LIST OF PROJECT SUBMITTALS

Culpeper National Cemetery – 2018 M&R Projects

Project No. 839-MR18-05

SUBMITTAL REQUIREMENTS ("X")

Spec. Sec.

Par. No.

Description

C E

R T

./L A

B

TE

ST

R E

PO

R

T/ C

A L

C

O R

P L

A N

SA

M

PL

E

SH

O

P D

R A

W

IN

G fg

. D A

T A

O

O T

H

M M

E N

T S

01 00 02 1.2.C. Luminaire designs – Lighting Manufacturer X Prior to Work

01 00 02 1.7.E. Request to Interrupt Utility Service X 7 Days Prior

01 33 23 1.2 Certificate of Insurance X Pre-Construction

01 33 23 1.2 Schedule of Values X Pre-Construction

01 33 23 1.2 / 1.3 Submittal Register X Pre-Construction

01 33 23 1.2 List of Proposed Sub-Contractors X Pre-Construction

01 33 23 1.2 K. Record Drawings / As-Built Drawings X Closeout

01 33 23 1.4. Submittal Schedule X Pre-Construction

01 33 23 1.5.E. Submittal Transmittal Letter X Each Submittal

01 33 23 1.8. Submittal of O&M Data X Each Spec. Section

01 35 26 1.4 Accident Prevention Plan (APP) X Pre-Construction

01 35 26 1.8.E. OSHA Training Certificates X Pre-Construction

04 01 00 1.4.B. Manufacturer Literature & Data (All Masonry Products) X Prior to Work

04 01 00 1.4.C. Pointing Mortar Samples X Prior to Work

04 01 00 1.4.D.1. Existing Mortar Testing Results X Prior to Work

04 01 00 1.4.D.2. Mortar Mix Materials & Design X Prior to Work

04 05 13 1.2. Mortar Color Sample X Prior to Work

04 05 13 1.3.B.&1.5.B Testing Facility Qualifications – Mortar Analysis X Prior to Work

04 05 13 2.10.B.2. Mortar Lab Test Report X Prior to Work

07 60 00 1.6.B. Shop Drawings all Flashing & Sheet Metal Items X Prior to Work

07 60 00 1.6.C. Manufacturer Literature & Data (All Products) X Prior to Work

07 60 00 1.6.D. Certificates for Finishing Requirements X Prior to Work

07 92 22 1.3.A. Installer Qualifications – Joint Sealants X Prior to Work

07 92 22 1.4.A. Material & Work Certification – Joint Sealant X Prior to Work

07 92 22 1.5.B. Manufacturer Installation Instruction – Joint Sealant X Prior to Work

07 92 22 1.5.E. / 1.8. Manufacturer Warranty – Joint Sealant X Prior to Work

07 92 22 1.9. SWRI Validation – Joint Sealant X Prior to Work

09 91 00 1.5.B. Manufacturer Literature (All Painting Products) X X Prior to Work

09 91 00 1.5.C. Samples (All Painting Products) X Prior to Work

23 10 10 1.4.D. Leak Detection System Submittals X X X X X X Prior to Work

23 10 10 1.4.E. Tank Fluid Level System Submittals X X X X X X Prior to Work

23 10 10 1.4. F. Tank and Piping Accessories X X X X X X Prior to Work

23 10 10 1.4.G. Fuel Pumps & Meter System X X X X X X Prior to Work

23 10 10 1.4.H./3.7.B. Systems O&M Manual (Include Wiring Diagrams) X X Prior to Payment

23 10 10 1.4.I. System Readiness Checklist X Prior to Start-Up

23 10 10 2.12.A. Warranties – Fuel Pumps, Meters, & Dispensing System X Prior to Start-Up

23 10 10 2.12.G. Nozzle Color Submittal X Prior to Work

23 10 10 2.13.B. Emergency Fuel Shut Off Submittals X X X Prior to Work

23 10 10 3.1.A. System Schematic Layout X Prior to Work

26 05 19 1.4.A.1. Shop Drawing All Products – Electric Power Conductors X Prior to Work

5/15/2018

SUBMITTAL REQUIREMENTS ("X")

Spec. Sec.

Par. No.

Description

R

T ./L

A B

TE

ST

PO

R

T/ C

A L

C

O R

P L

A N

SA

PL

E

SH

O

P D

R A

W

IN

G fg

. D A

T A

O

T

H

M M

E N

T S

26 05 19 1.4.A.2. Contractor & Electrician Certifications X Prior to Payment

26 05 26 1.4.A.1. Shop Drawing All Products – Electric Grounding X Prior to Work

26 05 26 1.4.A.2. Ground Resistance Field Test Report X Prior to Final Insp.

26 05 26 1.4.A.3. Contractor Grounding Certification X Prior to Payment

26 05 33 1.4.A.1. Shop Drawing All Products – Electric Raceways & Boxes X Prior to Work

26 05 33 1.4.A.2. Contractor & Electrician Certifications X Prior to Final Insp.

26 05 33 3.3.A. Concrete Penetration Sketch Prior to Work

26 05 41 1.4.A.1.b. Manhole Plan & Elevation Drawings X Prior to Work

26 05 41 1.4.A.2. Contractor & Electrician Certifications X Prior to Final Insp.

26 56 00 1.3.B. Shop Drawing All Products – Exterior Lighting X Prior to Work

26 56 00 1.3.C. Manufacturer O&M Manual – Exterior Lighting X Prior to Start-Up

26 56 00 1.3.D. Contractor & Electrician Certifications X Prior to Final Insp.

26 56 00 2.3.D. Pole Anchor Base Design Calculations X Prior to Work

26 56 00 2.4.F. Luminaire Design X Prior to Work

31 20 12 1.6.B. Testing Lab Qualifications X Prior to Work

32 01 17 1.5.B. Data & Test Reports (Asphalt Paving Repair) X X X Prior to Work

32 01 17 1.5.C. Material & Methods Certification X Prior to Payment

32 05 23 1.5.B. Submittal Drawings – All Concrete Improv. Include Joints X Prior to Work

32 05 23 1.5.C. Manufacturer Literature & Data (All Products) X Prior to Work

32 05 23 1.5.D. Concrete Panel Samples X Prior to Work

32 05 23 1.5.E. Test Reports – All Products & Materials X Prior to Work

32 05 23 1.5.F. Certification that All Products & Materials X Prior to Work

32 05 23 1.5.H. Concrete Mix Design X Prior to Work

32 05 23 1.5.I. “Select Subbase” Job Mix Design X Prior to Work

32 05 23 1.6.A. Installer Qualification X Prior to Work

32 05 23 1.6.C. Pre-Construction Testing (All Sub-Items) X Prior to Work

32 05 23 1.10. “Warranty of Construction” X At Close-Out

32 05 23 2.1. All Products – Concrete Materials X X X X X Prior to Work

32 05 23 2.2. Select Subbase – All Requirements X X X X X Prior to Work