36C78621Q0143 0002.docx

DOCX document 14 KB Posted

Attached to
S208--FORT SAM HOUSTON GROUNDS MAINTENANCE BASE PLUS 4, ONE-YEAR OPTION PERIODS
Solicitation number
36C78621Q0143
Issued by

View the file

Other files

File Type Posted
36C78621Q0143 0008.docx DOCX document
36C78621Q0143 0007.docx DOCX document
36C78621Q0143 0006.docx DOCX document
36C78621Q0143 0005.docx DOCX document
36C78621Q0143 0004.docx DOCX document
36C78621Q0143 0003.docx DOCX document
ATTACHMENT B - 36C78621D0078 SOW.pdf PDF
ATTACHMENT A - VA786-16-C-0021 SOW.pdf PDF
36C78621Q0143 0001.docx DOCX document
36C78621Q0143_2.docx DOCX document
ATTACHMENT B - PERFORMANCE WORK STATEMENT.pdf PDF
ATTACHMENT C - WAGE DETERMINATION.pdf PDF
36C78621Q0143.pdf PDF
ATTACHMENT A - PRICE SCHEDULE.pdf PDF
ATTACHMENT F - PAST PERFORMANCE QUESTIONNAIRE.pdf PDF
ATTACHMENT E - LIST OF REFERENCES.pdf PDF
ATTACHMENT D - CEMETERY MAPS.pdf PDF
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract Opportunity Amendment to a Previous Combined Solicitation

PRODUCT SERVICE CODE

SUBJECT

CONTRACTING OFFICE'S

ZIP-CODE

SOLICITATION NUMBER

BASE NOTICE TYPE

RESPONSE DATE/TIME/ZONE

ARCHIVE

DAYS AFTER THE RESPONSE DATE

RECOVERY ACT FUNDS

SET-ASIDE

NAICS CODE

CONTRACTING OFFICE

ADDRESS

POINT OF CONTACT

(POC Information Automatically Filled from User Profile Unless Entered)

DESCRIPTION

See Attachment

AGENCY'S URL

URL DESCRIPTION

AGENCY CONTACT'S EMAIL

ADDRESS

EMAIL DESCRIPTION

ADDRESS

POSTAL CODE

COUNTRY

ADDITIONAL INFORMATION

GENERAL INFORMATION

PLACE OF PERFORMANCE

* = Required Field Contract Opportunity Amendment to a Previous Combined Solicitation S208

FORT SAM HOUSTON GROUNDS MAINTENANCE

BASE PLUS 4, ONE-YEAR OPTION PERIODS

22172 36C78621Q0143 04-28-2021

4PM

EASTERN TIME, NEW YORK, USA

N

SDVOSBC

561730 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle VA 22172

CONTRACTING OFFICER

KENNETH DOUGHERTY

KENNETH.DOUGHERTY@VA.GOV

703.630.9345

FORT SAM HOUSTON NATIONAL CEMETERY

1520 HARRY WURZBACH RD.

SAN ANTONIO

TX

78209

USA

https://www.va.gov// Department of VA NCA

KENNETH.DOUGHERTY@VA.GOV

CO'S EMAIL

The purpose of this amendment to the solicitation is to 1) address questions from prospective vendors in response to the solicitation, 2) revise language found in Attachment B – Performance Work Statement, section 3.4.12., and 3) incorporate revised Attachment B – Performance Work Statement.

1) Question 1: In reference to PWS Section 3.4.12: “The PWS states the Contractor shall use plastic blade attachments to cleanly trim edges around all headstones. Can the government confirm that this is not a requirement for upright headstones and only string trimming of upright headstones is required. Plastic blade edgers should only be used on flat markers.”

Answer 1: Turfgrass within 6 to 12 inches of upright headstones, monuments, etc., will be trimmed to the recommended mowing height using line-type trimmers. Each trimmer will be fitted with an anti-scalping devise and used only with the device properly attached.

Question 2: “I am writing to ask if a bid tabulation or matrix was released to any of the bidders for the cancelled solicitation #36C78621Q0026 that was submitted in November 2020, and if so, would you please send us a copy as well?”

Answer 2.a.: No, a bid tabulation or matrix was not released to any of the bidders for the cancelled solicitation #36C78621Q0026.

Answer 2.b.: Bid matrix provided below.

QUOTER
QUOTED PRICE
A
$3,415.702.75
B
$2,511,102.00
C
$3,793,525.19
D
$4,616,326.87
E
$4,729,828.01
F
$4,942,747.60
G
$5,463,342.21
H
$5,879,629.12
I
$7,984,625.60
J
$6,525,600.80
K
$22,011,295.28
L
$6,794,207.86
M
$6,973,216.00
N
$7,915,400.99
O
$6,495,600.80
P
$10,804,091.36
Q
$5,033,696.00

2) The language in Attachment B – Performance Work Statement See Attachment B – Performance Work Statement item 3.4.12. will change from, “The Contractor shall use edgers with a plastic blade attachment to cleanly trim edges around all headstones and flat markers, monuments, section markers, etc. Equipment or attachments not meeting the descriptions provided under this section require approval for use by COR prior to implementation.”

To:

“The Contractor shall use edgers with a plastic blade attachment to cleanly trim edges around all flat markers, monuments, section markers, etc. Equipment or attachments not meeting the descriptions provided under this section require approval for use by COR prior to implementation.”

3) Revised Attachment B – Performance Work Statement is hereby incorporated into the solicitation.

End of Document