36C78621B0010 0002.docx

DOCX document 30 KB Posted

Attached to
Y1PZ--817CM3022 Marion GSE - Construction IFB (VA-21-00065461)
Solicitation number
36C78621B0010
Issued by

About this file

This solicitation seeks proposals for a gravesite expansion project at the Marion National Cemetery in Marion, Indiana. The Department of Veterans Affairs intends to award a firm fixed-price construction contract valued between $2-5 million to provide labor, materials and equipment for installing 2,020 pre-cast concrete burial vaults and crypts, rerouting utilities, grading, erosion control and constructing roadways, monuments and columbaria. The contractor must also consider optional additions for irrigation system replacements. Proposals are due by September 1, 2021 and the contract term is 270 calendar days. This opportunity is open only to verified Service-Disabled Veteran-Owned Small Businesses.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

817CM3022

36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle

VA

22172 36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle

VA

22172 To all Offerors/Bidders

36C78621B0010

X X X

10:00 EST 09/01/2021

X See continuation pages for information regarding the virtual bid opening as well as other RFIs.

Trevor DiSimone Contracting Officer AMENDMENT-0002, Solicitation 36C78621B0010 Marion Gravesite Expansion Contractor Questions & GOV Responses

1. Will the owner accept the use of the industry leading Procore Project Management software as the primary submittal and data tracking tool for this project?

1. GOV Response: Yes.

2. The RFP states that we are to “submit a written RFI utilizing the RFI Form attached to this solicitation,” however there was no RFI Form attached with the solicitation. Can you please provide the referenced RFI form?

2. GOV Response: RFIs acceptable as submitted. Form attached for further use.

3. As a result of the effect of COVID-19 throughout the U.S., and the resulting Federal, State, and local governments’ responses/requirements of safe distancing and potential advocations of working remotely and/or complete organization closures, please advise how the Government intends to address delays resulting there as it pertains to the current solicitation schedule for this and all future projects.

3. GOV Response: Delays shall be handled on a case by case basis.

4. Under Address Offer To, Bid submission and opening refers to Section L, “Virtual Bid Instructions”. Section L does not include virtual/bid instructions. Are bids to be submitted by email? Is the big opening via virtual bid opening? Please provide virtual bid opening instructions.

4. GOV Response: Bids are to be submitted using the VA Vendor Portal.

5. Can we submit our bid via email, if we mail the original hardcopy Bid Bond prior to the due date?

5. GOV Response: See response to question 4.

6. Is this project tax exempt, and will the CO/COR provide necessary tax exempt certificates?

6. GOV Response: It is the Contractor’s responsibility to determine if there are any applicable exemptions and to obtain requisite paperwork.

7. The Contracting Officer will issue NTP to the awardee after the contract award is made. What is the approximate duration between issuing the award and issuing the NTP?

7. GOV Response: Approximately 10-14 days after issuance of award.

8. For planning the preliminary project schedule, can you please provide an anticipated award date?

8. GOV Response: No.

9. What is the anticipated duration between issuance of contract award and issuance of the NTP?

9. GOV Response: See answer to question 7.

10. Contractor feels this project warrants a Senior Project Manager. This is not a position noted in the solicitation for Proposal. Can our Senior Project Manager be added to the project organization portion of the proposal?

10. GOV Response: Yes.

11. Contractor feels this project warrants a QA/QC Super. This is not a position noted in the solicitation for Proposal. Can a QA/QC Super requirement be added to the required staffing plan?

11. GOV Response: Yes.

12. How many calendar days should be included in the critical-path method schedule for owner and A/E review and respond to RFIs?

12. GOV Response: See Specification 013217 Network Analysis Schedule (Microsoft Project Gantt Chart).

13. How many calendar days should be included in the critical-path method schedule for owner and A/E submittal review?

13. GOV Response: See response to question 12.

14. Can 3-D REVIT Design model in native file format, for creation of coordination documentations, be provided?

14. GOV Response: Autocad files may be available after award. Autocad files are not considered signed PDF drawings, however, the successful bidder may use them at their own risk.

15. Will the owner provide the contract drawings in the native Revit format for use by the GC?

15. GOV Response: See response to question 14.

16. Will owner require GC’s to develop and submit coordination drawings in Revit?

16. GOV Response: No.

17. Will the owner provide as-built drawings for the existing structures/work area of the project?

17. GOV Response: If necessary, additional as-built information may be provided through the RFI process. However, prior to submitting a bid, bidders are required to perform due diligence in accordance with FAR 52.236-3 Site Investigation and Conditions Affecting the Work and VAAR 852.236-71 Specification and Drawings for Construction (APR 2019).

18. Where will the designated parking & laydown area be for workers accessing the construction site?

18. GOV Response: See sheet 0-100 for project area and staging area. If additional area is desired, additional areas can be discussed after award. Any associated costs for securing, erosion control, restoration, etc. for all staging areas shall not incur any additional costs to the Government.

19. Please confirm that the project is to be completed during normal working hours, not nights and weekends.

19. GOV Response: Confirmed.

20. Does the contract includes liquidated damages? If the owner temporarily shuts down or suspends the project (i.e. for noise), will extended general conditions cost and time be added to the contract?

20. GOV Response: See Section F.2 52.211-12 LIQUIDATED DAMAGES – CONSTRUCTION (SEPT 2000) (pg 9 of 66) of the solicitation.

21. We anticipate certain construction activities to generate high levels of noise. Please confirm that only the Contracting Officer can suspend work via written notification to the Contractor.

21. GOV Response: Confirmed.

22. Can the owner confirm that the General Contractor is to not include any Asbestos or Lead Removal?

22. GOV Response: Asbestos and lead abatement is not anticipated as part of the scope of work.

23. Has the work area been checked for asbestos, lead based materials and/or other hazardous materials? Is there a report available?

23. GOV Response: See response to question 22.

24. What is the Governments’ policy if asbestos products are encountered during construction?

24. GOV Response: It is the responsibility of the Contractor to notify the Contracting Officer promptly and before such conditions are disturbed of the possible presence of asbestos pursuant to the Differing Site Conditions clause. A laboratory analysis of suspected material will be completed at the direction of the Contracting Officer at Government expense. If the test proves to be positive, the Contractor may be required to hire a Certified Industrial Hygienist at Government expense. He will determine how and the cost to remove the asbestos. The Contractor will then submit a cost proposal to the Contracting Officer based on the findings of the Certified Industrial Hygienist.

25. Is a bond required? What is the % required?

25. GOV Response: A bid guarantee is required and is 20% or $2 million, whichever is less. See far

26. Please confirm that only the original sealed bid is required.

26. GOV Response: Confirmed, along with bid submitted via the VA Vendor Portal.

27. Please confirm the bid due time is EST.

27. GOV Response: Confirmed.

28. Do we need to send the bid bond in before bid day? Or will a copy in the bid work with hard copy to follow?

28. GOV Response: Yes.

29. Attachment 5, Contractor Cost Estimate Worksheet. Can we use our own breakdown format?

29. GOV Response: No.

30. Is SWPPP plan submitted and approved by government and applied to this site? Whereas, contractor does not have to register with NPDES/Indiana and apply for a SWPPP.

30. GOV Response: The NPDES permit shall be applied for by the Contractor. Indiana does not require a NPDES certified installer to implement the requirements of the NPDES permit. It is the responsibility of the Contractor to adhere to requirements of the NPDES permit and keep the SWPPP on site and up to date to changing site conditions.

31. Drawings state contractor to obtain permits for project. What permits are required? Is there a building permit with city of Marion required?

31. GOV Response: Contractor shall be required to obtain all permits applicable to the project including but not limited to NPDES permit, land disturbance permit, and drainage permit.

32. Have the SWPPP fees been paid to the local and state NPDES registration? Ie. Contractor does not need to include SWPP state registration fees.

32. GOV Response: Contractor is responsible for applicable fees to obtain NPDES permit and other permits as required for project work.

33. Drawing CG-103 chain of responsibility says Owner and contractor are co-permitees for the North Dakota Pollutant discharge system (NDPDES) construction permit. Is there a reason for North Dakota SWPPP plan? How does North Dakota vary from the State of Indiana compliance?

33. GOV Response: NDPDES is noted in error. Chain of responsibility is to NPDES.

34. Granite section markers, as shown on 8/LC-503 show frost depth as not defined. Please provide actual length dimension required for frost line from Architect/Engineer of record.

34. GOV Response: Frost dept is 3’-0” per geotechnical report. See sheet SS000 (sheet 32 of 46) for further information.

35. Bid Date submission is set for 10AM Monday August 23. Will the VA please consider moving bid date and time to another day than Monday? Typically, Mondays limit subcontractor, vendor, and suppliers timely submission of required pricing. This limits contractor competitiveness for the government.

35. GOV Response: Bid due date extended until Wednesday, September 1st.

Virtual Bid Opening: (872) 701-0185, Conference ID 223 969 067#.

36. The POP for this project is 270 days (aprx 9 months). This POP duration seems too tight considering the amount of earthwork needed for preparation of site for crypt installation.

36. GOV Response: The period of performance is 270 calendar days.

37. The POP for this project is 270 days (aprx 9 months). This POP duration seems too tight when also considering time for submittal, purchase, manufacturing, delivery, and installation of crypts in earth, after earthwork preparation.

37. GOV Response: See response to question 36.

38. Drawing O-100 Note 12 calls for site fencing and shown on drawing D-101. There are no details, sections, or information on required makeup of this temp fencing. Please provide temporary fencing for bid pricing.

38. GOV Response: See specifications section 01 00 02 GENERAL REQUIREMENTS – 1.5 OPERATIONS AND STORAGE AREAS – 1 for construction fencing requirements. In addition to the chain link construction fence, screening shall be provided with a minimum of 90% blockage.

39. Spec section 02 21 00 Site Surveys requests contractor to provide perform a site survey of land, public documents, title searches, easements, possession, ownership, topographic survey, layout of all buildings, markers, boundaries, utilities, etc. Additionally, spec section requires contractor professional land surveyor to work with the government's architect to produce CADD files, vicinity maps, plats, surveys, contour maps, survey boundaries, etc. All of this information has been provided by the governments Architect/Civil Engineer of Record in the solicitation drawings as shown on the site civil drawings CS-101 -CS-107.

We assume that it is not the intent for the contractor to re-create civil drawings, design, layout, plats, etc as required in spec section 02 21 00 as that information has already been provided to the contractor.

39. GOV Response: Specification section 02 21 00 refers to any additional survey work required if existing conditions differ from the signed PDF drawings.

40. Granite Section markers, as shown on 8/LC-503 do not have required color or material type provided in spec section 09 06 00 Schedule. Please provide granite type and color.

40. GOV Response: See sheet LC-503, Detail 8. New section markers shall match existing granite color and type. Shop drawings and samples will be required to be provided by the Contractor for review/approval.

41. Boring Logs on BL-101 water level observation note (at bottom of log) show water was not observed at the time of boring and at boring completion; however, water level observations are shown on the table in depth below existing grade. The borings were made in dry season (July 2020). The site observation / boring / soils reports are not included in RFP to draw conclusion based on the professional engineer’s observations. Please provide by amendment, copy of the site observation/boring/soils report completed in July 2020 along with the professional engineer’s final report.

41. GOV Response: Geotechnical report will be provided as an addendum.

42. Spec section 31 23 19 dewatering included with RFP. Boring Logs on BL-101 show water level observations are lower that subgrade for the crypts. It is unclear with this spec section was included in the RFP for wellpoint type dewatering requirements. However, conclusions for proposals cannot be made without reviewing the professional engineer’s report along with the site observation/boring/soils report conclusions. Please provide copy, by amendment, the site observation/boring/soils report along with the professional engineer’s report conclusion.

42. GOV Response: Section 31 23 19 Dewatering is included as an option should site conditions require dewatering due to unusually high precipitation and infiltration. It is not anticipated that dewatering will be required due to groundwater.

43. Spec section 31 23 19 dewatering requires professional design with sealed engineered drawings for dewatering systems. However, the drawings and civil design do not show or indicate locations/requirements for any dewatering systems. Please provide locations and requirements for dewatering on the civil plan by amendment.

43. GOV Response: See response to question 42.

44. The RFP POP is 270 calendar days. It appears that project could be awarded by end of fiscal year FY 2021 / Sept 30th. NTP stated at 10 days after award. Has weather and winter season been factored with the RFP to account for typical weather days within the 270 days? Weather day historical data has not been included in the RFP for Marion, IN. If work proceeds accordingly to stated days in this RFI, the work will begin and proceed during the fall and winter months. It seems that 270 calendar days is not realistic due to amount of earthwork to be performed over the winter season. Has weather/winter been factored in the government’s 270 POP for the project?

44. GOV Response: Yes.

45. There will be significant soils removal in the earthwork operation for the crypt area of work. A significant amount of topsoil and backfill will need to be stockpiled for the completion phase of the crypt installation for coverup. There is a limited space/area for stockpiling with this site/cemetery. Drawing O-100 operations drawing does not show or indicate area(s) for soils stockpiling. Please indicate location where soils can be stockpiled.

45. GOV Response: Sheet O-100 indicates a staging area. This area can also be used for stockpiling of soils as needed, provided that permission is obtained from the Cemetery Director and VA Medical Center staff. Additionally, the area demarked as “Future PPC Section 15” on Site Plan sheet CS-101 (pg 7 of 46) can be used for stockpiling of soils and staging area.

See attached document: S06_Attachment 1_Terracon Geotecnical Report - CJ205083 - Gravesite Expansion.

End of Document