36C78619B0017-0001002.pdf
PDF 2 MB Posted
- Solicitation number
- 36C78619B0017
About this file
36C78619B0017 0001 190618 FRNC 910-008 Bid Specifications Final - Copy.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C78619C0143-000.docx | DOCX document | |
| 36C78619B0017-0002005.xlsx | XLSX spreadsheet | |
| 36C78619B0017-0002000.docx | DOCX document | |
| 36C78619B0017-0002002.docx | DOCX document | |
| 36C78619B0017-0002001.docx | DOCX document | |
| 36C78619B0017-0002003.pdf | ||
| 36C78619B0017-0002004.pdf | ||
| 36C78619B0017-0001001.xlsx | XLSX spreadsheet | |
| 36C78619B0017-0001000.docx | DOCX document | |
| 36C78619B0017-004.pdf | ||
| 36C78619B0017-003.docx | DOCX document | |
| 36C78619B0017-006.pdf | ||
| 36C78619B0017-005.pdf | ||
| 36C78619B0017-002.docx | DOCX document | |
| 36C78619B0017 36C78619B0017_1.docx | DOCX document | |
| 36C78619B0017-001.docx | DOCX document |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Package Project No. 910CM3008
Fort Richardson National Cemetery Gravesite Expansion 31 May 2019
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
NCA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS
00 01 10 Table of Contents (TOC)
00 01 15 List of Drawing Sheets
DIVISION 01 - GENERAL REQUIREMENTS
01 00 02 General Requirements (Minor NCA Projects)
01 33 23 Shop Drawings, Product Data, and Samples
01 42 19 Reference Standards
01 45 29 Testing Laboratory Services
01 57 19 Temporary Environmental Controls
01 74 19 Construction Waste Management
DIVISION 02 – EXISTING CONDITIONS
02 41 10 Demolition and Site Clearing
DIVISION 03 – CONCRETE
03 30 53 (Short-Form) Cast-in-Place Concrete
03 48 21 Precast Concrete Burial Crypts (Double Depth Lawn Crypt)
DIVISION 04 – MASONRY
04 72 00 Cast Stone Masonry
DIVISION 10 – SPECIALTIES
10 14 00 Exterior Signage
DIVISION 31 – EARTHWORK
31 20 00 Earth Moving
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements
32 12 16 Asphalt Paving
32 33 00 Site Furnishings
32 84 00 Planting Irrigation
32 90 00 Planting
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
DRAWING NO. DRAWING TITLE
G-001 COVER SHEET
V-101 TOPOGRAPHICAL SURVEY 1 OF 4
V-102 TOPOGRAPHICAL SURVEY 2 OF 4
V-103 TOPOGRAPHICAL SURVEY 3 OF 4
V-104 TOPOGRAPHICAL SURVEY 4 OF 4
B-101 CONSTRUCTION ACCESS ROUTE
B-102 EXISTING CONDITIONS
D-101 DEMOLITION PLAN
C-101 SITE PLAN
C-102 GRADING AND DRAINAGE PLAN
C-103 EROSION CONTROL PLAN
C-104 SIGNAGE PLAN
C-201 PLAN AND PROFILE
C-401 GRAVESITE NUMBERING PLAN
C-501 GRAVESITE DETAILS 1
C-502 GRAVESITE DETAILS 2
C-503 EROSION CONTROL AND SITE DETAILS
C-504 SIGNAGE DETAILS
LI101 IRRIGATION PLAN
LI501 IRRIGATION DETAILS
LI502 IRRIGATION DETAILS
LP101 PLANTING PLAN
LP501 PLANTING DETAILS
- - - END - - -
i
SECTION 01 00 02
GENERAL REQUIREMENTS (MINOR NCA PROJECTS)
TABLE OF CONTENTS
1.1 GENERAL INTENTION
1.2 STATEMENT OF BID ITEM(S)
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.4 CONSTRUCTION SECURITY REQUIREMENTS
1.5 FIRE SAFETY
1.6 OPERATIONS AND STORAGE AREAS
1.7 ENVIRONMENTAL CONTROLS
1.8 DISPOSAL AND RETENTION
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS
1.10 RESTORATION
1.11 PHYSICAL DATA
1.12 PROFESSIONAL SURVEYING SERVICES
1.13 LAYOUT OF WORK
1.14 As-Built Drawings
1.15 USE OF ROADWAYS
1.16 TEMPORARY TOILETS
1.17 AVAILABILITY AND USE OF UTILITY SERVICES
1.18 TESTS
1.19 INSTRUCTIONS
1.20 GOVERNMENT-FURNISHED PROPERTY
1.21 CONSTRUCTION SIGN
1.22 SAFETY SIGN
1.23 CONSTRUCTION DIGITAL IMAGES
1.24 FINAL ELEVATION PHOTOGRAPHS
1.25 HISTORIC PRESERVATION
1.26 PROJECT HEALTH AND SAFETY PLAN
ii
This page intentionally blank
GENERAL REQUIREMENTS
01 00 02 - 1
SECTION 01 00 02
GENERAL REQUIREMENTS (MINOR NCA PROJECTS)
1.1 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor, materials, equipment and services and perform and complete all work for Fort Richardson National Cemetery Gravesite Expansion as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the
Cemetery Director. VA COR should inform bidders if a pre-bid is scheduled.
C. All Testing Laboratory services will be retained and paid for by the
Contractor (see Spec Section 01 45 29, Testing Laboratory Services).
However, the Department of Veterans Affairs may elect to retain its own
Testing Laboratory for any purpose. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.
D. Not Used
E. All employees of general contractor and subcontractors shall comply with security requirements as established by the RE, be identified by name and employer. They shall be restricted from unauthorized access.
F. Prior to commencing work, general contractor shall provide proof that a
OSHA certified “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.
G. Training:
1. All employees of general contractor or subcontractors shall, at the minimum, have successfully completed the 10-hour OSHA certified
Construction Safety course and/or other relevant competency training, as determined by VA CP.
2. Submit OSHA training records of all employees for approval before the start of work.
01 00 02 - 2
1.2 STATEMENT OF BID ITEM(S)
A. CLIN 0001, GENERAL CONSTRUCTION: Installation of all work shown on the plans and described in the specifications included but not limited to:
Project Description:
Construction includes installation of Pre-Placed Crypts; In-Ground
Cremains with and without vaults; irrigation and landscaping. New roadways, stormwater management systems and relevant grading are proposed. Installation of gravesite section markers and grid monuments will be installed in the proposed burial sections. Prior to construction beginning the installation of erosion control measures and construction fencing will be installed.
B. CLIN 0002, Manufacture and delivery of crypts. Installation of crypts to be included in CLIN 0001.
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. AFTER AWARD OF CONTRACT, one electronic set of specifications and drawings will be furnished.
1.4 CONSTRUCTION SECURITY REQUIREMENTS
A. ENTRY REQUIREMENTS: Contractors working at Joint Base Elmendorf-
Richardson (JBER), including subcontractors, shall ensure all employees are in compliance with the DBIB Program. Contractors must comply with the Immigration and Naturalization Act (INA), U.S. Code:
Title 8, Section 1324a, and its prohibition against employing illegal aliens.
B. Personnel with any of the following disqualifying criteria will be denied entry onto JBER:
1. Inability to verify U.S. citizenship, immigration status, or
Social Security Account Number;
2. Evidence of past or present barment from entry/access to any federal/military installation or facility;
3. Outstanding warrant by federal or civil law enforcement authorities, regardless of offense/violation;
4. Incarceration for 12-months or longer within the past 10-years, regardless of offense/violation, unless released on proof of innocence;
5. Any conviction for espionage, sabotage, treason, terrorism or murder;
6. Individual's name appears on any federal agency's "watch list" or
"hit list" for criminal behavior or terrorist activity;
01 00 02 - 3
7. Individual is unable to obtain a favorable National Agency Check
(NAC);
8. Registration as a sex offender;
9. Conviction of firearms or explosives violation within the past
10-years;
10. Conviction within the last 10-years of sexual assault, armed assault/robbery, rape, child molestation, drug possession with intent to sell, drug distribution, or trafficking of humans.
C. JBER CONTRACTOR VETTING PROGRAM (CVP): Contractor/contractor employees and subcontractor/subcontractor employees performing work under a government contract on JBER shall have been the subject of a favorable contractor vetting check prior to issuance of a contractor pass or badge. The background check will consist of a favorable review of the contract authorization letter, Contractor Access Badge
Affidavit, Homeland Security Form I-9, Employment Eligibility
Verification, National Crime Information Center Wants/Warrants
Check, identity proofing, driver license/vehicle registration check, Security Forces Management Information System (SFMIS) check and other records as appropriate.
1. Exceptions: Unclassified contractor employees that have a favorable government personnel security background investigation verifiable within the Joint Personnel Adjudication System (JPAS).
2. Classified Contracts: Personnel working under a classified contract that require a clearance shall be pre-announced by a
JPAS visit request. Personnel will be issued an AF Form 75 pending issue of a Common Access Card (CAC).
D. PROCEDURES REQUIRED PRIOR TO ISSUANCE OF CONTRACTOR PASS OR BADGE:
The following shall be presented by each contract employee to the
JBER Field Visitor Control Center, on or prior to the first day of work:
1. Contract Authorization Letter-signed by the contracting officer, and/or verified through the JBER Contractor Database;
2. Contractor Access Affidavit;
3. Homeland Security Form I-9, "Employment Eligibility
Verification;"
4. Two forms of Identification-at least one must have a color photograph;
01 00 02 - 4
5. Driver license, proof of insurance and vehicle registration- if driving a vehicle.
NOTE: Provision of official photo identification, Social Security
Number (SSN) and Date of Birth (DOB) are necessary to identify the person and records. Information on these forms is collected in accordance with, federal law permitting the installation commander to limit access to the installation for security reasons (50 U.S.C.
Section 797 and DOD Directive 5200.8). Base security forces personnel will review the paperwork for completeness. If errors or omissions are identified, security forces personnel will return the paperwork to the employee for correction. If disqualifying information is identified during the initial screening or vetting process, security forces will contact the contracting officer and advise him of the intent to issue a
Denial of Contractor Pass Letter. The contracting office will notify the contractor's organization. Please refer to Appendix I Contractors &
Vendors Guide to Base Security Operations for additional information and necessary forms.
E. CONTRACTOR PASS/BADGE PROCEDURES: Prior to pass or badge issue, contractors/vendors will be photographed. All personnel will be processed individually. No "group" passes will be issued.
1. Base Entry/Contracts for 1-3 Days or Less: After favorable completion of the contractor vetting process, contract employees will be issued a generated Visitor Pass. The Visitor Pass will be valid for the duration of the access required not to exceed 3-days.
2. Base Entry/Contracts for 4-Days or More; Not to Exceed 1-Year:
After favorable completion of the contractor vetting process, contract employees will be issued a JBER Contractor Badge valid for the duration of the contract; not to exceed one year.
3. Base Entry/Contracts Requiring CAC Card: The decision to issue a
CAC card to contractors is the responsibility of the Contracting
Office, using guidance and criteria in Homeland Security Policy
Directive 12, and contract security clauses.
F. CHANGE IN CONTRACTOR PERSONAL STATUS: Under the authority of 50
U.S.C. Section 797 and DOD 5200.8, the installation commander has imposed a continuing obligation for any individual to disclose to
JBER Security, within 24-hours, if convicted or found not guilty by
01 00 02 - 5 reason of insanity of any of the forms listed criminal offenses that occurs while possessing unescorted access authority within JBER.
G. REGISTRATION OF PRIVATELY OWNED VEHICLES: All vehicles owned, leased, or operated on military installations shall possess State vehicle registration and current vehicle tags. Evidence of required insurance must be present in the vehicle at all times.
H. All vehicles and personnel are subject to inspection while on JBER.
I. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. Assure that all sub-contractors working on the project and their employees also comply with these regulations. Dismissal of violators may be directed by the COR.
J. Security Procedures:
1. Contractor’s employees shall not enter the project site without an appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. For working outside the “regular hours” as defined in the contract, give 3 days' notice to the COR so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the COR.
4. VA reserves the right to close down or shut down the project site and order Contractor’s employees off the premises in the event of a national emergency. Return to the site only with the written approval of the COR.
K. Guards:
1. Provide unarmed guards at the project site if deemed necessary because of vandalism or theft within the contract work areas.
2. The guard shall have communication devices to report events as directed by Local Police Department.
4. Secure the project site, work in progress, materials, tools, equipment and any other materials within the project site that are not under operational control of the Cemetery staff. The use of guards is a Contractor responsibility, if deemed necessary
01 00 02 - 6 because of ongoing theft and/or vandalism within the project work area. Coordinate the use of guards with the RE following input from the Cemetery Operations through the RE. Any guards provided shall be able to communicate with the local police.
L. Key Control:
1. Provide duplicate keys and lock combinations to the COR for the purpose of security inspections of every area of project including tool boxes and parked machines and to take any emergency action(s).
2. Coordinate the lock cylinder and key system work with cemetery staff and provide the devices required to comply with the facility security system.
M. Document Control:
1. Before starting any work, submit an electronic security memorandum, from the Contractor and each Subcontractor describing the actions to be performed to achieve the goals of maintaining confidentiality of “sensitive information”.
2. Perform safekeeping procedures for all drawings, project manual and other project information. This information from these shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive
Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project.
Return the information to the COR upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of the COR.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify COR immediately when there is a loss or compromise of
“sensitive information”.
7. All electronic information shall be stored in a specified location following VA standards and procedures using an
Engineering Document Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
01 00 02 - 7
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
1.5 FIRE SAFETY
A. Applicable Publications: Publications listed below form part of this
Article to the extent referenced. Publications are referenced in text by basic designations only.
1. American Society for Testing and Materials (ASTM):
E84-2009a Surface Burning Characteristics of Building
Materials
2. National Fire Protection Association (NFPA):
10-2010 Standard for Portable Fire Extinguishers
30-2008 Flammable and Combustible Liquids Code
51B-2009 Standard for Fire Prevention During Welding, Cutting and Other Hot Work
70-2008 National Electrical Code
241-2009 Standard for Safeguarding Construction, Alteration, and Demolition Operations
3. Occupational Safety and Health Administration (OSHA):
29 CFR 1926 Safety and Health Regulations for Construction
B. Fire Safety Plan: Establish and maintain a fire protection program in accordance with 29 CFR 1926. Prior to start of work, prepare a plan detailing project-specific fire safety measures, including periodic status reports, and submit to COR/Cemetery Director for review for compliance with contract requirements in accordance with Section 01 33
23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES. Prior to any worker for the contractor or subcontractor’s beginning work, they shall undergo a safety briefing provided by the General Contractor’s competent person per OSHA requirements. This briefing shall include information on the construction limits, safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of NCA equipment, etc.
Documentation shall be provided to the COR that individuals have undergone the Contractor’s safety briefing.
C. Site and Building Access: Maintain free and unobstructed access to emergency services and for fire, police and other emergency response forces in accordance with NFPA 241.
D. Separate temporary facilities, such as trailers, storage sheds, and dumpsters, from existing buildings and new construction by distances in
01 00 02 - 8 accordance with NFPA 241. For small facilities with less than 6 m (20 feet) exposing overall length, separate by 3m (10 feet).
E. Temporary Heating and Electrical: Install, use and maintain installations in accordance with 29 CFR 1926, NFPA 241 and NFPA 70.
F. Flammable and Combustible Liquids: Store, dispense and use liquids in accordance with 29 CFR 1926, NFPA 241 and NFPA 30.
G. Hot Work: Perform and safeguard hot work operations in accordance with
NFPA 241 and NFPA 51B. Coordinate with COR.
H. Fire Hazard Prevention and Safety Inspections: Inspect entire construction areas weekly. Coordinate with, and report findings and corrective actions weekly to COR.
I. Smoking: Smoking is prohibited in and adjacent to construction areas inside existing buildings and additions under construction. In separate and detached buildings under construction, smoking is prohibited except in designated smoking rest areas.
J. Dispose of waste and debris in accordance with NFPA 241. Remove from site weekly.
K. Perform other construction, alteration and demolition operations in accordance with 29 CFR 1926.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the COR. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage trailers, office trailers) and utilities may be erected by the Contractor only with the approval of the COR and shall be built with labor and materials furnished by the
Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work.
C. The Contractor shall, under regulations prescribed by the COR, use only established roadways, or use temporary roadways constructed by the
Contractor when and as authorized by the COR. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the
01 00 02 - 9
Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as shown on the drawings. Contractor parking will be only in areas and on roadways designated and agreed to by the COR in agreement of the
Cemetery.
E. Workmen are subject to rules of the Cemetery applicable to their conduct.
F. Execute work so as to interfere as little as possible with normal functioning of Cemetery as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by the Cemetery in quantities sufficient for not more than two work days. Provide unobstructed access to the Cemetery areas required to remain in operation.
3. Where access by Cemetery personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements. All such actions shall be coordinated with the Utility Company per section J.
G. Construction Fence: Before construction operations begin, the
Contractor shall provide a chain link construction fence, 1.85m (six
(6) feet) minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. The temporary fencing shall encompass the construction work area(s) to serve as a pedestrian barrier to alert cemetery patrons of the construction site. Remove the fence when directed by COR.
H. Utilities Services: Maintain existing utility services for the Cemetery at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems
01 00 02 - 10 and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the Utility Company involved.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without the COR, and Cemetery Director’s prior knowledge and written approval.
2. The Contractor shall submit a request to interrupt any such services to both COR and the Cemetery Director in writing, 48 hours in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. The Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of the Cemetery. Interruption time approved by the Cemetery and COR may occur at other than
Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
I. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
01 00 02 - 11
J. To minimize interference of construction activities with flow of
Cemetery traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
K. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
L. Coordination of Construction with Cemetery Director: The burial activities at a National Cemetery shall take precedence over construction activities. The Contractor must cooperate and coordinate with the Cemetery Director, through the COR, in arranging construction schedule to cause the least possible interference with Cemetery activities in actual burial areas. Construction noise during the committal services shall not disturb the service. Trucks and workmen shall not pass through the service area during this period.
1. The Contractor is required to discontinue his work sufficiently in advance of Easter Sunday, Mother's Day, Father's Day, Memorial Day, Veteran's Day and/or Federal holidays, to permit him to clean up all areas of operation adjacent to existing burial plots before these dates.
2. Cleaning up shall include the removal of all equipment, tools, materials and debris and leaving the areas in a clean, neat condition.
1.7 ENVIRONMENTAL CONTROLS
A. In general, following preventive measures shall be adopted during construction to keep down dust.
1. Dampen debris to keep down dust and provide temporary construction partitions in existing structures where directed by COR. Block off ducts and diffusers to prevent circulation of dust into occupied areas during construction.
B. Final Cleanup:
01 00 02 - 12
1. Upon completion of the project, or as work progresses, remove all construction debris from site, roadways, and walkways that have been part of the construction.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from the Cemetery.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the COR.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the COR may have the necessary work performed and charge the cost to the
Contractor. (FAR 52.236-9)
01 00 02 - 13
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Restoration", and "Operations and
Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. Alaska Pollutant Discharge Elimination
System (APDES)permit is required for this project. The Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate NCA
Central/Cemetery) office. The contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the Contractor's method of operations and operations planning and the Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:
1. Designating areas for equipment maintenance and repair;
2. Providing waste receptacles at convenient locations and provide regular collection of wastes;
3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;
4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and
5. Providing adequately maintained sanitary facilities.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any water/irrigation work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
01 00 02 - 14
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, landscape stone, lawns, paving, roads, walks, etc.)
disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At the Contractor's own expense, the Contractor shall immediately restore to service and repair any damage caused by the Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services; irrigation system control and power which are indicated on drawings and which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.11 PHYSICAL DATA
A. Data and information furnished or referred to below is for the
Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
B. A copy of the geotechnical investigation is an Appendix to these specifications and shall be considered part of the contract documents.
C. The Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine the site of work and logs of borings and, after investigation, decide for themselves the character of materials and make their bids accordingly. Upon proper application to the Department of Veterans Affairs, including approved scheduling bidders will be permitted to make subsurface explorations of their own at site.
1.12 PROFESSIONAL SURVEYING SERVICES
A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections.
The Contractor shall certify that the land surveyor or civil engineer
01 00 02 - 15 is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
1.13 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks indicated on the drawings and shall be responsible for all measurements in connection with the layout. The
Contractor shall furnish, at the Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the COR. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the COR until authorized to remove them. If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the COR may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
B. Establish and plainly mark center lines for each gravesite control monument, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, roads, parking lots, gravesite control monuments, are in accordance with lines and elevations shown on contract drawings.
C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. The
Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:
1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.
D. During progress of work, the Contractor shall have lines, grades, locations and plumbness of all major form work checked and certified by
01 00 02 - 16 a registered land surveyor or registered civil engineer as meeting requirements of contract drawings. Furnish such certification to the
COR before any major items of concrete work are placed. In addition, furnish to the COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.
1. Lines and elevations of sewers and of all outside distribution systems.
2. Lines of grave plot documentation.
3. Lines of elevations of all swales and interment areas.
4. Lines and elevations of roads, streets and parking lots.
5. Lines and elevations and location of top of pre-placed crypts within their respective plots.
6. Lines and elevations of grade over pre-placed crypts.
7. Northing/Easting coordinate locations and elevation depth below finished grade of all water, storm, and irrigation structures, directional fittings, control wire and lines.
8. Northing/Easting coordinate locations and elevation for each gravesite grid monument.
E. Upon completion of the work, the Contractor shall furnish the COR with reproducible drawings, in AutoCAD form, at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.
F. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of
Article "Professional Surveying Services".
1.14 AS-BUILT DRAWINGS
A. The Contractor shall maintain two full size sets of as-built drawings which will be kept current (red lined) during construction of the project, which will include all contract changes, modifications and clarifications.
1. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the RE/COR's review, as often as requested.
B. At substantial completion, the Contractor shall secure the services of a professional land surveyor, as defined in Section 1.10, to perform a site survey within the project limits in accordance with the NCA Site, 01 00 02 - 17
Topographic, Utility, Landscape & Soil Survey scope of services, as listed in the appendix of this specification. Elements to be surveyed include, but are not limited to:
1. Location, alignment, and dimension of roads, curbs, walks, parking, and paved areas. Indicate road centerlines with true bearings and lengths by 15 m (50') stationing. Describe curves by designating the points of curvature and tangency by station. Include all curve data as well as location of radius and vertex points. Designate roads with curbs by double lines. Show equalities for intersecting roads by station.
2. Crown, grade, and climb of curb at road crossings contours.
3. Elevations on 50' centers on centerline of roads, edges of roads, and top and bottom of curbs.
4. Type of pavement of roads.
5. Surface elevations on a 50' grid pattern, except where terrain features require greater detail. At abrupt changes in grade, show elevations at the tops and bottoms of slopes to the nearest 0.1'.
6. Site features of every character identified and located with exact measurements. Include fences, walls, areaways, steps, ramps, railings, gratings, flumes, pads, sprinkler heads, telephone poles, signage, and site furnishings.
7. All underground, overhead, and surface electrical utilities and structures. Show size, depth, and top elevation of all electrical structures, based on actual site investigation.
8. All underground and surface civil and mechanical utilities and structures. Show size depth, invert and top elevation of all utility structures, such as manholes, catch basins and headwalls, based on actual site investigation. Indicate direction of flow and size of pipe for all sewers drains and connecting lines between manholes.
9. Grid monuments.
C. The Contractor shall deliver two (as mentioned in A) approved completed sets of as-built drawings to the COR within 15 calendar days after acceptance of the project by the COR.
D. Section 1.13 shall also apply to all shop drawings.
1.15 USE OF ROADWAYS
01 00 02 - 18
A. For hauling, use only established public roads and designated permanent roads on Cemetery property when indicated or authorized by the COR.
Temporary roads shall be constructed or modified by the Contractor at the Contractor's expense following approved plans that include:
construction, operation, maintenance and restoration. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
B. When new permanent roads are to be a part of this contract, the
Contractor may construct them immediately to facilitate building operations. These roads may be used by all who have business thereon within zone of building operations.
C. When certain buildings (or parts of certain buildings) are required to be completed in advance of general date of completion, all roads leading thereto must be completed and available for use at the time set for completion of such buildings or parts thereof.
1.16 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water connections, or when approved by COR provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
1.17 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner satisfactory to the COR, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the
Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.
01 00 02 - 19
C. The Contractor shall install meters at the Contractor's expense and furnish the Cemetery a monthly record of the Contractor's usage of electricity as hereinafter specified.
D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:
E. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Cemetery electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Where not available or not convenient to connect to the Cemetery distribution system, the contractor shall supply power via portable generators at own expense. Generators shall be acoustically screened so as not to disturb committal services and/or visitation to the adjacent columbarium.
F. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Cemetery irrigation distribution system. Water is available at no cost to the Contractor.
2. If potable water is required and convenient connection is available the contractor may connect to the Cemetery potable water distribution system. The contractor shall install reduced pressure backflow preventer at each connection at own expense.
3. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR's discretion) of use of water from the Cemetery's system.
4. Where not available or not convenient to connect to the Cemetery distribution system, the Contractor shall supply water via portable/temporary means at his own expense.
G. Fuel: Natural and LP gas required for burner cleaning, normal initial burner-burner setup and adjusting, and for performing the specified burner tests will be furnished by the Government. Fuel required for prolonged burner setup, adjustments, or modifications due to improper
01 00 02 - 20 design or operation of burner, or control devices shall be furnished by the Contractor at Contractor's expense.
1.18 TESTS
A. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.
B. Conduct final tests required in various sections of specifications in presence of an authorized representative of the COR. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
C. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire complex which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply;
air is only one part of entire system which provides comfort conditions for a building. Other related components are return air, exhaust air, hot water, controls and electricity, etc. Another example of a complex which involves several components of different disciplines is a burner installation. Efficient and acceptable burner operation depends upon the coordination and proper operation of fuel, combustion air, controls, and other related components.
D. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably short period of time during which operating and environmental conditions remain reasonably constant.
E. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.
1.19 INSTRUCTIONS
A. The Contractor shall furnish Maintenance and Operating manuals and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
B. Manuals: Maintenance and operating manuals (four copies each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for
01 00 02 - 21 starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
C. Instructions: the Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed instructions to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system; shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed.
This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COR, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.
1.20 GOVERNMENT-FURNISHED PROPERTY
A. The Government shall deliver to the Contractor, Government-furnished property shown on drawings including IGC plastic drums.
B. Materials furnished by the Government to be installed by the Contractor will be furnished to the Contractor at the Cemetery.
01 00 02 - 22
C. Storage space for materials will be provided by the Contractor and the
Contractor shall be prepared to unload and store such equipment therein upon its receipt at the Cemetery.
D. Notify COR in writing, 60 days in advance, of date on which Contractor will be prepared to receive materials furnished by Government.
Arrangements will then be made by the Government for delivery of materials.
1. Immediately upon delivery of materials, the Contractor shall arrange for a joint inspection thereof with a representative of the
Government. At such time the Contractor shall acknowledge receipt of materials described, make notations, and immediately furnish the
Government representative with a written statement as to its condition or shortages.
2. The Contractor thereafter is responsible for such material until such time as acceptance of contract work is made by the Government.
E. Equipment furnished by the Government will be delivered in a partially assembled (knock down) condition…