Replace_Overhead_Doors_at_Maint_Bldgs-_SOW_Updated_1_17_19.pdf
PDF 2 MB Posted
- Solicitation number
- 36C78619Q0094
About this file
36C78619Q0094 0001 Replace Overhead Doors at Maint Bldgs- SOW Updated 1_17_19.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 083613SectionalDoors_-_Updated_1_17_2019.pdf | ||
| 36C78619Q0094_0001.docx | DOCX document | |
| 083613SectionalDoors.pdf | ||
| Wage_Determination_Black_Hills_Cemetery.pdf | ||
| 36C78619Q0094.docx | DOCX document | |
| BHNC_additional_requirements.pdf | ||
| Map_and_Aerial_Pictures_Black_Hill_National_Cemetery.pdf | ||
| 36C78619Q0094_1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project No. 884-19-104 Scope of Work
Black Hills National Cemetery Replace Overhead Doors at Utility Buildings-FCA Deficiency Corrections
October 2018
Provide all labor, materials, tools, equipment, transportation and supervision to replace 8 overhead doors at two maintenance utility buildings at the Black Hills National Cemetery, Sturgis, South Dakota. The work includes site investigation to verify all measurements and site conditions before start of the work and the ordering of any materials. All work shall be performed in a professional workmanship like manner. All adjacent disturbed surfaces shall be repaired to the same quality standards of the existing work and shall also match the adjacent areas. Properly remove and dispose all debris from government property. All work must be in accordance with applicable federal, state and local codes and regulations. The contractor shall be responsible for any applicable permits. A pre-bid visit by the bidder is required to get an accurate understanding of the work. All work shall be performed by a licensed full time professional with five or more years of experience in the respective trade.
1) At the two maintenance utility buildings replace the 8 existing overhead doors, electric door openers as well as the internal and external push button controls with 8 new (procure and install) pre-finished (white) steel insulated sectional overhead doors with windows, electric door openers, internal and external push button controls.
a) The approximate door sizes are: Utility Building One- (1 ea) 10’-2” H X 12’- 2” W, (1 ea) 10’2” H X 16’2” W, (1 ea) 10’2” H X 10’2” Utility Building Two- (2 ea) 14’2”H X 14’2” W, (3 ea) 10’1”H X 16’2” W
b) The Pre-finished (white) Door Sections shall be formed of hot-dipped galvanized steel not lighter than 24 gauge, with R-Value of 12 insulation and maximum U-Value of 0.0833 as well as insulated glass windows similar in style to the existing windows but above eye viewing height. Provide 2” thick double steel sandwich construction (steel interior and exterior).
c) Provide all new tracks, rails, torsion spring, hardware, weather stripping, etc. as well as the electric motor operators/door openers and the internal and external push buttons (remove the old, procure and install new) all designed to handle the newly installed insulated doors. Provide all connections for a complete and operating system. The push buttons shall function in the same manner as the existing and placed in the same location. The external push buttons shall be designed to handle the harsh weather conditions of the area.
d) Building will remain occupied during all garage door work, coordinate work with owner and provide temporary weather protection and secure the building after normal work hours (i.e. temporary door). This will be considered incidental to the cost of the contract.
e) Any areas disturbed in performance of this contract which may require restoration shall be restored by the contractor and considered incidental to the contract. Areas outside of the construction limits impacted by operations of the contractor shall be returned to the state it was found prior to new construction.
f) The route of construction traffic to and from the project site shall be clear of debris at all times as well as the required safety signage and barricades for the safe passage of visitors. Thoroughly clean up the work area at the end of each day’s work and at the completion of the project. Leave the premises clean and free of waste, scrap, used equipment or other material intentionally delivered to the site by the contractor or contractor’s personnel.
2) Map and Aerial picture follow:
Aerial View
Photos
Garage Doors to be Replaced
All New Garage Doors to have Windows
All Windows to be Placed above Eye Viewing Height
All Windows to be Similar in Style to Existing Windows
Example of Exterior Push Buttons to be Replaced
Example of Interior Push Buttons to be Replaced
Example of Electric Motor Operator/Door Opener to be Replaced