36C78620B0003 0001.docx

DOCX document 100 KB Posted

Attached to
Y1PZ--Columbarium Plaza 2 Leavenworth National Cemetery Project: 897CM3022
Solicitation number
36C78620B0003
Issued by

About this file

This amendment to a solicitation provides responses to questions from prospective bidders for the construction of Columbarium Plaza 2 at Leavenworth National Cemetery. The scope of work includes demolition, site preparation, erosion control, excavation, backfilling, grading, foundations, footings, columbaria walls consisting of 1,720 niches, irrigation, landscaping, signage, storm drainage, utilities, road pavement, and curbs. Bidders must acknowledge receipt of the amendment by the unchanged due date of May 29, 2020 at 2:00 PM Eastern time. The amendment clarifies that onsite soils may be used if specifications are met, excess soil must be hauled offsite by the contractor, and the designated construction route and staging area are shown on provided drawings. Revised drainage details are also included with the amendment.

View the file

Other files

File Type Posted
36C78620B0003 0002.docx DOCX document
15342-C-108 STORM UTILITY PLAN-2020.05.19.pdf PDF
36C78620B0003-002.pdf PDF
36C78620B0003-005.pdf PDF
36C78620B0003-004.pdf PDF
36C78620B0003-003.pdf PDF
36C78620B0003-006.pdf PDF
36C78620B0003-001.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

36C786 05-20-2020

897CM3022

897CM3022

36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle VA 22172

36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle VA 22172 To all Offerors/Bidders

36C78620B0003 04-29-2020

X

897CM3022

COLUMBARIUM PLAZA 2, LEAVENWORTH NATIONAL CEMETERY: The purpose of this amendment is to provide responses to questions received and provide a revised drawing sheet 18.

The bid due date remains UNCHANGED at 5/29/2020 at 2:00 PM Eastern time.

*SEE CONTINUATION PAGE*

VALERIE WALLACE

CONTRACTING OFFICER

VA-NCA-2020-C729FF06

36C78620B0003

COLUMBARIUM PLAZA 2

LEAVENWORTH NATIONAL CEMETERY

897CM3022

QUESTIONS AND ANSWERS

1. Suitability of Onsite Material Is the onsite material acceptable for use as backfill?

Government Response: Yes, the onsite soil may be used if it meets the requirements outlined in specification section 31 20 11 and the geotechnical report.

2. Has a proctor been formed on onsite material?

Government Response: No, a proctor has not been performed on the onsite material and soil testing has been limited to what is provided in the geotechnical report. The contractor is required to test material as required in specification sections 01 45 29 and 31 20 11.

3. Onsite excess spoils disposal Is there a dumpsite available onsite for excess soils or will they have to be hauled offsite?

Government Response: Onsite excess soils shall be hauled offsite by the contractor at their own expense.

4. Designated Construction Route Is there a designate construction route for ingress and egress to the worksite?

Government Response: Yes, the contractor is to close Riverview Drive in the designated locations shown on sheet O-101. The contractor’s staging area and project area shall be enclosed with a temporary chain-link fence. See sheet D-101 for more information.

5. Grid line On Sheet B101 boring locations there is a straight line that runs close to B101 and over the top of B103. This line runs from the left side of the page to the right side of the page. It is not a contour line. What is this line?

Government Response: The line means nothing. Disregard from the sheet.

6. Soils Report Clarification The soils report shows rock encountered at varying depths which would indicate a rock ledge in the area of the excavation. If the foundation fails on differing material (rock and soil) are we to install on varying types of material?

Government Response: It is acceptable to support foundations on a combination of clay soils, engineered fill, and moderately to slightly weathered bedrock. If the bedrock is highly weathered and fractured, some over-excavation would be required.

7. Elevations on structural drawings There are no elevations on the structural drawings and it references the architectural. Please confirm the top and bottom of footing elevations.

Government Response: Top of Footing Elevations (TFE) is shown on sheet S-101. Footing size is referenced on sheet S-101 Foundation Plan Notes.

8. Foundation drain elevation Geo tech report page 10 shows a footing drain at/alongside the footing. If you take the elevation on the grid line C4 on page C108 the flow line of the perforated footing drain is 787.50 this would put it approx 1'0" below the bottom of the footing at grid line C4 and 1'6" below the footing at grid line 4A. Is the footing drain to be install per grades on C108 or the Geo tech report?

Government Response: Revised cleanout and catch basin invert elevations have been revised. See attached revised Sheet C-108.

9. Foundation drain Sheet 4/S502 does not show drain tile in the upper backside of wall. Is one required?

Government Response: Yes, reference CO-22 and CO-25 on 1/C-108.

10. Benches and Trash Receptacles Typically for the VA cemetery projects we see the S-424 with a special hinged lid for vases and S-42 with a convex lid and a self-close door for trash. The detail image reflects this. However, the specs state that the two receptacles will be the same model. Should the trash and vase receptacles be the same model? As for the benches, I could use a little help selecting the model. The details show a backed bench with no end arms and horizontal slats. However, the specs state there should be end armrests and vertical steel slats. Should we base the design on the specs or the detail image? Judging by the specs I think RB-28 and the matching RB-12 is probably correct, but I wanted to confirm.

Government Response: Provide the trash and vase receptacle as shown on drawing sheet C-501, detail 1. There are two different bench types for this project; 6’ bench without a backrest, 6’ bench with a backrest. Both benches shall have end armrests and may have vertical or horizontal steel slats. These benches would correspond to the RB-28 and RB-12 models.

See attached document: 15342-C-108 STORM UTILITY PLAN-2020.05.19.

End of Document