36C78618R0383-0001002.docx

DOCX document 29 KB Posted

Attached to
(NRM) 910-18-011 | 36C78618C0255 | OFFICE REMODEL FORT RICHARDSON NATIONAL CEMETERY
Solicitation number
36C78618R0383
Issued by

About this file

36C78618R0383 0001 Fort Richardson Office Remodel SOW rev 6-19-18.docx

View the file

Other files

File Type Posted
36C78618C0255-000.docx DOCX document
36C78618R0383-0002001.pdf PDF
36C78618R0383-0002000.docx DOCX document
36C78618R0383-0001001.pdf PDF
36C78618R0383-0001000.docx DOCX document
36C78618R0383-002.docx DOCX document
36C78618R0383-003.pdf PDF
36C78618R0383-004.pdf PDF
36C78618R0383-005.docx DOCX document
36C78618R0383-001.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK/SPECIFICATION

Project Title: Office Remodel

All work shall be performed in accordance the Description/Specifications/Statement of Work, contained in this contract.

SCHEDULE OF SERVICES:

Contract Line Item

Description

Quantity

Unit

Unit Price Total Price

0001
Office Remodel
1
Job
$________

TOTAL PRICE

SCOPE OF WORK

GENERAL SCOPE OF WORK:

The Contractor shall furnish all labor, materials, equipment and supplies necessary to perform the work for the Remodel of the Existing Office in accordance with the solicitation, Statement of Work, required permits, drawings, terms and conditions. The work shall be performed at Fort Richardson National Cemetery, Bldg. 58-512, Davis Hwy, Fort Richardson, AK 99505. The work includes but is not limited to:

1. Remove door between existing Garage and Office space.

2. Construct 2x4 walls as per plans.

3. Reroute existing IT equipment to new IT closet.

4. Provide new electrical outlets, telephone and IT outlets as per plan.

5. Install new baseboard heater in Office.

6. Install new lights in Office, IT Closet and Hall.

7. Install VCT Tile in IT Closet

8. Install New Carpet tiles in Office and Hall.

9. Provide new plywood backboard painted with semi-gloss grey paint and quadplex electrical outlet as per drawing in IT Closet.

10. Remove Exterior plywood behind demarcation point for existing telcom data box. Fill any holes made for attatchment to existing building.

11. A schedule of work shall be coordinated with the Cemetery Director and be strictly adhered to since the space will be occupied during construction.

All work shall be coordinated with the Contracting Officer’s Representative (COR) and/or the Cemetery Director. Work will be conducted in such a manner to minimize the impact on the Cemetery operations.

All work shall be accomplished during normal business hours (8:00 am to 4:30 pm, local time) Monday through Friday, except Federal Holidays.

Only the Contracting Officer (CO) has the authority to make changes to the contract that affects price and/or time.

Contact information for Points of Contact (POCs) shall be provided by the Contracting Officer upon award.

1. GENERAL REQUIREMENT

1. Upon award, the Contractor shall submit sample and technical specifications on all materials being used in this project and shall not proceed with any work prior to approval by the Project Manager and COR.

2. Before beginning any demolition work, the Contractor shall survey the site and examine the drawings and review the scope of work to determine the extent of the work. The Contractor shall take the necessary precautions to avoid damages to existing items to remain in place, to be reused or to remain the property of the Cemetery. Any damaged items shall be repaired or replaced at the Contractor’s expense as directed by the CO.

3. Establish construction limits, install safety controls, and install construction fencing as approved by the COR.

4. Thoroughly clean up the work area at the end of each day’s work and at completion of the project. Leave premises clean and free of waste, scrap, used equipment or other material intentionally or incidentally delivered to the site by Contractor or Contractor’s personnel.

5. The Contractor shall protect form damage all existing improvements, equipment, structures, facilities, grounds and utilities at or near the work site or adjacent property. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

6. Upon completion of contact, deliver work complete and undamaged. Existing materials, equipment, structures, facilities, grounds and disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in good condition as existed before commencing work.

7. At Contractor’s own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor’s workmen to exist ring piping and consults, wires, cables, etc., of utility services or of fire protection systems, communication systems (including telephone) which are not scheduled for discontinuance or abandonment.

8. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the CO and COR before it is disturbed. Materials and workmanship used in restoring work shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

9. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs and grass) on or adjacent to the work site not to be removed and do not reasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

10. All utilities required for the continuous operation of all existing facilities shall be maintained in service at all times except when disruptions are needed. The contractor shall inform the Cemetery Director, COR and CO in writing two (2) weeks prior to the need shutdown. When the option exists, implement options to minimize interruption of services to the facilities.

11. The Contractor shall coordinate with the Cemetery Director for parking, material storage, temporary portable restroom facilities and any other needs for the work. Public access to the National Cemetery shall not be impaired.

12. Coordination of Construction with the Cemetery Director: The burial activities at a National Cemetery shall take precedence over construction activities. The Contractor must cooperate and coordinate with the Cemetery Director, through the COR, in arranging construction the construction schedule to cause the least possible interference with Cemetery activities in actual burial areas. Construction noise during the committal services shall not disturb the service. Trucks and workmen shall not pass through the service area during this period.

a. The Contractor is required to discontinue his work efficiently in advance of Easter Sunday, Mother’s Day, Father’s Day, Memorial Day, Veteran’s Day and/or Federal Holidays to permit him to clean up all areas of operation adjacent to existing burial plots before these dates.

b. Cleaning up shall include the removal of all equipment, tools, materials and debris and leaving the area in a clean, neat condition.

c. Site work will be accomplished between the hours of 8:00 and 4:30, Monday through Friday, except Federal Holiday’s. Work outside of the Cemetery’s normal operating hours of 8:00 am to 4:30 pm shall be permitted on by approval of the COR and to only meet the Period of Performance.

2. STANDARDS OF EMPLOYEE CONDUCT:

1. The National Cemetery Administration honors veterans with a final resting place and lasting memorials that commemorate their service to our Nation. National Cemeteries are national shrines. The standards of work appearance and procedures performed by the Contractor at this cemetery shall reflect this nations concern for those interred there. Due to the sensitive mission of the cemetery and exhibit absolute decorum, composure, and stability all times.

2. Contractor personnel shall be required to adhere to the following standards of dress and conduct, as briefly mentioned here while performing work in the National Cemetery. These standards are enforceable under Title 38, USC, Part 1, Chapter 9, and Section 5901.

3. Clothing shall be presentable and suitable to the work while maintaining proper appearance and decorum indicative for a National Shrine. Uniform shirts and hats are preferred. Clothing shall be clean and cleanliness and personal hygiene are imperative. T-shirts and/or tank tops as outer garments are prohibited. Protective/Safety clothing and shoes shall meet or exceed OSHA and state requirements.

4. Behavior and language must be appropriate, reverent and respectful at all times.

5. Eating and drinking (except water) is prohibited in the work areas and within the sight of a committal shelter during a service.

6. Use of intoxicating beverages, any tobacco products, and illegal drugs on the Cemetery is strictly prohibited.

7. Contractor personnel shall not lean, sit, or stand on or against headstones or monuments. No tools, equipment’s or other items will be placed on or leaned on headstones or monuments.

8. The Contractor shall be responsible for maintaining satisfactory standards of personnel conduct and work performance and shall administer disciplinary action as required. The Contractor is expected to remove any employee(s) from the Cemetery for cause, to include, but not limited to, safety violations, other misconduct in performance of duty under these specifications and/or contrary to the best interest of the Government. If the Contractor fails to act in this regard, or the reason for removal is immediately required to protect the interests of the Government, the COR may direct the removal of an employee from the premises. Contractor objections to any such action will be referred to the Contracting Officer (CO) for final resolution; however, the Contractor will first immediately comply with COR direction pending any CO final resolution at a later date or time. The Contractor will not be due any type of compensation for their costs incurred as a result of an employee being removed for cause; unless the removal is directed by the COR and in later found to be invalid or and/or unreasonable by the Contracting Officer.

9. All work shall be performed in accordance with National, State, and Local Codes including the International Building Code (IBC), the International Mechanical Code (IMC), the International Plumbing Code (IPC), and the National Electrical Code (NEC).

All work shall be performed in accordance with the drawings and specifications. It shall be the Contractor’s responsibility to comply with all the applicable codes. The Contractor shall apply and obtain all applicable permits to comply with local, State and Federal regulations.

3. CONTRACTOR QUALITY CONTROL

1. The Contractor shall guarantee that all work done under this contract shall be free from defaults and no faulty materials or workmanship with one (1) year warranty or extended manufacturer’s warranty. The Contractor hereby agrees to repair or replace deficiencies within the specified time frame by the direction of the Contracting Officer (CO) at the Contractor’s expense, and shall be corrected to the satisfaction of the Government.

2. The Contractor shall provide a Job Site Superintendent who speaks and write fluent English on site, and at all times when Contractor personnel are on the premises. The Job Superintendent will:

a. Review and Approve submittals

b. Inspect the quality of work performed

c. Certify the completed work for payment and other purposes

3. Completion Time: One hundred fifty days (150) calendar days from date of issuance of Notice to Proceed (NTP).

(END OF WORK STATEMENT)