36C78618Q0292-009.pdf

PDF 28 KB Posted

Attached to
NRM - MIDWEST DISTRICT. Project: 909-18-107 “Honor Guard Building Repairs
Solicitation number
36C78618Q0292
Issued by

About this file

36C78618Q0292 S02 ResinousFlooring.pdf

View the file

Other files

File Type Posted
36C78618Q0292-00002000.docx DOCX document
36C78618Q0292-00001000.docx DOCX document
36C78618Q0292-005.pdf PDF
36C78618Q0292-007.pdf PDF
36C78618Q0292-010.pdf PDF
36C78618Q0292-006.pdf PDF
36C78618Q0292-001.docx DOCX document
36C78618Q0292-004.pdf PDF
36C78618Q0292-002.pdf PDF
36C78618Q0292-003.pdf PDF
36C78618Q0292-008.pdf PDF
36C78618Q0292-000.docx DOCX document
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

06-01-14

RESINOUS FLOORING

09 67 23 - 1

SECTION 09 67 23

RESINOUS FLOORING

PART 1 - GENERAL

1.1 DESCRIPTION

A. This section specifies a seamless flooring system with integral base.

B. Flooring consists of epoxy resin, aggregate, and finish coats for non-slip finish.

1.2 SUBMITTALS

A. Manufacturer's Literature and Data:

1. Description of product to be provided; technical data showing compliance with specifications.

2. Application and installation instructions, including proposed deviations from specifications.

1.3 QUALITY ASSURANCE

A. Single Source Responsibility:

1. Obtain primary resinous flooring materials including primers, resins, hardening agents, finish or sealing coats from a single manufacturer.

2. Provide secondary materials only of type and from source recommended by manufacturer of primary materials.

B. Installer Qualifications: Installer trained and approved by manufacturer of primary material and having completed at least five projects of similar size and complexity.

1.4 MATERIAL PACKAGING DELIVERY AND STORAGE

A. Deliver materials to the site in original sealed packages or containers, clearly marked with the manufacturer's name or brand, type and color, production run number and date of manufacture.

B. Protect materials from damage and contamination in storage.

C. Maintain temperature of storage area between 15oC and 32oC (60o and

90oF).

D. Package materials in factory pre-weighed and in single, easy to manage batches sized for ease of handling and mixing proportions from entire package or packages.

1.5 APPLICABLE PUBLICATIONS

A. Publications listed below form a part of this specification to extent referenced. Publications are referenced in text by the basic designation only. Comply with applicable provisions and recommendations of the following, except as otherwise shown or specified.

09 67 23 - 2

B. American Society for Testing and Materials (ASTM):

B221-13 Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Shapes, and Tubes

C267-07(2013) Chemical Resistance of Mortars, Grouts, and

Monolithic Surfacings

C413-01(2012) Absorption of Chemical-Resistant Mortars, Grouts, and Monolithic Surfacings, and Polymer

Concretes

C580-02(2012) Flexural Strength and Modulus of Elasticity of

Chemical Resistant Mortars, Grouts, Monolithic

Surfacings and Polymer Concretes

C722-04(2012) Chemical-Resistant Resin Monolithic Surfacing

C882/C882M-12 Bond Strength of Epoxy-Resin Systems Used with

Concrete by Slant Shear

D635-10 Rate of Burning and/or Extent and Time of

Burning of Plastics in a Horizontal Position

D2047-11 Static Coefficient of Friction of Polish-Coated

Floor Surfaces as Measured by the James Machine

D2240-05(2010) Rubber Property - Durometer Hardness

D4060-10 Abrasion Resistance of Organic Coatings by the

Taber Abraser

F1869-11 Measuring Moisture Vapor Emission Rate of

Concrete Subfloor Using Anhydrous Calcium

Chloride

F2170-11 Determining Relative Humidity in Concrete Floor

Slabs Using in situ Probes

C. National Association of Architectural Metal Manufacturers (NAAMM):

AMP 501 Finishes for Aluminum

PART 2 - PRODUCTS

2.1 SYSTEM DESCRIPTION

A. Epoxy resinous flooring includes concrete epoxy primer, colored quartz aggregate epoxy resin mortar, clear epoxy sealer coat, and finish coat for non-slip finish.

B. System to be resistant to chemicals and abrasion.

C. Comply with requirements of FloorScore standard.

2.2 EPOXY FLOORING SYSTEM

A. Conform to ASTM C722, Type A, Epoxy resin, quartz aggregate.

09 67 23 - 3

B. Physical Properties of flooring system addition to C722 when tested as follows:

PROPERTY TEST VALUE

Hardness ASTM D2240 Shore Durometer

75-80

Bond ASTM C882 Bonding epoxy flooring to hardened concrete min 400 psi

Water Absorption ASTM C413 max 0.1 percent Abrasion Resistance ASTM D4060

Taber Abrader CS-17 wheel, 1000 gm load;

1000 cycle max 0.10 gms.

weight loss

Flexural Strength ASTM C580 min 2200 psi Extent of Burning extinguishing Heat Resistant

ASTM D635

For continuous exposure min 140 deg. F For intermittent spills min 200 deg. F max 0.25 inch self No Effect

No Effect

Coefficient of Friction

ASTM D 2047 0.7

Chemical Resistance of the following:

ASTM C267 No Effect

Acetic acid 5 percent Ammonium hydroxide 10 percent

Citric Acid Fatty acid Motor Oil, 20W Hydrochloric acid Salt water Sodium Hydroxide Sulfuric acid Trisodium phosphate

50 percent

10 percent

5 percent

Urine Feces Hydrogen peroxide 28 percent Distilled Water Sodium Hypochloride 5.28 percent

C. Primer, Coloring, Sealer, and Finish coats as standard with manufacture of flooring system.

PART 3 - EXECUTION

3.1 PROJECT CONDITIONS

A. Maintain temperature of materials above 21oC (70 degrees F), for 48 hours before installation.

B. Maintain temperature of rooms where work occurs, between 21oC and 32oC

(70oF and 90oF) for at least 48 hours, before, during, and 24 hours after installation. Maintain temperature at least 21oC (70 degrees F) thereafter.

09 67 23 - 4

C. Do not install materials until building is permanently enclosed and wet construction is complete, dry, and cured.

D. Concrete substrate cured and not less than 30 days old.

E. Area free of other trades during and for a period of 24 hours after installation.

3.2 INSTALLATION REQUIREMENTS

A. The respective manufacturer's instructions for application and installation will be considered for use when approved by the RE/COR.

B. Submit proposed installation deviation from this specification to the

RE/COR indicating the differences in the method of installation.

3.3 PREPARATION

A. Prepare surface in accordance with manufacturer's instructions.

B. Mechanically remove bond inhibiting materials and loose or laitance materials to ensure bond.

C. Moisture Testing: Perform moisture and pH test as recommended by the flooring and adhesive manufacturers. Perform test locations starting on the deepest part of the concrete structure. Proceed with installation only after concrete substrates meet or exceed the manufacturer’s requirements. In the absence of specific guidance from the flooring or adhesive manufacturer the following requirements are to be met:

1. Perform moisture vapor emission tests in accordance with ASTM F1869.

Proceed with installation only after substrates have a maximum moisture-vapor-emission rate of 1.36 kg of water/92.9 sq. m (3lb of water/1000 sq. ft.) in 24 hours.

2. Perform concrete internal relative humidity testing using situ probes in accordance with ASTM F2170. Proceed with installation only after concrete reaches maximum 75 percent relative humidity level measurement.

D. Prepare wall and set base cap mold level.

1. Fill voids within the height of the wall where base is applied even with the wall surface.

2. Grind, sand, or cut away protrusions.

3.4 APPLICATION

A. Mix and apply each component of resinous flooring system in compliance with manufacturer's specifications to produce a uniform monolithic flooring surface of 5 mm (3/16 inch) minimum thickness.

09 67 23 - 5

B. Turn flooring up for coved 100 mm (4-inch) high base at vertical wall surfaces and penetrations. Cove joint with floor; 6 mm (1/4 inch) radius. Round interior and external corners.

C. Apply primer over prepared substrate at manufacturers specified rate.

Coordinate timing of primer application with application of troweled mortar to ensure optimum adhesion between resinous flooring materials and substrate.

D. Uniformly spread mortar over substrate adjusted to manufacturer's recommended maximum thickness to plane line of floor.

E. Trowel finish for smooth surface on base and coved surface.

F. Grout mortar surface as specified by manufacturer and broad cast colored quartz aggregate uniformly distributed for non-slip texture on floors to within one inch of base cove horizontal edge.

G. Apply a clear finish coat.

3.5 CURING, PROTECTION, AND CLEANING

A. Cure resinous flooring materials in compliance with manufacturer's directions, taking care to prevent contamination during stages of application and prior to completion of curing process.

B. Close area of application for a minimum of 24 hours.

C. Protect resinous flooring materials from damage and wear during construction operation.

1. Cover flooring with kraft paper.

2. Covers paper with 6 mm (1/4 inch) thick hardboard, plywood, or particle board where area is in foot or vehicle traffic pattern, rolling or fixed scaffolding and overhead work occurs.

D. Remove temporary covering and clean resinous flooring just prior to final inspection. Use cleaning materials and procedures recommended by resinous flooring manufacturer.

3.6 TOLERANCE

A. From Line of Plane: Maximum 3 mm (1/8 inch) in total distance of flooring and base.

B. From Radius of Cove: Maximum of 3 mm (1/8 inch) plus or 1.6 mm (1/16-inch) minus.

- - - E N D - - -

SECTION 09 67 23 RESINOUS FLOORING
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies a seamless flooring system with integral base.
B. Flooring consists of epoxy resin, aggregate, and finish coats for non-slip finish.
1.2 SUBMITTALS
A. Manufacturer's Literature and Data:
1. Description of product to be provided; technical data showing compliance with specifications.
2. Application and installation instructions, including proposed deviations from specifications.
1.3 QUALITY ASSURANCE
A. Single Source Responsibility:
1. Obtain primary resinous flooring materials including primers, resins, hardening agents, finish or sealing coats from a single manufacturer.
2. Provide secondary materials only of type and from source recommended by manufacturer of primary materials.

B. Installer Qualifications: Installer trained and approved by manufacturer of primary material and having completed at least five projects of similar size and complexity.

1.4 MATERIAL PACKAGING DELIVERY AND STORAGE
A. Deliver materials to the site in original sealed packages or containers, clearly marked with the manufacturer's name or brand, type and color, production run number and date of manufacture.
B. Protect materials from damage and contamination in storage.
C. Maintain temperature of storage area between 15oC and 32oC (60o and 90oF).
D. Package materials in factory pre-weighed and in single, easy to manage batches sized for ease of handling and mixing proportions from entire package or packages.
1.5 APPLICABLE PUBLICATIONS
A. Publications listed below form a part of this specification to extent referenced. Publications are referenced in text by the basic designation only. Comply with applicable provisions and recommendations of the following, except as otherwise shown o...
B. American Society for Testing and Materials (ASTM):
B221-13 Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Shapes, and Tubes
C267-07(2013) Chemical Resistance of Mortars, Grouts, and Monolithic Surfacings
C413-01(2012) Absorption of Chemical-Resistant Mortars, Grouts, and Monolithic Surfacings, and Polymer Concretes
C580-02(2012) Flexural Strength and Modulus of Elasticity of Chemical Resistant Mortars, Grouts, Monolithic Surfacings and Polymer Concretes
C722-04(2012) Chemical-Resistant Resin Monolithic Surfacing
C882/C882M-12 Bond Strength of Epoxy-Resin Systems Used with Concrete by Slant Shear
D635-10 Rate of Burning and/or Extent and Time of Burning of Plastics in a Horizontal Position
D2047-11 Static Coefficient of Friction of Polish-Coated Floor Surfaces as Measured by the James Machine
D2240-05(2010) Rubber Property - Durometer Hardness
D4060-10 Abrasion Resistance of Organic Coatings by the Taber Abraser
F1869-11 Measuring Moisture Vapor Emission Rate of Concrete Subfloor Using Anhydrous Calcium Chloride
F2170-11 Determining Relative Humidity in Concrete Floor Slabs Using in situ Probes
C. National Association of Architectural Metal Manufacturers (NAAMM):
AMP 501 Finishes for Aluminum
PART 2 - PRODUCTS
2.1 SYSTEM DESCRIPTION
A. Epoxy resinous flooring includes concrete epoxy primer, colored quartz aggregate epoxy resin mortar, clear epoxy sealer coat, and finish coat for non-slip finish.
B. System to be resistant to chemicals and abrasion.
C. Comply with requirements of FloorScore standard.
2.2 EPOXY FLOORING SYSTEM
A. Conform to ASTM C722, Type A, Epoxy resin, quartz aggregate.
B. Physical Properties of flooring system addition to C722 when tested as follows:
C. Primer, Coloring, Sealer, and Finish coats as standard with manufacture of flooring system.
PART 3 - EXECUTION
3.1 PROJECT CONDITIONS
A. Maintain temperature of materials above 21oC (70 degrees F), for 48 hours before installation.
B. Maintain temperature of rooms where work occurs, between 21oC and 32oC (70oF and 90oF) for at least 48 hours, before, during, and 24 hours after installation. Maintain temperature at least 21oC (70 degrees F) thereafter.
C. Do not install materials until building is permanently enclosed and wet construction is complete, dry, and cured.
D. Concrete substrate cured and not less than 30 days old.
E. Area free of other trades during and for a period of 24 hours after installation.
3.2 INSTALLATION REQUIREMENTS
A. The respective manufacturer's instructions for application and installation will be considered for use when approved by the RE/COR.
B. Submit proposed installation deviation from this specification to the RE/COR indicating the differences in the method of installation.
3.3 PREPARATION
A. Prepare surface in accordance with manufacturer's instructions.
B. Mechanically remove bond inhibiting materials and loose or laitance materials to ensure bond.
C. Moisture Testing: Perform moisture and pH test as recommended by the flooring and adhesive manufacturers. Perform test locations starting on the deepest part of the concrete structure. Proceed with installation only after concrete substrates meet o...
1. Perform moisture vapor emission tests in accordance with ASTM F1869. Proceed with installation only after substrates have a maximum moisture-vapor-emission rate of 1.36 kg of water/92.9 sq. m (3lb of water/1000 sq. ft.) in 24 hours.
2. Perform concrete internal relative humidity testing using situ probes in accordance with ASTM F2170. Proceed with installation only after concrete reaches maximum 75 percent relative humidity level measurement.
D. Prepare wall and set base cap mold level.
1. Fill voids within the height of the wall where base is applied even with the wall surface.
2. Grind, sand, or cut away protrusions.
3.4 APPLICATION
A. Mix and apply each component of resinous flooring system in compliance with manufacturer's specifications to produce a uniform monolithic flooring surface of 5 mm (3/16 inch) minimum thickness.
B. Turn flooring up for coved 100 mm (4-inch) high base at vertical wall surfaces and penetrations. Cove joint with floor; 6 mm (1/4 inch) radius. Round interior and external corners.
C. Apply primer over prepared substrate at manufacturers specified rate. Coordinate timing of primer application with application of troweled mortar to ensure optimum adhesion between resinous flooring materials and substrate.
D. Uniformly spread mortar over substrate adjusted to manufacturer's recommended maximum thickness to plane line of floor.
E. Trowel finish for smooth surface on base and coved surface.
F. Grout mortar surface as specified by manufacturer and broad cast colored quartz aggregate uniformly distributed for non-slip texture on floors to within one inch of base cove horizontal edge.
G. Apply a clear finish coat.
3.5 CURING, PROTECTION, AND CLEANING
A. Cure resinous flooring materials in compliance with manufacturer's directions, taking care to prevent contamination during stages of application and prior to completion of curing process.
B. Close area of application for a minimum of 24 hours.
C. Protect resinous flooring materials from damage and wear during construction operation.
1. Cover flooring with kraft paper.
2. Covers paper with 6 mm (1/4 inch) thick hardboard, plywood, or particle board where area is in foot or vehicle traffic pattern, rolling or fixed scaffolding and overhead work occurs.

D. Remove temporary covering and clean resinous flooring just prior to final inspection. Use cleaning materials and procedures recommended by resinous flooring manufacturer.

3.6 Tolerance
A. From Line of Plane: Maximum 3 mm (1/8 inch) in total distance of flooring and base.
B. From Radius of Cove: Maximum of 3 mm (1/8 inch) plus or 1.6 mm (1/16-inch) minus.