About this file

36C78619Q0121 S02 Planting.pdf

View the file

Other files

File Type Posted
36C78619Q0121-0001001.pdf PDF
36C78619Q0121-0001000.docx DOCX document
36C78619Q0121-007.pdf PDF
36C78619Q0121-003.pdf PDF
36C78619Q0121-000.docx DOCX document
36C78619Q0121-006.pdf PDF
36C78619Q0121-002.pdf PDF
36C78619Q0121-004.pdf PDF
36C78619Q0121-008.pdf PDF
36C78619Q0121-005.pdf PDF
36C78619Q0121.docx DOCX document
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11-01-16

PLANTING

32 90 00 - 1

SECTION 32 90 00

PLANTING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Plants, soils, turf, and landscape materials and accessories.

1.2 RELATED REQUIREMENTS

A. Topsoil Materials, Stripping and Stockpiling: Section 31 20 00, EARTH

MOVING.

B. Erosion control: Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS.

C. Topsoil Placement and Compaction Test: Section 31 20 00, EARTH MOVING.

1.3 APPLICABLE PUBLICATIONS

A. Comply with references to extent specified in this section.

B. American National Standards Institute (ANSI) Publications:

1. ANSI Z60.1-2014 - Nursery Stock.

2. ANSI Z133.1-2012 - Tree Care Operations-Pruning, Trimming, Repairing, Maintaining, and Removing Trees and Cutting Brush- Safety

Requirements.

C. Hortus Third, most current edition: A Concise Dictionary of Plants

Cultivated in the United States and Canada.

D. National Cemetery Administration (NCA):

1. Handbook 3410 - Integrate Pest Management.

2. Handbook 3420-11 - Turfgrass Maintenance.

E. Turfgrass Producers International (TPI):

1. 2006 Guideline Specifications to Turfgrass Sodding.

F. United States Department of Agriculture (USDA):

1. Federal Seed Act-2011 - Rules and Regulations of the Secretary of

Agriculture.

G. United States Environmental Protection Agency (EPA):

1. 40 CFR Part 503-1993 - Biosolids Rule.

1.4 SUBMITTALS

A. Manufacturer's Literature and Data:

1. Description of each product.

a. Sod.

b. Soil amendments.

c. Erosion control materials.

B. Certificates: Certify products comply with specifications.

32 90 00 - 2

C. Before delivery, submit notarized certificates for approval to COR attesting that following materials meet specified requirements:

1. Sod.

1.5 QUALITY ASSURANCE

A. Installer Qualifications:

1. Regularly installs specified materials and products.

2. Installed specified products with satisfactory service on five similar installations for minimum five years.

1.6 DELIVERY

A. Deliver products in manufacturer's original sealed packaging.

B. Mark packaging, legibly. Indicate manufacturer's name or brand, type, production run number, and manufacture date.

C. Before installation, return or dispose of products within distorted, damaged, or opened packaging.

D. Bulk Products:

1. Deliver bulk products away from buildings, utilities, pavement, and existing turf and planted areas. Maintain dry bulk product storage away from contaminants. Protect products from weather.

2. Install erosion control materials to prevent erosion or displacement of bulk products.

E. Notify COR of delivery schedule five days in advance, minimum. COR will inspect materials upon arrival. Remove unacceptable plant materials from project site immediately.

F. Protect sod from drying out.

1.7 STORAGE AND HANDLING

A. Store fertilizers and packaged materials in dry locations away from contaminants.

B. Keep sod moist and protect from exposure to wind and direct sunlight.

1.8 FIELD CONDITIONS

A. Seasons and Conditions:

B. Restrictions: Do not plant when ground is frozen, snow covered, saturated or in otherwise unsuitable condition for planting.

1.9 WARRANTY

A. Comply with "Warranty" requirements, including the following supplements:

32 90 00 - 3

1. One Year Plant and Turfgrass Warranty: Warranty begins when

Government accepts plants and turfgrass but not before end of

Landscape Plant and Turfgrass Establishment Period.

2. Replace any dead plant material and any areas void of turfgrass immediately during warranty period and during an active growing season. One year warranty for replaced plants and turfgrass begins on day replacement work is completed and accepted.

3. Government will inspect replacement plants and turfgrass at end of

Warranty period. Replace any dead, missing, or defective plant material and turfgrass immediately and during growing season.

Warranty ends on date of this inspection provided work specified in this section is complied.

PART 2 - PRODUCTS

2.1 PRODUCTS - GENERAL

A. Provide each product from one source or manufacturer.

B. Turf Grasses: Comply with the varieties specified or shown in plant list.

C. Warrant plants are true to botanical name as listed in Hortus Third.

D. Maintain equipment, tools and machinery on project site in sufficient quantities and capacity for proper execution of Work.

2.2 TOPSOIL

A. Topsoil: Provide well-graded soil of good uniform quality, natural, friable soil representative of productive soils in project vicinity.

Topsoil to be free of subsoil, foreign matter, objects larger than

25 mm (1 inch) in any dimension, toxic substances, weeds and any material or substances that may be harmful to plant growth and have pH value of minimum 6.0 and maximum 7.0, and be best suited to region, climate and plant material specific to project.

B. Obtain material from stockpiles established under Section 31 20 00, EARTH MOVING, subparagraph, Stripping Topsoil that meet general requirements stated above. Amend topsoil not meeting pH range specified by the addition of pH adjusters.

C. When sufficient topsoil is not available on project site to specified depth, provide additional topsoil. Minimum 10 days before topsoil delivery, notify COR of sources from which topsoil will be furnished.

Obtain topsoil meeting general requirements stated above.

32 90 00 - 4

2.3 TURFGRASS FERTILIZER

A. Provide commercial grade granular fertilizer, free flowing, uniform in composition, and complying with applicable state and federal regulations. Submit fertilizer manufacturer's warranted statement of analysis. Fertilizer contain minimum 20 percent nitrogen by weight (50 percent from controlled release source such as sulfur coated urea), 5 percent available phosphoric acid, and 15 percent potash. Liquid starter fertilizer for hydro mulch slurry, commercial type with 50 percent of nitrogen from controlled release source.

B. Erosion Control Blanket: Cellulose fiber blanket bonded to 6 mm

(1/4 inch) square plastic net weighing 10 kg/100 sq. m

(20 lbs./1000 sq. ft.) in 1250 mm (50 inch) wide rolls.

2.4 SOD

A. Sod: Nursery grown, certified sod as classified in TPI "Guideline

Specifications to Turfgrass Sodding." Sod must also conform to turfgrass species limitations as outlined in the project scope of work.

PART 3 - EXECUTION

3.1 PREPARATION

A. Examine and verify substrate suitability for product installation.

B. Protect existing construction and completed work from damage.

C. Examine areas to receive planting for compliance with requirements and other conditions affecting performance.

D. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 FINISH GRADING

A. After ripping subgrade for topsoil/subsoil bonding, spread topsoil evenly to minimum 150 mm (6 inches) deep. Incorporate topsoil at least

50 to 75 mm (2 to 3 inches) into subsoil to avoid soil layering. Spread additional topsoil as required to meet finish grades. Do not spread topsoil when frozen or excessively wet or dry. Correct irregularities in finished surfaces to eliminate depressions. Protect finished lawn areas from damage by vehicular or pedestrian traffic. Complete lawn work only after areas are brought to finished grade.

32 90 00 - 5

3.3 APPLICATION OF FERTILIZER AND SOIL AMENDMENTS FOR TURFGRASS AREAS

A. Apply turfgrass fertilizer and adjust soil acidity as recommended by soil test results. Add soil conditioners as specified for suitable topsoil in PART 2.

3.4 SODDING

A. Place sod according to TPI Guideline Specifications for sodding. Lay sod at right angles to slope or the flow of water. On slope areas, start at bottom of slope.

B. Finishing: After sodding, blend edges of sod smoothly into surrounding area. Roll with lightweight roller to eliminate air spaces between sod and firmed soil.

3.5 WATERING

A. Watering: Start watering turfgrass areas immediately after installation at sufficient rate to ensure thorough wetting of soil to minimum 50 mm

(2 inches) deep. Supervise watering operation to prevent run-off.

Supply necessary pumps, hoses, pipelines, and sprinkling equipment.

Repair all areas damaged by water operations. Keep soil surface constantly moist, not wet, until turfgrass plants are well established.

3.6 EROSION CONTROL MATERIAL

A. Install and maintain erosion control material on designated areas as shown on drawings. Prepare, fertilize and vegetate areas to be covered, before erosion material is placed. Immediately following planting operations, lay erosion control material evenly and smoothly and in contact with soil throughout. Omit straw mulch from all seeded areas receiving erosion control material.

B. For waterways, unroll erosion control material in direction of water flow. When two or more strips are required to cover ditch area, overlap strips minimum 100 mm (4 inches). For strips to be spliced lengthwise, overlap ends minimum 150 mm (6 inches) with upgrade section on top.

C. On slopes, place erosion control material either horizontally or vertically to slope with edges and ends of adjacent strips butted tightly against each other.

D. Staple each erosion control strip in three rows (each edge and center with center row alternately spaced) with staples spaced maximum 1200 mm

(4 feet) longitudinally. For two or more strips side by side on slopes, install common row of staples on adjoining strips. Staple all end

32 90 00 - 6 strips at 300 mm (12 inch) intervals at end. Firmly embed staples in underlying soil.

E. Provide erosion control maintenance to repair damage by erosion, wind, or any other cause. Maintain, protect, repair, or replace erosion control material until Termination of the Plant and Warranty Period.

3.7 LANDSCAPE PLANT AND TURFGRASS ESTABLISHMENT PERIOD

A. Landscape Plant and Turfgrass Establishment Period: Begins immediately after installation, with COR's approval, and continues through growing season sufficiently long for turfgrass and landscape plant materials to become establish and provide satisfactory to District Agronomist and

NCA. Conditions and appearance are as follows:

1. Turfgrass has obtained minimum of 98 percent generally weed-free surface cover.

2. Maintain plant and turfgrass during establishment period.

3. Plants and turfgrass will not be accepted until completion of acceptable establishment period.

4. During Landscape Plant and Turfgrass Establishment Period complete the following:

a. Water plants and turfgrass to maintain moist soil surface until plants and turfgrass are well established.

b. Provide the following during turfgrass establishment:

1) Eradicate weeds. Water, fertilize, overseed, and perform other operation necessary to promote growth of turfgrass.

2) Mow turfgrasses as often as necessary to maintain

NCA specified mowing height for each type of turfgrass before final acceptance. Begin mowing when cool season turfgrass is

100 mm (4 inches) high.

c. Sod will be evaluated for species and health thirty (30) days after laying last piece and reevaluated each 15 days during the establishment period. A satisfactory stand of grass plants from sod operation will be living sod, uniform in color and leaf texture. Bare spots to be maximum 1250 sq. mm (2 sq. inches).

Joints between sod pieces to be tight and free of weeds and other undesirable growth.

d. Repair damage caused while making plant or turfgrass replacements.

32 90 00 - 7

3.8 LANDSCAPE PLANT AND TURFGRASS ACCEPTANCE

A. Criteria for Acceptance of Turfgrass:

1. Sod: Living sod grass plants uniform in color and leaf texture and well rooted into soil below so that gentle pulling of turfgrass leaves by hand does not dislodge sod. Bare spots to be maximum

1250 sq. mm (2 sq. inches). Joints between sod pieces shall be tight and free from weeds and other undesirable growth.

3.9 CLEANING

A. Remove and legally dispose of all debris, rubbish, and excess material from project site.

B. Where existing or new turfgrass areas have been damaged or scarred, restore disturbed areas to original condition.

C. In areas where planting and turfgrass work have been completed, clear the area of all debris, spoil piles, and containers.

3.10 PROTECTION

A. Protect plants and turfgrass areas from traffic and construction operations. Erect barricades, as required, and place approved signs at appropriate intervals until final acceptance.

B. Remove protective materials immediately before acceptance.

C. Repair damage.

3.11 ENVIRONMENTAL PROTECTION

A. All work and operations to comply with requirements of Section

01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS.

- - - E N D - - -

PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Plants, soils, turf, and landscape materials and accessories.
1.2 RELATED REQUIREMENTS
A. Topsoil Materials, Stripping and Stockpiling: Section 31 20 00, EARTH MOVING.
B. Erosion control: Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS.
C. Topsoil Placement and Compaction Test: Section 31 20 00, EARTH MOVING.
1.3 APPLICABLE PUBLICATIONS
A. Comply with references to extent specified in this section.
B. American National Standards Institute (ANSI) Publications:
1. ANSI Z60.1-2014 - Nursery Stock.
2. ANSI Z133.1-2012 - Tree Care Operations-Pruning, Trimming, Repairing, Maintaining, and Removing Trees and Cutting Brush- Safety Requirements.
C. Hortus Third, most current edition: A Concise Dictionary of Plants Cultivated in the United States and Canada.
D. National Cemetery Administration (NCA):
1. Handbook 3410 - Integrate Pest Management.
2. Handbook 3420-11 - Turfgrass Maintenance.
E. Turfgrass Producers International (TPI):
1. 2006 Guideline Specifications to Turfgrass Sodding.
F. United States Department of Agriculture (USDA):
1. Federal Seed Act-2011 - Rules and Regulations of the Secretary of Agriculture.
G. United States Environmental Protection Agency (EPA):
1. 40 CFR Part 503-1993 - Biosolids Rule.
1.4 SUBMITTALS
A. Manufacturer's Literature and Data:
1. Description of each product.
a. Sod.
b. Soil amendments.
c. Erosion control materials.
B. Certificates: Certify products comply with specifications.
C. Before delivery, submit notarized certificates for approval to COR attesting that following materials meet specified requirements:
1. Sod.
1.5 QUALITY ASSURANCE
A. Installer Qualifications:
1. Regularly installs specified materials and products.
2. Installed specified products with satisfactory service on five similar installations for minimum five years.
1.6 DELIVERY
A. Deliver products in manufacturer's original sealed packaging.
B. Mark packaging, legibly. Indicate manufacturer's name or brand, type, production run number, and manufacture date.
C. Before installation, return or dispose of products within distorted, damaged, or opened packaging.
D. Bulk Products:
1. Deliver bulk products away from buildings, utilities, pavement, and existing turf and planted areas. Maintain dry bulk product storage away from contaminants. Protect products from weather.
2. Install erosion control materials to prevent erosion or displacement of bulk products.
E. Notify COR of delivery schedule five days in advance, minimum. COR will inspect materials upon arrival. Remove unacceptable plant materials from project site immediately.
F. Protect sod from drying out.
1.7 STORAGE AND HANDLING
A. Store fertilizers and packaged materials in dry locations away from contaminants.
B. Keep sod moist and protect from exposure to wind and direct sunlight.
1.8 FIELD CONDITIONS
A. Seasons and Conditions:
B. Restrictions: Do not plant when ground is frozen, snow covered, saturated or in otherwise unsuitable condition for planting.
1.9 WARRANTY
A. Comply with "Warranty" requirements, including the following supplements:
1. One Year Plant and Turfgrass Warranty: Warranty begins when Government accepts plants and turfgrass but not before end of Landscape Plant and Turfgrass Establishment Period.
2. Replace any dead plant material and any areas void of turfgrass immediately during warranty period and during an active growing season. One year warranty for replaced plants and turfgrass begins on day replacement work is completed and accepted.
3. Government will inspect replacement plants and turfgrass at end of Warranty period. Replace any dead, missing, or defective plant material and turfgrass immediately and during growing season. Warranty ends on date of this inspection provided work s...
PART 2 - PRODUCTS
2.1 PRODUCTS - GENERAL
A. Provide each product from one source or manufacturer.
B. Turf Grasses: Comply with the varieties specified or shown in plant list.
C. Warrant plants are true to botanical name as listed in Hortus Third.
D. Maintain equipment, tools and machinery on project site in sufficient quantities and capacity for proper execution of Work.
2.2 TOPSOIL
A. Topsoil: Provide well-graded soil of good uniform quality, natural, friable soil representative of productive soils in project vicinity. Topsoil to be free of subsoil, foreign matter, objects larger than 25 mm (1 inch) in any dimension, toxic subst...
B. Obtain material from stockpiles established under Section 31 20 00, EARTH MOVING, subparagraph, Stripping Topsoil that meet general requirements stated above. Amend topsoil not meeting pH range specified by the addition of pH adjusters.
C. When sufficient topsoil is not available on project site to specified depth, provide additional topsoil. Minimum 10 days before topsoil delivery, notify COR of sources from which topsoil will be furnished. Obtain topsoil meeting general requirement...
2.3 TURFGRASS FERTILIZER
A. Provide commercial grade granular fertilizer, free flowing, uniform in composition, and complying with applicable state and federal regulations. Submit fertilizer manufacturer's warranted statement of analysis. Fertilizer contain minimum 20 percent...
B. Erosion Control Blanket: Cellulose fiber blanket bonded to 6 mm (1/4 inch) square plastic net weighing 10 kg/100 sq. m (20 lbs./1000 sq. ft.) in 1250 mm (50 inch) wide rolls.
2.4 SOD
A. Sod: Nursery grown, certified sod as classified in TPI "Guideline Specifications to Turfgrass Sodding." Sod must also conform to turfgrass species limitations as outlined in the project scope of work.
PART 3 - EXECUTION
3.1 PREPARATION
A. Examine and verify substrate suitability for product installation.
B. Protect existing construction and completed work from damage.
C. Examine areas to receive planting for compliance with requirements and other conditions affecting performance.
D. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 FINISH GRADING
A. After ripping subgrade for topsoil/subsoil bonding, spread topsoil evenly to minimum 150 mm (6 inches) deep. Incorporate topsoil at least 50 to 75 mm (2 to 3 inches) into subsoil to avoid soil layering. Spread additional topsoil as required to meet...
3.3 APPLICATION OF FERTILIZER AND SOIL AMENDMENTS FOR TURFGRASS AREAS
A. Apply turfgrass fertilizer and adjust soil acidity as recommended by soil test results. Add soil conditioners as specified for suitable topsoil in PART 2.
3.4 SODDING
A. Place sod according to TPI Guideline Specifications for sodding. Lay sod at right angles to slope or the flow of water. On slope areas, start at bottom of slope.
B. Finishing: After sodding, blend edges of sod smoothly into surrounding area. Roll with lightweight roller to eliminate air spaces between sod and firmed soil.
3.5 WATERING
A. Watering: Start watering turfgrass areas immediately after installation at sufficient rate to ensure thorough wetting of soil to minimum 50 mm (2 inches) deep. Supervise watering operation to prevent run-off. Supply necessary pumps, hoses, pipeline...
3.6 EROSION CONTROL MATERIAL
A. Install and maintain erosion control material on designated areas as shown on drawings. Prepare, fertilize and vegetate areas to be covered, before erosion material is placed. Immediately following planting operations, lay erosion control material ...
B. For waterways, unroll erosion control material in direction of water flow. When two or more strips are required to cover ditch area, overlap strips minimum 100 mm (4 inches). For strips to be spliced lengthwise, overlap ends minimum 150 mm (6 inche...
C. On slopes, place erosion control material either horizontally or vertically to slope with edges and ends of adjacent strips butted tightly against each other.
D. Staple each erosion control strip in three rows (each edge and center with center row alternately spaced) with staples spaced maximum 1200 mm (4 feet) longitudinally. For two or more strips side by side on slopes, install common row of staples on a...
E. Provide erosion control maintenance to repair damage by erosion, wind, or any other cause. Maintain, protect, repair, or replace erosion control material until Termination of the Plant and Warranty Period.
3.7 LANDSCAPE PLANT AND TURFGRASS ESTABLISHMENT PERIOD
A. Landscape Plant and Turfgrass Establishment Period: Begins immediately after installation, with COR's approval, and continues through growing season sufficiently long for turfgrass and landscape plant materials to become establish and provide satis...
1. Turfgrass has obtained minimum of 98 percent generally weed-free surface cover.
2. Maintain plant and turfgrass during establishment period.
3. Plants and turfgrass will not be accepted until completion of acceptable establishment period.
4. During Landscape Plant and Turfgrass Establishment Period complete the following:
a. Water plants and turfgrass to maintain moist soil surface until plants and turfgrass are well established.
b. Provide the following during turfgrass establishment:
1) Eradicate weeds. Water, fertilize, overseed, and perform other operation necessary to promote growth of turfgrass.
2) Mow turfgrasses as often as necessary to maintain NCA specified mowing height for each type of turfgrass before final acceptance. Begin mowing when cool season turfgrass is 100 mm (4 inches) high.
c. Sod will be evaluated for species and health thirty (30) days after laying last piece and reevaluated each 15 days during the establishment period. A satisfactory stand of grass plants from sod operation will be living sod, uniform in color and lea...
d. Repair damage caused while making plant or turfgrass replacements.
3.8 LANDSCAPE PLANT AND TURFGRASS ACCEPTANCE
A. Criteria for Acceptance of Turfgrass:
1. Sod: Living sod grass plants uniform in color and leaf texture and well rooted into soil below so that gentle pulling of turfgrass leaves by hand does not dislodge sod. Bare spots to be maximum 1250 sq. mm (2 sq. inches). Joints between sod pieces ...
3.9 CLEANING
A. Remove and legally dispose of all debris, rubbish, and excess material from project site.
B. Where existing or new turfgrass areas have been damaged or scarred, restore disturbed areas to original condition.
C. In areas where planting and turfgrass work have been completed, clear the area of all debris, spoil piles, and containers.
3.10 PROTECTION
A. Protect plants and turfgrass areas from traffic and construction operations. Erect barricades, as required, and place approved signs at appropriate intervals until final acceptance.
B. Remove protective materials immediately before acceptance.
C. Repair damage.
3.11 ENVIRONMENTAL PROTECTION
A. All work and operations to comply with requirements of Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS.