36C78619B0014-007.pdf
PDF 7 MB Posted
- Attached to
- Grave Expansion- Roseburg Nat'l Cemetery
- Solicitation number
- 36C78619B0014
About this file
36C78619B0014 Roseburg 902-008 Bid Specs.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C78619C0142-000.docx | DOCX document | |
| 36C78619B0014-0003000.docx | DOCX document | |
| 36C78619B0014-0002001.pdf | ||
| 36C78619B0014-0002000.docx | DOCX document | |
| 36C78619B0014-0001000.docx | DOCX document | |
| 36C78619B0014-0001003.pdf | ||
| 36C78619B0014-0001001.pdf | ||
| 36C78619B0014-0001002.pdf | ||
| 36C78619B0014-0001005.partial | — | |
| 36C78619B0014-0001004.pdf | ||
| 36C78619B0014-010.pdf | ||
| 36C78619B0014-009.xlsx | XLSX spreadsheet | |
| 36C78619B0014-006.docx | DOCX document | |
| 36C78619B0014-008.docx | DOCX document | |
| 36C78619B0014-001.docx | DOCX document | |
| 36C78619B0014-000.docx | DOCX document | |
| 36C78619B0014-000.docx | DOCX document |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Roseburg National Cemetery Project No. 902CM3008
Gravesite Expansion BID DOCUMENTS May 9 ,2019
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets
DIVISION 01 - GENERAL REQUIREMENTS
01 00 02 General Requirements (Minor NCA Projects)
01 32 17 Network Analysis Schedules (Microsoft Project Gantt
Chart)
01 33 23 Shop Drawings, Product Data, and Samples
01 42 19 Reference Standards
01 43 39 Mockup Requirements
01 45 29 Testing Laboratory Services
01 57 19 Temporary Environmental Controls
01 74 19 Construction Waste Management
DIVISION 02 – EXISTING CONDITIONS
02 41 10 Demolition and Site Clearing
DIVISION 03 – CONCRETE
03 30 53 (Short-Form) Cast-in-Place Concrete
03 48 24 Precast Concrete Columbarium Units
DIVISION 04 – MASONRY
04 05 13 Masonry Mortaring
04 20 00 Unit Masonry
04 43 00 Natural Stone Veneer
04 73 00 Columbarium Niche Covers
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 60 00 Flashing and Sheet Metal
07 92 00 Joint Sealants
DIVISION 09 – FINISHES
09 06 00 Schedule for Finishes
DIVISION 10 – SPECIALTIES
10 14 00 Exterior Signage
DIVISION 31 – EARTHWORK
00 01 10-2
31 20 11 Earth Moving (Short Form)
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements
32 14 13 Concrete Unit Paving
32 33 00 Site Furnishings
32 84 00 Planting Irrigation
32 90 00 Planting
DIVISION 33 – UTILITIES
33 40 00 Storm Sewer Utilities
Appendix
AGEGC Geotechnical Report, September 15,2018
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
SHEET SHEET TITLE
GENERAL
G-001 COVER
G-002 SHEET INDEX
TOPOGRAPHIC SURVEY
V-101 EXISTING CONDITIONS SURVEY
V-102 EXISTING CONDITIONS SURVEY
V-103 EXISTING CONDITIONS SURVEY
GEOTECHNICAL TEST PITS
B-101 GEOTECHNICAL TEST PITS
DEMOLITION
D-101 DEMOLITION OVERALL
D-102 DEMOLITION ENLARGEMENT 1
D-103 DEMOLITION ENLARGEMENT 2
D-104 DEMOLITION ENLARGEMENT 3
D-105 DEMOLITION ENLARGEMENT 4
OPERATIONS ACCESS & LOGISTICS
O-101 CONSTRUCTION ACCESS & PHASING
O-102 COLUMBARIUM PHASING
SITE PLAN
C-101 SITE PLAN OVERALL
C-102 COLUMBARIUM SITE PLAN & DIMENSIONING PLAN
C-103 COLUMBARIUM NUMBERING PLAN
C-104 GRAVESITE LAYOUT PLAN - SECTION 7
C-105 GRAVESITE NUMBERING PLAN - SECTION 7
C-106 CONSTRUCTION ENTRANCE PLAN
C-201 EXISTING COLUMBARIUM CAP REPLACEMENT & PAVEMENT REPAIRS
C-501 COLUMBARIUM 5 NICHE HIGH DETAILS 1
C-502 COLUMBARIUM 5 NICHE HIGH DETAILS 2
C-503 COLUMBARIUM 3 NICHE HIGH DETAILS
C-504 COLUMBARIUM 5 & 3 NICHE HIGH DETAILS 1
C-505 COLUMBARIUM 5 & 3 NICHE HIGH DETAILS 2
C-506 EXISTING COLUMBARIUM & MEMORIAL WALL CAP REPLACEMENT DETAILS
C-507 SITE DETAILS
GRADING & UTILITY
CG-101 GRADING OVERALL
CG-102 GRADING ENLARGEMENT 1
CG-103 GRADING ENLARGEMENT 2
CG-104 GRADING ENLARGEMENT 3
CG-105 GRADING ENLARGEMENT 4
CG-106 GRADING ENLARGEMENT 5
CG-107 GRADING ENLARGEMENT 6
CG-108 GRADING ENLARGEMENT 7
00 01 15 - 2
CG-109 GRADING ENLARGEMENT 8
CG-501 GRADING & UTILITY DETAILS
EROSION CONTROL
CE-101 STORMWATER POLLUTION PREVENTION PLAN
CE-102 EROSION CONTROL OVERALL
CE-501 EROSION CONTROL DETAILS
LANDSCAPE
L-101 LANDSCAPE PLAN OVERALL
L-102 COLUMBARIUM LANDSCAPE PLAN
L-103 NE EXISTING COLUMBARIUM LANDSCAPE PLAN
L-104 IGC SECTION 7 LANDSCAPE PLAN
L-105 NE LOOP ROAD
L-106 CONSTRUCTION ACCESS
STRUCTURAL
S-001 TITLE SHEET - STRUCTURAL GENERAL NOTES
S-101 FOUNDATION PLAN
S-501 COLUMBARIA - PLAN, SECTIONS AND DETAILS
IRRIGATION
LI001 IRRIGATION GENERAL NOTES
LI201 IRRIGATION PLAN 1
LI202 IRRIGATION PLAN 2
LI203 IRRIGATION PLAN 3
LI204 IRRIGATION PLAN 4
LI205 IRRIGATION PLAN 5
LI301 IRRIGATION PLAN (REFERENCE ONLY)
LI501 IRRIGATION DETAILS 1
LI502 IRRIGATION DETAILS 2
LI503 IRRIGATION DETAILS 3
- - - END - - -
i
SECTION 01 00 02
GENERAL REQUIREMENTS (MINOR NCA PROJECTS)
TABLE OF CONTENTS
1.1 GENERAL INTENTION
1.2 STATEMENT OF BID ITEM(S)
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.4 CONSTRUCTION SECURITY REQUIREMENTS
1.5 FIRE SAFETY
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 PERMITS
1.9 DISPOSAL AND RETENTION
1.10 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS
1.11 RESTORATION
1.12 PHYSICAL DATA
1.13 PROFESSIONAL SURVEYING SERVICES
1.14 LAYOUT OF WORK
1.15 AS-BUILT DRAWINGS
1.16 USE OF ROADWAYS
1.17 TEMPORARY TOILETS
1.18 AVAILABILITY AND USE OF UTILITY SERVICES
1.19 INSTRUCTIONS
1.20 GOVERNMENT-FURNISHED PROPERTY
1.21 CONSTRUCTION SIGN
1.22 SAFETY SIGN
1.23 CONSTRUCTION DIGITAL IMAGES
1.24 FINAL ELEVATION PHOTOGRAPHS
1.25 HISTORIC PRESERVATION
1.26 PROJECT HEALTH AND SAFETY PLAN
ii
This page intentionally blank
GENERAL REQUIREMENTS
01 00 02 - 1
SECTION 01 00 02
GENERAL REQUIREMENTS (MINOR NCA PROJECTS)
1.1 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor, materials, equipment and services and perform and complete all work for Roseburg National Cemetery Gravesite Expansion as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the
Cemetery Director.
C. Offices of Anderson Engineering of Minnesota, LLC, as
Architect-Engineers (A/E), may render certain technical services during construction. Such services shall be considered as advisory to the
Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Resident
Engineer/Contracting Officers Representative (RE/COR) or his duly authorized representative.
D. All Testing Laboratory services will be retained and paid for by the
Contractor (see Spec Section 01 45 29, Testing Laboratory Services).
However, the Department of Veterans Affairs may elect to retain its own
Testing Laboratory for any purpose. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the RE/COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the RE/COR.
E. All employees of general contractor and subcontractors shall comply with security requirements as established by the RE/COR. They shall be restricted from unauthorized access.
F. Prior to commencing work, general contractor shall provide proof that a
OSHA certified “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.
G. Training:
1. All employees of general contractor or subcontractors shall, at the minimum, have successfully completed the 10-hourOSHA certified
01 00 02 - 2
Construction Safety course and/or other relevant competency training, as determined by VA CP.
2. Submit OSHA training records of all employees for approval before the start of work.
1.2 STATEMENT OF BID ITEM(S)
A. ITEM I, GRAVESITE EXPANSION: Installation of all work shown on the plans and described in the specifications including but not limited to:
PROJECT DESCRIPTION
Construct Columbarium, Grave Sections, Columbaria Cap Replacement, Drainage Improvements, and e Irrigation system expansion/alteration along with associated, walkways, utilities, restoration, planting, and other improvements as depicted in Plans and Specifications.
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. AFTER AWARD OF CONTRACT, (zero) bond paper set(s) of specifications and drawings will be furnished.
B. Additional sets of drawings may be made by the Contractor, at
Contractor's expense, from digital files furnished by the Issuing
Office.
1.4 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the site without following the procedures approved by the RE/COR. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. For working outside the “regular hours” as defined in the contract, The General Contractor shall give 3 days notice to the RE/COTR so that appropriate arrangements can be provided for the Cemetery employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the RE/COTR.
01 00 02 - 3
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the RE/COR.
C. Guards:
1. The General Contractor shall provide unarmed guards at the project site when theft or vandalism warrants.
D. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the RE/COR for the purpose of security inspections of every area of project including tool boxes and parked machines, and to take any necessary emergency action.
1.5 FIRE SAFETY
A. Applicable Publications: Publications listed below form part of this
Article to the extent referenced. Publications are referenced in text by basic designations only.
1. American Society for Testing and Materials (ASTM):
E84-2009a Surface Burning Characteristics of Building
Materials
2. National Fire Protection Association (NFPA):
10-2010 Standard for Portable Fire Extinguishers
30-2008 Flammable and Combustible Liquids Code
51B-2009 Standard for Fire Prevention During Welding, Cutting and Other Hot Work
70-2008 National Electrical Code
241-2009 Standard for Safeguarding Construction, Alteration, and Demolition Operations
3. Occupational Safety and Health Administration (OSHA):
29 CFR 1926 Safety and Health Regulations for Construction
B. Fire Safety Plan: Establish and maintain a fire protection program in accordance with 29 CFR 1926. Prior to start of work, prepare a plan detailing project-specific fire safety measures, including periodic status reports, and submit to RE/COR/Cemetery Director for review for compliance with contract requirements in accordance with Section 01 33
23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES. Prior to any worker for the contractor or subcontractor’s beginning work, they shall undergo a safety briefing provided by the General Contractor’s competent person per OSHA requirements. This briefing shall include information on the
01 00 02 - 4 construction limits, safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of NCA equipment, etc.
Documentation shall be provided to the RE/COR that individuals have undergone the Contractor’s safety briefing.
C. Site and Building Access: Maintain free and unobstructed access to emergency services and for fire, police and other emergency response forces in accordance with NFPA 241.
D. Separate temporary facilities, such as trailers, storage sheds, and dumpsters, from existing buildings and new construction by distances in accordance with NFPA 241. For small facilities with less than 6 m (20 feet) exposing overall length, separate by 3m (10 feet).
F. Temporary Heating and Electrical: Install, use and maintain installations in accordance with 29 CFR 1926, NFPA 241 and NFPA 70.
G. Means of Egress: Do not block exiting for occupied buildings, including paths from exits to roads. Minimize disruptions and coordinate with
RE/COR/Cemetery Director.
H. Egress Routes for Construction Workers: Maintain free and unobstructed egress. Inspect daily. Report findings and corrective actions weekly to
RE/COR.
I. Fire Extinguishers: Provide and maintain extinguishers in construction areas and temporary storage areas in accordance with 29 CFR 1926, NFPA
241 and NFPA 10.
J. Flammable and Combustible Liquids: Store, dispense and use liquids in accordance with 29 CFR 1926, NFPA 241 and NFPA 30.
M. Hot Work: Perform and safeguard hot work operations in accordance with
NFPA 241 and NFPA 51B. Coordinate with RE/COR
N. Fire Hazard Prevention and Safety Inspections: Inspect entire construction areas weekly. Coordinate with, and report findings and corrective actions weekly to RE/COR.
O. Smoking: Smoking is prohibited in and adjacent to construction areas inside existing buildings and additions under construction. In separate and detached buildings under construction, smoking is prohibited except in designated smoking rest areas.
P. Dispose of waste and debris in accordance with NFPA 241. Remove from and site weekly.
Q. Perform other construction, alteration and demolition operations in accordance with 29 CFR 1926.
01 00 02 - 5
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the RE/COR. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage trailers, office trailers) and utilities may be erected by the Contractor only with the approval of the RE/COR and shall be built with labor and materials furnished by the
Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work.
C. The Contractor shall, under regulations prescribed by the RE/COR, use only established roadways, or use temporary roadways constructed by the
Contractor when and as authorized by the RE/COR. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the
Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as shown on the drawings and as determined by the RE/COR with agreement of the Cemetery. Contractor parking will be only in areas and on roadways designated and agreed to by the RE/COR in agreement of the Cemetery.
E. Workmen are subject to rules of the Cemetery applicable to their conduct.
F. Execute work so as to interfere as little as possible with normal functioning of Cemetery as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.
1. Do not store materials and equipment in other than assigned areas.
2. Provide unobstructed access to the Cemetery areas required to remain in operation.
G. Phasing: To insure such executions, the Contractor shall furnish the
RE/COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site or portion thereof. In addition, the Contractor shall notify the RE/COR two weeks
01 00 02 - 6 in advance of the proposed date of starting work in each specific area of site or portion thereof. Arrange such dates to insure accomplishment of this work in successive phases mutually agreeable to the Cemetery
Director, RE/COR and Contractor, as follows:
All Phases of Work can occur concurrently, with certain restrictions as described on plans O-101 and O-102:
1. The Construction Access Roadway shall be constructed prior to beginning work on the Columbarium or IGC grave sections 6 or 7.
2. Work in each Drainage Improvement area shall be completed and restored no later than 4 calendar weeks from start of construction in each area.
3. Each Zone of existing Columbarium cap replacement shall be completed in 14 days from the start of work on that zone.
4. Work within the Irrigation Improvement Area shall be completed in 6 calendar weeks from start of construction in that area. No staging of materials either than irrigation items will be permitted.
I. Construction Fence: Before construction operations begin, the
Contractor shall provide a chain link construction fence, six feet minimum height, around the construction area indicated on the drawings.
Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm
(one inch) above grade. The temporary fencing shall encompass the construction work area(s) to serve as a pedestrian barrier to alert cemetery patrons of the construction site. Remove the fence when directed by RE/COR.
K. Utilities Services: Maintain existing utility services for the Cemetery at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such
01 00 02 - 7 indication, where directed by RE/COR. All such actions shall be coordinated with the Utility Company involved.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of RE/COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without the
RE/COR, and Cemetery Director’s prior knowledge and written approval.
2. The Contractor shall submit a request to interrupt any such services to both RE/COR and the Cemetery Director in writing, 48 hours in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. The Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of the Cemetery. Interruption time approved by the Cemetery and RE/COR may occur at other than
Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the RE/COR.
5. In case of a contract construction emergency, service will be interrupted on approval of RE/COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
01 00 02 - 8
M. To minimize interference of construction activities with flow of
Cemetery traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the RE/COR.
N. Coordinate the work for this contract with other construction operations as directed by RE/COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF
ROADWAYS.
O. Coordination of Construction with Cemetery Director: The burial activities at a National Cemetery shall take precedence over construction activities. The Contractor must cooperate and coordinate with the Cemetery Director, through the RE/COR, in arranging construction schedule to cause the least possible interference with
Cemetery activities in actual burial areas. Construction noise during the committal services shall not disturb the service. Trucks and workmen shall not pass through the service area during this period.
1. The Contractor is required to discontinue his work sufficiently in advance of Easter Sunday, Mother's Day, Father's Day, Memorial Day, Veteran's Day and/or Federal holidays, to permit him to clean up all areas of operation adjacent to existing burial plots before these dates.
2. Cleaning up shall include the removal of all equipment, tools, materials and debris and leaving the areas in a clean, neat condition.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the RE/COR of areas in which alterations occur and areas which are anticipated routes of access, and furnish a signed report, to the Contracting Officer. This report shall list by space:
1. Existing condition and types of other surfaces not required to be altered throughout affected areas.
2. Existence and conditions of items required by drawings to be either reused or relocated, or both.
01 00 02 - 9
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and RE/COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of
RE/COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by the Contractor with new items in accordance with specifications which will be furnished by the Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR
52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR 852.236-88).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and RE/COR together shall make a thorough re-survey of the areas of spaces involved. They shall furnish a report on conditions then existing surfaces as compared with conditions of same as noted in first condition survey report.
1. Re-survey report shall also list any damage caused by the Contractor to such flooring and other surfaces, despite protection measures;
and, will form the basis for determining extent of repair work required of the Contractor to restore damage caused by the
Contractor's workmen in executing work of this contract.
D. Protection: Provide the following protective measures: 1.
1. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protect existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, any surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 PERMITS
A. The following Permits shall be obtained by the Contractor. Fees indicated shall be paid by the contractor on behalf of the VA.
1. NPDES Permit (Oregon 1200-C Construction Storm water Permit) shall be obtained from the Oregon Department of Environmental Quality.
01 00 02 - 10
Anticipated Fee is $2,130 based on project disturbed area. The
Contractor shall apply and coordinate obtaining the LUSC statement from the City of Roseburg as part of this process
1.9 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are noted on drawings or in specifications. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by RE/COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from the Cemetery.
1.10 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the RE/COR.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the RE/COR may have the necessary work performed and charge the cost to the
Contractor.
(FAR 52.236-9)
01 00 02 - 11
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge
Elimination System (NPDES) permit is required for this project. The
Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate NCA
Central/Cemetery) office. The contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the Contractor's method of operations and operations planning and the Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:
1. Designating areas for equipment maintenance and repair;
2. Providing waste receptacles at convenient locations and provide regular collection of wastes;
3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;
4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and
5. Providing adequately maintained sanitary facilities.
1.11 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any, gas, water/irrigation or electric work without approval of the
RE/COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the RE/COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
01 00 02 - 12
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, landscape stone, lawns, paving, roads, walks, etc.)
disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At the Contractor's own expense, the Contractor shall immediately restore to service and repair any damage caused by the Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or irrigation system control and power which are indicated on drawings and which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.12 PHYSICAL DATA
A. Data and information furnished or referred to below is for the
Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
1. The indications of physical conditions on the drawings and in the specifications, are the result of site investigations by Anderson
Engineering combined with as-built information provided by the owner.
B. Subsurface conditions have been developed by test pits. Logs of subsurface exploration conducted by Applied Geotechnical Engineering &
Geological Consulting, Report dated September 15. 2018 are shown diagrammatically on drawings.
C. A copy of the soil geotechnical investigation report is an Appendix to these specifications and shall be considered part of the contract documents.
D. The Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine the site of work and logs of borings and, after
01 00 02 - 13 investigation, decide for themselves the character of materials and make their bids accordingly. Upon proper application to the Department of Veterans Affairs, including approved scheduling bidders will be permitted to make subsurface explorations of their own at site.
1.13 PROFESSIONAL SURVEYING SERVICES
A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections.
The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
1.14 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The
Contractor shall furnish, at the Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the RE/COR. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the RE/COR until authorized to remove them. If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the RE/COR may replace them and deduct the expense of the replacement from any amounts due or to become due to the
Contractor.
(FAR 52.236-17)
B. Establish and plainly mark center lines for each building and/or addition to each existing building, lines for each gravesite control monument, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, roads, parking lots, gravesite control monuments, are in accordance with lines and elevations shown on contract drawings.
C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey
01 00 02 - 14 control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. The
Survey shall include, but not be limited to, location of lines and grades of footings, walls, center lines of columns in both directions, major utilities and elevations of structures and walks:
1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the RE/COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.
D. During progress of work, the Contractor shall have lines, grades, locations and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings. Furnish such certification to the
RE/COR before any major items of concrete work are placed. In addition, furnish to the RE/COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.
1. Lines of each building and/or addition.
2. Elevations of bottoms of footings and tops of stem walls and masonry ledges. Lines and elevations of pedestrian pavements and sidewalks.
3. Lines and elevations of storm drains, drain tiles and of all outside distribution systems.
4. Lines of grave plot documentation elevations in in-ground
5. Lines of elevations of all swales and interment areas.
6. Lines and elevations of roads, streets and parking lots
9. Northing/Easting coordinate locations and elevation of all storm, and irrigation structures, directional fittings, control wire and lines.
10. Northing/Easting coordinate locations and elevation for each gravesite grid monument.
E. Upon completion of the work, the Contractor shall furnish the RE/COR with reproducible drawings, in AutoCAD form, at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.
01 00 02 - 15
F. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of
Article "Professional Surveying Services".
1.15 AS-BUILT DRAWINGS
A. The Contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, which will include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the RE/COR's review, as often as requested.
C. The Contractor shall deliver two approved completed sets of as-built drawings to the RE/COR within 15 calendar days after acceptance of the project by the RE/COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.16 USE OF ROADWAYS
A. For hauling, use only established public roads and designated permanent roads on Cemetery property and, when authorized by the RE/COR.
Contractor constructed temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed by the Contractor at the Contractor's expense at locations coordinated with the RE/COR. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.17 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water connections, or when approved by RE/COR provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
Temporary Toilets shall be placed in unobtrusive locations away from existing burial sections.
1.18 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.
01 00 02 - 16
B. The Contractor, at Contractor's expense and in a workmanlike manner satisfactory to the RE/COR, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the
Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.
C. The Contractor shall install meters at the Contractor's expense and furnish the Cemetery a monthly record of the Contractor's usage of electricity as hereinafter specified.
D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:
E. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Cemetery electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Where not available or not convenient to connect to the Cemetery distribution system, the contractor shall supply power via portable generators at own expense. Generators shall be acoustically screened so as not to disturb committal services and/or visitation to the adjacent columbarium.
F. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Cemetery irrigation distribution system. Backflow preventer may not be required at connections to the irrigation system. Water is available at no cost to the Contractor.
2. If potable water is required and convenient connection is available the contractor may connect to the Cemetery potable water distribution system. The contractor shall install reduced pressure backflow preventer at each connection at own expense.
3. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at RE/COR's discretion) of use of water from the Cemetery's system.
01 00 02 - 17
4. Where not available or not convenient to connect to the Cemetery distribution system, the Contractor shall supply water via
1.19 INSTRUCTIONS
A. The Contractor shall furnish Maintenance and Operating manuals and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
B. Manuals: Maintenance and operating manuals (four copies each) for each separate piece of equipment shall be delivered to the RE/COR coincidental with the delivery of the equipment to the job site.
Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
C. Instructions: the Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed instructions to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system; shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed.
This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the RE/COR and shall be considered concluded only when the RE/COR is
01 00 02 - 18 satisfied in regard to complete and thorough coverage. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the RE/COR, does not demonstrate sufficient qualifications in accordance with requirements for instructors
1.20 GOVERNMENT-FURNISHED PROPERTY
A. The Government shall deliver to the Contractor, the
Government-furnished property shown on drawings.
B. Materials furnished by the Government to be installed by the Contractor
C. Storage space for materials will be provided by the Contractor and the
Contractor shall be prepared to unload and store such equipment therein upon its receipt at the Cemetery.
D. Notify RE/COR in writing, 120 days in advance, of date on which
Contractor will be prepared to receive materials furnished by
Government. Arrangements will then be made by the Government for delivery of materials.
1. Immediately upon delivery of materials, the Contractor shall arrange for a joint inspection thereof with a representative of the
Government. At such time the Contractor shall acknowledge receipt of materials described, make notations, and immediately furnish the
Government representative with a written statement as to its condition or shortages.
2. The Contractor thereafter is responsible for such material until such time as acceptance of contract work is made by the Government.
E. Completely assemble and install the Government furnished equipment in place ready for proper operation in accordance with specifications and drawings.
1.21 CONSTRUCTION SIGN
A. Provide a Construction Sign where directed by the RE/COR. All wood members shall be of framing lumber. Cover sign frame with 0.7 mm (24 gage) galvanized sheet steel nailed securely around edges and on all bearings. Signface shall be 4 feet x 5 feet and 6 inches. Provide two 100 by 100 mm (4 inch by 4 inch) posts (or equivalent round posts) set 900 mm (three feet) into ground. Set bottom of sign level at 900 mm (three feet) above ground and secure to posts with through bolts.
Make posts full height of sign. Brace posts with 50mm x 100 mm (two by four inch) material as directed.
01 00 02 - 19
B. Paint all surfaces of sign and posts two coats of white semi-gloss paint. Border and letters shall be of black gloss paint, except project title which shall be blue gloss paint.
C. Maintain sign and remove it when directed by the RE/COR.
D. Detail Drawing of construction sign and location are shown on plan.
1.22 SAFETY SIGN
A. Provide a Safety Sign where directed by RE/COR. Signboard shall be shall be three feet x four feet, 19 mm (3/4-inch) thick exterior grade plywood. Provide two 100 mm by 100 mm (four by four inch) posts extending full height of sign and 900 mm (three feet) into ground. Set bottom of sign level at 1200 mm (four feet) above ground.
B. Paint all surfaces of Safety Sign and posts with one prime coat and two coats of white gloss paint. Letters and design shall be painted with gloss paint of colors noted.
C. Maintain sign and remove it when directed by RE/COR.
D. Detail Drawing of safety sign showing required legend and other characteristics of sign is shown on plan.
E. Post the number of accident free days on a daily basis.
1.23 CONSTRUCTION DIGITAL IMAGES
A. During construction period through completion, furnish Department of
Veterans Affairs weekly color digital photographs of construction progress (8 to 10 images per week.) Photographs of the reinforcing steel shall be taken after all reinforcing steel, sleeves, inserts, etc. are in place but prior to setting of runways. Photographs must show distinctly, at as large a scale as possible, all parts of work embraced in picture.
B. Photographs are to be taken with a high-resolution digital camera, minimum 6 megapixels, with good wide-angle capability. The images shall be recorded in JPEG format with a minimum of 24-bit color and no reduction in actual picture size.
1. Compressed size of the file shall be no less than 80% or the original with no loss of information.
2. File names shall contain the Project number, the date the image was taken, and a unique sequential identifier, for example:
101CM3202_10-01-2013_0001. Use underscore, not spaces in digital file names.
01 00 02 - 20
C. The digital photo files shall become property of Government and will be both e-mailed and submitted on CD-ROM.
1. The images shall be forwarded electronically to the COR/Project
Manager via email to NAME@va.gov within 2 days of when the photo was taken. Identify the content of each picture by a caption incorporated in the photo.
2. The digital photo files shall also be submitted on CD-ROM to the
COR/Project Manager at the conclusion of the project. The CD-ROM shall also contain an index of all the images contained therein in either a TXT or Microsoft Word format.
D. Aerial Photographs: Submit aerial photographs at one-month intervals during the entire construction period. The first aerial photo shall be taken just prior to the start of construction and then at one-month intervals. The final aerial photograph shall be taken at full project completion during a growing season when lawns are green and not dormant and as directed by the RE/COR.
1.24 FINAL ELEVATION PHOTOGRAPHS
A. Final photographs shall be taken by a commercial/professional photographer. They shall be taken upon completion, including landscaping. They shall be taken on a clear sunny day at as large a scale as possible to obtain sufficient detail to show depth and to provide clear, sharp pictures. All images shall become property of the Government.
B. Photographs shall be artistically composed showing full front elevations of new columbarium court(s), grave sections and surrounding landscapes. A minimum of thirty six (36) images shall be taken as per these specifications.
C. Minimum digital photo file size for final photos is 20 mb un-interpolated, preferably 52 mb. Submit proofs, via e-mail or web photo gallery, from which the COR/Project Manager will select the final images for printing.
D. Pictures selected by the COR/Project Manager for printing shall be printed on regular weight paper, matte finish archival grade photographic paper and produced by a RA4 process from the digital image with a minimum 300 PPI. Photographs shall have full picture print with no margin.
01 00 02 - 21
E. Submit two (2) 400 mm x 500 mm (16 x 20) framed prints and three (3)
8 x 10 prints of the final selected photos. Deliver to the
COR/Project Manager, in boxes suitable for shipping, F. Submit a CD-ROM to the COR/Project Manager containing all (minimum
36) final digital photo files.
1. Images on CD-ROM shall be recorded in JPEG format with a minimum of 24 bit color and no reduction in actual picture size.
Compressed size of the file shall be no less than 80% of the original with no loss of information.
2. File names shall contain the date the image was taken, the
Project number and a unique sequential identifier.
3. The CD-ROM shall also contain an index of all the images contained therein in either a TXT or Microsoft Word format.
G. Each of the selected 16 x 20 prints shall be placed in a frame with a minimum 2 inches, maximum 3 inches, of appropriate matting as a border. Provide a selection of 3 different mats and 3 different frames from which the COR will select one mat and one frame style to frame both prints. Preferred frame style is wood molding, matte black finish, box frame, 1-1/8" wide x 7/8-inch deep.
H. Place a…