to maximize the longevity on the stain application. Provide recommended materials and procedures from the manufacturer to maximize the longevity of the stain application and follow the approved procedures.

Item 2 – Contract Specifications Section 04 43 00 -Natural Stone Veneer ADD Paragraph 3.15:

3.15 ENGRAVING

A. Provide all labor, materials, manpower and equipment required to perform the engraving for the indicated locations as approved during the submittal process, to result in high quality engraving meeting the contract documents, including the approved submittal documents.

Item 3 – Contract Specifications Section 07 92 00 – Joint Sealants DELETE Section 2.1 Sealants and REPLACE with:

2.1 SEALANTS

A. S-1: Basis of Design Pecora 890 NST Non-Staining, ultra-low modulus silicone sealant.

1. ASTM C920 silicone.

2. Type S.

3. Class 50 or higher.

4. Grade NS.

5. Shore A hardness of 15-25.

6. Non-yellowing, mildew resistant.

Item 4 – Contract Specifications 03 48 24 - Precast Columbarium Units:2.15.6.b DELETE and REPLACE WITH:

b. Back side of single columbarium units, with back exposed to view shall have surface finish with a waterborne, High Build, Modified

Acrylic. Waterproof Coating – Basis of Design: Sika Thorocoat- 300

Artic (formerly MProtect HB 300SB). Contractor to submit color for review and approval by CO/COR.

https://usa.sika.com/en/construction/repair-protection/coatings-water-repellents/building-facade-coatings/sika-thorocoat-

300arctic.html

Item 5 – Contract Specifications ADD Specification Section 01 57 19-

TEMPORARY ENVIRONMENTAL CONTROLS IN ITS ENTIRETY:

Bay Pines National Cemetery Gravesite Expansion Phase 2 Project No. 830CM3019 Bid Documents 29 March 2024

TEMPORARY ENVIRONMENTAL CONTROLS

01 57 19 - 1

SECTION 01 57 19

TEMPORARY ENVIRONMENTAL CONTROLS

PART 1 GENERAL

1.1 DESCRIPTION

A. This section specifies the control of environmental pollution and damage that the Contractor must consider for air, water, and land resources. It includes management of visual aesthetics, noise, and solid waste, as well as other pollutants and resources encountered or generated by the Contractor. The Contractor is obligated to consider specified control measures with the costs included within the various contract items of work.

B. Environmental pollution and damage is defined as the presence of chemical, physical, or biological elements or agents which:

1. Adversely effect human health or welfare.

2. Unfavorably alter ecological balances of importance to human life.

3. Affect other species of importance to humankind.

4. Degrade the utility of the environment for aesthetic, cultural, and historical purposes.

1.2 DEFINITIONS OF POLLUTANTS

A. Chemical Waste: Petroleum products, bituminous materials, salts, acids, alkalis, herbicides, pesticides, organic chemicals, and inorganic wastes.

B. Debris: Combustible and noncombustible wastes, such as leaves, tree trimmings, ashes, and waste materials resulting from construction or maintenance and repair work.

C. Sediment: Soil and other debris that has been eroded and transported by runoff water.

D. Solid Waste: Rubbish, debris, garbage, and other discarded solid materials resulting from project construction activities.

E. Surface Discharge: The term "Surface Discharge" implies that the water is discharged with possible sheeting action and subsequent soil erosion may occur. Waters that are surface discharged may terminate in drainage ditches, storm sewers, creeks, and/or "waters of the United States" and require a permit to discharge water from the governing agency.

F. Rubbish: Combustible and noncombustible wastes such as, but not limited to, paper, plastic, metal and plastic containers and cans, boxes, metal and lumber scrap.

G. Sanitary Wastes: Domestic Sanitary Sewage.

TEMPORARY ENVIRONMENTAL CONTROLS

01 57 19 - 2

1.3 QUALITY CONTROL

A. Establish and maintain quality control for the environmental protection of all items set forth herein.

B. Record on daily reports any problems in complying with laws, regulations, ordinances and note any corrective action taken.

1.4 REFERENCES

A. Publications listed below form a part of this specification to extent referenced. Publications are referenced in text by the basic designation only. Comply with applicable provisions and recommendations of the following, except as otherwise shown or specified.

B. U.S. National Archives and Records Administration (NARA):

33 CFR 328 Definitions, Waters of the United States.

C. Federal Environmental Regulatory Requirements: Comply with applicable regulations. The following is for Contractor's information only:

1. Storm water permits; refer to The Office of Wastewater Management, NPDES Storm Water Program: http://www.epa.gov/npdes/stormwater

2. Dredge and fill (Section 404) permits; refer to U.S. EPA Office of

Wetlands, Oceans, and Watersheds (OWOW): http://www.epa.gov/owow/

3. RCRA hazardous and non-hazardous solid waste requirements; refer to

EPA’s Office of Solid Waste and Emergency Response:

http://www.epa.gov/epaoswer/osw/laws-reg.htm

4. Oil spill requirements for construction activities; refer to EPA Oil

Program web site: http://www.epa.gov/oilspill/

5. Hazardous substances (Superfund Liability) requirements for construction activities; refer to EPA’s Superfund website:

http://www.epa.gov/superfund/index.htm

6. Polychlorinated Biphenyl (PCB) waste requirements; refer to EPA’s

Polychlorinated Biphenyl (PCB) Homepage: http://www.epa.gov/pcb/

7. Air quality requirements for construction activities; refer to EPA’S

Air Program Mobile Sources Page:

http://www.epa.gov/ebtpages/airmobilesources.html

8. Asbestos requirements for construction activities; refer to EPA’s

Asbestos Management and Regulatory Requirements Website:

http://www.epa.gov/fedsite/cd/asbestos.html

9. National Environmental Policy Act (NEPA) requirements for construction activities

10.Endangered Species Act; refer to The US Fish and Wildlife Service

Endangered Species Program: http://endangered.fws.gov/ http://www.epa.gov/npdes/stormwater http://www.epa.gov/owow/ http://www.epa.gov/epaoswer/osw/laws-reg.htm http://www.epa.gov/oilspill/ http://www.epa.gov/superfund/index.ht http://www.epa.gov/pcb/ http://www.epa.gov/ebtpages/airmobilesources.html http://www.epa.gov/fedsite/cd/asbestos.html http://endangered.fws.gov/

TEMPORARY ENVIRONMENTAL CONTROLS

01 57 19 - 3

11.National Historic Preservation Act

C. State and Local Environmental Regulatory Requirements: Comply with applicable regulations. The following is for Contractor's information only:

1. State Office/Department of Environmental Quality.

2. Local Office/Department of Environmental Quality.

3. The Construction Industry Compliance Assistance Center:

http://www.cicacenter.org/index.cfm

4. The National Environmental Compliance Assistance Clearinghouse:

http://cfpub.epa.gov/clearinghouse/

1.5 SUSTAINABILITY REQUIREMENTS

A. Materials in this section may contribute towards contract compliance with sustainability requirements. See Section 01 81 11, SUSTAINABLE

DESIGN REQUIRMENTS, for project local/regional materials, low-emitting materials, recycled content, certified wood requirements.

B. Biobased Material: For products designated by the USDA’s BioPreferred® program, provide products that meet or exceed USDA recommendations for biobased content, subject to the products compliance with performance requirements in this Section. For more information regarding the product categories covered by the BioPreferred® program, visit http://www.biopreferred.gov.

1.6 SUBMITTALS

A. In accordance with Section, 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND

SAMPLES, the Contractor shall furnish the following:

1. Environmental Protection Plan: After the contract is awarded and prior to the commencement of the work, meet with the Resident

Engineer/Contracting Officer’s Representative (CO/COR) to discuss the proposed Environmental Protection Plan and to develop mutual understanding relative to details of environmental protection. Not more than 20 days after the meeting, prepare and submit to the

CO/COR for approval, a written and/or graphic Environmental

Protection Plan including, but not limited to, the following:

a. Name(s) and qualifications of person(s) within the Contractor's organization who is (are) responsible for:

1) Ensuring adherence to the Environmental Protection Plan.

2) Manifesting hazardous waste to be removed from the site.

3) Training the Contractor's environmental protection personnel.

http://www.cicacenter.org/index.cfm http://cfpub.epa.gov/clearinghouse/ http://www.biopreferred.gov/

TEMPORARY ENVIRONMENTAL CONTROLS

01 57 19 - 4

b. Description of the Contractor's environmental protection personnel training program.

c. A list of Federal, State, and local laws, regulations, and permits concerning environmental protection, pollution control, noise control and abatement that are applicable to the

Contractor's proposed operations and the requirements imposed by those laws, regulations, and permits.

d. Methods for protection of features to be preserved within authorized work areas including trees, shrubs, vines, grasses, ground cover, landscape features, air and water quality, fish and wildlife, soil, historical, and archeological and cultural resources.

e. Procedures to provide environmental protection that complies with the applicable laws and regulations. Describe the procedures to correct pollution of the environment due to accident, natural causes, or failure to follow the procedures as described in the

Environmental Protection Plan.

f. Permits, licenses, and the location of the solid waste disposal area.

g. Drawings showing locations of any proposed temporary excavations or embankments for haul roads, stream crossings, material storage areas, structures, sanitary facilities, and stockpiles of excess or spoil materials. Include as part of an Erosion Control Plan approved by the District Office of the U.S. Soil Conservation

Service and/or mandated state agency, and the Department of

Veterans Affairs.

h. Environmental Monitoring Plans for the job site including land, water, air, and noise.

i. Work Area Plan showing the proposed activity in each portion of the area and identifying the areas of construction limits or protected areas. Plan should include measures for marking the limits of use areas. This plan may be incorporated within the

Erosion Control Plan.

B. Within 20 days after the date of its submittal, the CO/COR shall approve the Contractor’s Comprehensive Environmental Protection Plan, or respond with an explanation for its rejection and resubmittal.

TEMPORARY ENVIRONMENTAL CONTROLS

01 57 19 - 5

C. Approval of the Contractor's Environmental Protection Plan will not relieve the Contractor of responsibility for adequate and continued control of pollutants and other environmental protection measures.

1.7 PROTECTION OF ENVIRONMENTAL RESOURCES

A. Protect environmental resources within the project boundaries and those affected outside the limits of permanent work during the entire period of this contract and after the project is complete, based upon leaving the site that has yet to mature of hydroseeding. Confine construction activities to areas defined by construction limits, the specifications and drawings.

B. Protection of Land Resources: Prior to construction, identify all land resources to be preserved within the work area. Do not remove, cut, deface, injure, or destroy land resources including trees, shrubs, vines, grasses, top soil, land forms, wetlands or wetland buffers without prior approval from the CO/COR. Do not fasten or attach ropes, cables, or guys to trees for anchorage unless specifically authorized, or dictated by special emergency use.

1. Work Area Limits: Prior to any construction, mark/fence/protect the areas that require work to be performed under this contract. Prior to construction, mark/fence/protect monuments, works of art, and any other markers to remain. Convey to all personnel the purpose of marking and protecting all marked and protected objects.

2. Protection of Specific Regulated Elements: Wetlands and wetland buffers and other landscape features shown on the drawings to be preserved by marking, fencing, or using any other approved protective techniques.

a. Protect trees and shrubs to remain on site to protect from damage per contract details.

b. All damage to existing trees and shrubs shall be immediately repaired by trimming, cleaning, and painting with antiseptic tree paint. See Section 02 41 10.

c. Do not store building materials or perform construction activities closer to existing trees or shrubs than the farthest extension of their limbs.

3. Reduction of Exposure of Unprotected Erodible Soils: Plan and conduct earthwork to minimize the duration of exposure of unprotected soils. Clear areas only as needed to use to work the area to be developed. Form earthwork to final grade as shown as

TEMPORARY ENVIRONMENTAL CONTROLS

01 57 19 - 6 quickly as possible to minimize potential erosion damage.

Immediately protect side slopes and back slopes upon completion of rough grading or clearing with appropriate material as defined in the Sediment and Erosion Control Plan.

4. Temporary Protection of Disturbed Areas: Construct diversion ditches, benches, check dams and berms to retard and divert runoff from the construction site to protected drainage areas as intended under paragraph 208 of the Clean Water Act.

a. Sediment Basins: Trap sediment from construction areas in temporary or permanent sediment basins that accommodate the runoff of a local 25 (design year) storm. After each storm, pump the basins dry and remove the accumulated sediment. Control overflow/drainage with paved weirs or by vertical overflow pipes, that drain from the surface of the basin.

b. Reuse or conserve the collected topsoil sediment as directed by the CO/COR. Topsoil use and requirements are specified in Section

31 20 00, EARTH MOVING.

c. Institute effluent quality monitoring programs as required by

Federal, State, and local environmental agencies.

5. Erosion and Sedimentation Control Devices: Construct or install all temporary and permanent erosion and sedimentation control features shown. on the Environmental Protection Plan to avoid violating water quality in accordance with federal and state regulations. Maintain temporary erosion and sediment control measures such as berms, dikes, drains, sedimentation basins, grassing, and mulching, straw waddles, fiber rolls, until permanent drainage and erosion control facilities are completed and operative.

6. Manage and control borrow and spoil areas on Government property to minimize erosion and to prevent soil and/or sediment from entering nearby water courses or lakes.

7. Protect adjacent areas from despoilment by temporary excavations and embankments.

8. Handle and dispose of solid wastes in such a manner that will prevent contamination of the environment. Place solid wastes

(excluding clearing debris) in containers that are emptied on a regular schedule. Transport all solid waste off Government property and dispose of waste in compliance with Federal, State, and local requirements.

TEMPORARY ENVIRONMENTAL CONTROLS

01 57 19 - 7

9. Store chemical waste away from the work areas in corrosion resistant containers and dispose of waste in accordance with Federal, State, and local regulations.

10.Handle discarded materials other than those included in the solid waste category as directed by the CO/COR.

C. Protection of Water Resources: Keep construction activities under surveillance, management, and control to avoid pollution of surface and ground waters and sewer systems. Implement management techniques to control water pollution by the listed construction activities that are included in this contract.

1. Washing and Curing Water: Do not allow wastewater directly derived from construction activities to enter water areas. Collect and place wastewater in sediment basins prior to entering retention/detention ponds, allowing the suspended material to settle, the pollutants to separate, or the water to evaporate.

2. Control movement of materials and equipment at stream crossings during construction to prevent violation of water pollution control standards of the Federal, State, or local government.

3. Monitor water areas, wetlands and wetland buffers affected by construction.

D. Protection of Fish and Wildlife Resources: Keep construction activities under surveillance, management, and control to minimize interference with, disturbance of, or damage to fish and wildlife. Prior to beginning construction operations, list protected species that require specific attention along with measures for their protection.

E. Protection of Air Resources: Keep construction activities under surveillance, management, and control to minimize pollution of air resources. Burning is not permitted on the job site. Keep activities, equipment, processes, and work operated or performed, in strict accordance with the State of Florida Department of Environmental

Protection, F.A.C. Chapter 62-204 Air Pollution Control- General

Provisions and Federal emission and performance laws and standards.

Maintain ambient air quality standards set by the Environmental

Protection Agency, for those construction operations and activities specified.

1. Particulates: Control dust particles, aerosols, and gaseous by-products from all construction activities, processing, and

TEMPORARY ENVIRONMENTAL CONTROLS

01 57 19 - 8 preparation of materials at all times, including weekends, holidays, and hours when work is not in progress.

2. Particulates Control: Maintain all excavations, stockpiles, haul roads, permanent and temporary access roads, spoil areas, borrow areas, and all other work areas within or outside the project boundaries free from particulates which would cause a hazard or a nuisance. Sprinklering, chemical treatment of an approved type, light bituminous treatment, or other methods are permitted to control particulates in the work area as approved in the

Environmental Protection Plan.

3. Hydrocarbons and Carbon Monoxide: Control monoxide emissions from equipment to Federal and State allowable limits.

4. Odors: Control odors of construction activities and prevent obnoxious odors from occurring.

F. Noise Control: Minimize noise using every action possible. Perform noise-producing work in less sensitive hours of the day or week as directed by the CO/COR. Maintain noise-produced work at or below the decibel levels and within the time periods specified.

1. Perform construction activities involving repetitive, high-level impact noise only between 7:00a.m. and 4:00p.m unless otherwise permitted by local ordinance or the CO/COR. Repetitive impact noise on the property shall not exceed the following Decibel A-scale (dBA) limitations:

Time Duration of Impact Noise Sound Level in dBA

More than 12 minutes in any hour 70

Less than 30 seconds of any hour 85

Less than three minutes of any hour

Less than 12 minutes of any hour 75

2. Provide sound-deadening devices on equipment and take noise abatement measures that are necessary to comply with the requirements of this contract, consisting of, but not limited to, the following:

a. Maintain maximum permissible construction equipment noise levels as measured with an A-scale decibel measuring device at 15 m (50 feet) (dBA):

CATEGORY OF EQUIPMENT

EARTHMOVING MATERIALS HANDLING

TEMPORARY ENVIRONMENTAL CONTROLS

01 57 19 - 9

EQUIPMENT

STYLE

SOUND LEVEL

dBA

EQUIPMENT STYLE SOUND

LEVEL dBA

FRONT LOADERS 75 CONCRETE MIXERS 75

BACKHOES 75 CONCRETE PUMPS 75

DOZERS 75 CRANES 75

TRACTORS 75 DERRICKS IMPACT 75

SCAPERS 80 PILE DRIVERS 95

GRADERS 75 JACK HAMMERS 75

TRUCKS 75 ROCK DRILLS 80

PAVERS,

STATIONARY

80 PNEUMATIC TOOLS 80

PUMPS 75 BLASTING //--//

GENERATORS 75 SAWS 75

COMPRESSORS 75 VIBRATORS 75

b. Provide soundproof housings or enclosures for noise-producing machinery.

c. Use efficient silencers on equipment air intakes.

d. Use efficient intake and exhaust mufflers on internal combustion engines that are maintained so equipment performs below noise levels specified.

e. Line hoppers and storage bins with sound deadening material.

f. Conduct truck loading, unloading, and hauling operations so that noise is kept to a minimum.

3. Measure sound level for noise exposure due to the construction at least once every five successive working days while work is being performed above 75 dB(A) noise level. Measure noise exposure at the property line or 15 m (50 feet) from the noise source, whichever is greater. Measure the sound levels on the A weighted sound level of a

General Purpose sound level meter at slow response. To minimize the effect of reflective sound waves at buildings, take measurements at

900 to 1800 mm (three to six feet) in front of any building face.

Submit the recorded information to the Resident Engineer/COR noting any problems and the alternatives for mitigating actions.

G. Restoration of Damaged Property: If any direct or indirect damage is done to public or private property resulting from any act, omission, neglect, or misconduct, the Contractor shall restore the damaged property to a condition equal to that existing before the damage at no

TEMPORARY ENVIRONMENTAL CONTROLS

01 57 19 - 10 additional cost to the Government. Repair, rebuild, or restore property as directed or make good such damage in an acceptable manner.

H. Final Clean-up: On completion of project and after removal of all debris, rubbish, and temporary construction, Contractor shall leave the construction area in a clean condition as approved by the CO/COR. The site shall be left meeting the requirements of the local and state environmental requirements associated with the (SWPPP) Storm Water

Pollution Protection Plan as submitted. Cleaning shall include off-cemetery disposal of all items and materials not required to be salvaged, as well as all debris and rubbish resulting from demolition and new work operations, clearing, logging and general construction in accordance with state and local regulations and the contract.

- - - E N D - - -

1. ASTM C920 silicone.
2. Type S.
3. Class 50 or higher.
4. Grade NS.
5. Shore A hardness of 15-25.
6. Non-yellowing, mildew resistant.
b. Back side of single columbarium units, with back exposed to view
shall have surface finish with a waterborne, High Build, Modified Acrylic. Waterproof Coating – Basis of Design: Sika Thorocoat- 300 Artic (formerly MProtect HB 300SB). Contractor to submit color for review and approval by CO/COR. https://usa.sika.com...