36C78619R0034-0001000.docx

DOCX document 21 KB Posted

Attached to
Repair Ornamental Fencing at Ft. Sam Houston National Cemetery
Solicitation number
36C78619R0034
Issued by

About this file

36C78619R0034 0001 36C78619R0034 0001.docx

View the file

Other files

File Type Posted
36C78619C0064-000.docx DOCX document
36C78619R0034-004.pdf PDF
36C78619R0034-003.pdf PDF
36C78619R0034-005.pdf PDF
36C78619R0034-001.docx DOCX document
36C78619R0034-006.pdf PDF
36C78619R0034-002.pdf PDF
36C78619R0034-000.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 03-18-2019 7899-000054

789CM3919

36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 155 Van Gordon Street, Suite 510 Lakewood, CO

80228 36C786 See block 6.

To all Offerors/Bidders

36C78619R0034 03-18-2019

X X X

X See Continuation Pages.

Jerry L. Hodson Jr.

Contracting Officer

CONTINUATION PAGE

AMENDMENT-0001, Solicitation 36C78619R0034 Repair Ornamental Fencing at Ft. Sam Houston National Cemetery Contractor Questions & GOV Responses

1. Are there any records to indicate the manufacturer of the current fence installed at the Cemetery?

1. GOV Response: Unfortunately no records, cut sheets, or submittals are available that would indicate the original manufacturer(s) of the existing ornamental fencing. Based on past construction documents, the ornamental fencing was installed after 2001.

2. Is there a procedure for gaining access to the location for a site visit?

2. GOV Response: There is not a procedure for gaining access to the cemetery for the site visit. We are open to the public. Entrance is on Harry Wurzbach, come in the main gate and proceed on San Antonio Blvd for approximately one mile. At dead end, take a left and park at the administration building. Meeting will be held in administration conference room. Contractor to coordinate with the Contracting Officer and the Cemetery. Note: Access to all of the fencing can be performed from the inside of the cemetery property.

3. In an interest to match the existing fencing as closely as possible, can the government provide the original source for the current components (pickets, rails, posts, caps, and brackets)?

3. GOV Response: See response to Question #1.

4. In an interest to match the existing fencing as closely as possible, can the government provide the gauge (thickness) of the metal in the pickets, rails, and posts individually?

4. GOV Response: The contract scope of work requires the use of Commercial Grade materials. Industry standards for Commercial grade ornamental fence specifications are: Posts – 12 gauge minimum, Rails – 12 gauge minimum, and Pickets – 14 gauge minimum.

Note: The Contractor shall measure the material thickness of the existing fencing material. If the material thickness is found to be thinner than listed above, then the above listed gauges shall be applied to this contract and the materials installed. If the existing thickness is greater than the gauges listed above, then the Contractor shall provide materials that match the existing greater thickness.

5. Will the government use the Federal Highway Administration's Manual on Uniform Traffic Control Devices (MUTCD) or the Texas Manual on Uniform Traffic Control Devices for traffic control standards? If neither, what standard do we apply for traffic control?

5. GOV Response: Yes. See the following guidance that will be added to the contract Scope of Work:

1. The Contractor shall prepare and submit in advance a written traffic control program in accordance with the recommendations in Part VI of the "Manual of Uniform Traffic Control Devices," (MUTCD) current edition, for review and approval by the COR.

2.Contractor shall also submit a project phasing plan with their schedule. The Contractor’s plan shall incorporate the following restrictions:
a.During public visiting (i.e. business) hours (Sunday – Saturday, 7:00 am to 4:30 pm) two-way traffic shall be maintained at all times on the main boulevards. The Contractor shall provide and place temporary signage and barriers in accordance with the MUTCD to direct and notify traffic of any new two-way conditions.
b.Weekend and after-hours closure may be considered for other areas by approval of the COR.

c. The construction access route to the cemetery shall be as directed by the COR and Cemetery Director. The inbound and outbound lanes of San Antonio Boulevard shall be maintained open at all times for visitors and funeral corteges.

d. The Contractor is required to discontinue his work sufficiently in advance of Easter Sunday, Mother's Day, Father's Day, Memorial Day, Veteran's Day and/or Federal holidays, to permit him to clean up all areas of operation adjacent to existing burial plots before these dates.

3. When other than normal business hours are approved in any case, all traffic control devices shall be removed to allow normal traffic flow (one lane) the following morning (i.e. at 7:00 am).:

6. Will the Government allow traffic to self-regulate in accordance with the appropriate MUTCD?

6. GOV Response: See the response to Question # 5 above.

7. Is a traffic control plan required?

7. GOV Response: See the response to Question # 5 above.

8. Who is the regulating authority for approval of traffic control on Winans Road?

8. GOV Response: See the Security Requirements, Paragraph B.1 as stated in the Scope of Work. Traffic on Winans is regulated by JBSA 502nd Security forces. All work for fence replacement can be conducted from inside the fence on Cemetery Property. If contractor needs to work from base property or receive deliveries, they will be responsible for vetting sub-contractor or employees to receive a day pass.

9. Where is the laydown yard and approximately how much area is available?

9. GOV Response: Laydown yard is at the back of the property. Area is a shared space with two other contractors. Alternate laydown area will a portion of maintenance parking lot. After award, site will be determined with Director and COR.

10. Is the laydown yard secured or will the contractor need security fencing around its materials and equipment?

10. GOV Response: Security will be the responsibility of the contractor. We do not provide fencing and fencing is not in the laydown area.

11. Will the Government allow a follow up RFI to clarify questions that may arise from the first RFI response?

11. GOV Response: YES.