36C78621B0008 0003.docx

DOCX document 27 KB Posted

Attached to
5680--Eagle Point 906-016 Expansion Construction (VA-21-00060646)
Solicitation number
36C78621B0008
Issued by

About this file

This document contains details regarding a federal contract solicitation for expansion construction work at the Eagle Point National Cemetery in Oregon. The Department of Veterans Affairs intends to issue a solicitation to install approximately 2,200 columbarium niches, 595 in-ground cremains sites, and 670 additional columbarium niches if additional funding becomes available. The work includes site preparation, excavation and grading, installation of walks and pavers, drainage, and utility systems. The solicitation is designated as a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses. Offers are due on or around May 17, 2020, and the contract value is estimated between $1 million and $5 million. Offerors must be registered in the System for Award Management and Vendor Information Pages databases to be considered for award.

View the file

Other files

File Type Posted
Eagle Point National Cemetery Geotechnical.pdf PDF
36C78621B0008 0005.docx DOCX document
36C78621B0008 0004.docx DOCX document
COLUMBARIUM DETAILS-CC501 COLUMBARIUM DETAILS 1-Revision20210803.pdf PDF
36C78621B0008 0002.docx DOCX document
36C78621B0008 0001.docx DOCX document
P07 Eagle Point.docx DOCX document
1_EPNC-P2-BD-Plans_GI001-CC103.pdf PDF
2_EPNC-P2-BD-Plans_CC104-CC507.pdf PDF
4_EPNC-P2-BD-Plans_LI201-SS502.pdf PDF
210318 Eagle Point 906-016 Bid Doc Specfications.pdf PDF
3_EPNC-P2-BD-Plans_LP101-LI104.pdf PDF
IFB Lump Sum Division Spreadsheet.xlsx XLSX spreadsheet
36C78621B0008_1.docx DOCX document
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7.

ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF

PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE

OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:

Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERE

D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED

STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF

CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF

SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 906-016 36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle VA 22172 36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle VA 22172 To all Offerors/Bidders

36C78621B0008 08-16-2021

X X X No Change in Bid Opening Date The purpose of Amendment-0003 is to provide Government responses to RFI questions.

See Continuation Page for details.

THE Q&A / RFI PERIOD HAS ENDED.

Flora Taylor Contracting Officer Amendment-0003 – Solicitation 36C78621B00008 Eagle Point Cemetery Expansion -Eagle Point National Cemetery Project NO# 906-016 Contractor Questions & GOV Responses

Question: 1 - Vendor Portal & Column Drawing Question There are three Interior Piers between EXIST grid line and grid line C. Please provide footing / reinforcing detail, and pier / reinforcing detail on Drawing SS101.

Response: Detail 4/SS101 provides dimensions for the footing at the pier. No additional reinforcing required – continue typical footing reinforcing of detail 1/SS502 through this area. For the “pier” portion, it will look similar to column detail 6/SS501 but with only (3) #5 verts (no ties needed). Please find the attached drawing for the required reinforcing for the three interior piers.

Question: 2 - Columbarium Cap It appears that the columbarium cap called out in the specs is different then the existing caps on site. Please clarify what the intended cap quarry/material/color that is to be used.

Response: The intent is to match the existing columbarium caps grade, classification, color, etc. Attached is Stone Cap Information/Testing Information from the supplier who supplied the stone caps for phase 1. Color Indiana Full Color Blend

Question: 3 - Stone Veneer The stone Veneer quarry (Gordon Stone Company) is not currently offering the thin veneer at this time. Since this product is not offered at this time what it to be used in it's place?

Response: The intent for this wall is use the same stone (Oklahoma Sandstone Quartz) and to be thin veneer. The contractor shall provide the means to generate the thin veneer as shown on the drawings and specifications.

Question: 4 - Grading Plan According to the plans there appears to be an average fill of 6’ to expand the slope from the existing contours. The fill appears to range from 1’ up to 7’. Per the explanation during the first walk through in mid July. It was perceived that the top of the existing grave site elevation would carry out to the end of the grading limits and abruptly slope down holding a 2:1 slope. Also while onsite and observing the existing topography and comparing it to the new grading plan on CS102 they do not appear to correlate with each other. Can you please confirm that the existing elevations and the proposed new contours are accurate. Also what direction are we going to go with? A) Carry out the top of slope and slope down holding the minimum 2:1 per the conversation during the walk through? B) build per plan matching new contours. Option A would carry a Fill amount four times more than option B.

Response: The existing conditions survey was completed pre-design and is believed to be accurate. Please follow the proposed contours elevations per sheet CS102.

End of Document