About this file

36C78619Q0115 S02 Maps.pdf

View the file

Other files

File Type Posted
36C78619Q0115-0003000.docx DOCX document
36C78619Q0115-0003001.pdf PDF
36C78619Q0115-0002000.docx DOCX document
36C78619Q0115-0001000.docx DOCX document
36C78619Q0115-001.pdf PDF
36C78619Q0115-000.docx DOCX document
36C78619Q0115.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No. 774 CM3919 002 Scope of Work

Dayton National Cemetery Prefabricated 40’ x 60’ Clearspan Metal Equipment Building

December 2018

Provide all labor, materials, tools, equipment, transportation and supervision for the construction of a prefabricated 40’ x 60’ clearspan post-frame metal equipment building with an 18’ tall sidewall height at Dayton National Cemetery, Dayton, Ohio. The work includes procuring (ordering) and constructing the building per the manufactures requirements and in compliance with the International Building Codes (IBC) and local building codes. The work also includes the excavation for building column footings, placement of concrete for footings and placement and compaction of select gravel fill under the footings.

Engineered stamped shop drawings of the building shall be provided and approved by the COR prior to ordering of any materials. The work includes site investigation to verify all measurements and site conditions before start of the work and the ordering of any materials. All work shall be performed in a professional workmanship like manner. All adjacent disturbed surfaces shall be repaired to the same quality standards of the existing work and shall also match the adjacent areas. Properly remove and dispose all debris from government property. All work must be in accordance with applicable federal, state and local codes and regulations. The contractor shall be responsible for any applicable permits. A pre-bid visit by the bidder is required to get an accurate understanding of the work. All work must be done in strict accordance with the manufacturer’s requirements and installation guidelines and shall be performed by a licensed full time professional with two or more years of experience in the respective trade.

1) Procure and install a new post-frame structure with metal siding and metal roof meeting the following criteria/parameters:

a) 40’ x 60’ rectangular post-frame metal equipment building with 18’ tall sidewalls, clearspan design and a 3/12 to a 4/12 sloped gable roof.

b) 26-gauge steel roof panels and sidewall panels.

c) Color to be approved by COR from the range of available options. Provide minimum 25-year color on walls, trim and roof.

d) Full color trim on all door openings (two-roll up overhead garage doors each 14-feet wide x

16-feet high as well as one- 3’ x 7’ side door), sculptured eave and rake trim.

e) Factory applied finish on all components.

f) Erect the post-frame metal equipment building per the manufacturer’s requirements.

2) Map and site information follows:

Location Map

PROJECT AREA

Aerial View