36C78618Q0207-003.pdf
PDF 353 KB Posted
- Solicitation number
- 36C78618Q0207
About this file
36C78618Q0207 917-M_R18-12 Full Specifications.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C78618Q0207-002.pdf | ||
| 36C78618Q0207-001.docx | DOCX document | |
| 36C78618Q0207-000.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment H:
Project Number 917-M&R18-12
Replace Flagpole at the
Albany Rural Cemetery Soldiers’
Lot
TECHNICAL SPECIFICATIONS AND DRAWINGS -
TABLE OF CONTENTS
SPECIFICATION SECTIONS:
01 33 23 Shop Drawings, Product Data, and Samples 01 45 29 Testing Laboratory Services 02 41 10 Demolition and Site Clearing 03 30 00 Cast-In-Place and Pre-cast Concrete 10 75 00 Flagpoles 31 20 11 Earth Moving (short form)
DRAWINGS:
NONE
06-01-14
SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
01 33 23 - 1
SECTION 01 33 23
1-1. Refer to Articles titled SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION
(FAR 52.236-21) and, SPECIAL NOTES (VAAR 852.236-91), in GENERAL
CONDITIONS.
1-2. For the purposes of this contract, samples including laboratory samples to be tested, test reports, certificates, and manufacturers' literature and data shall also be subject to the previously referenced requirements. The following text refers to all items collectively as
SUBMITTALS.
1-3. Submit for approval, all of the items specifically mentioned under the separate sections of the specification, with information sufficient to evidence full compliance with contract requirements. Materials, fabricated articles and the like to be installed in permanent work shall equal those of approved submittals. After an item has been approved, no change in brand or make will be permitted unless:
A. Satisfactory written evidence is presented to, and approved by
Contracting Officer, that manufacturer cannot make scheduled delivery of approved item or;
B. Item delivered has been rejected and substitution of a suitable item is an urgent necessity or;
C. Other conditions become apparent which indicates approval of such substitute item to be in best interest of the Government.
1-4. Forward submittals in sufficient time to permit proper consideration and approval action by Government. Time submission to assure adequate lead time for procurement of contract - required items. Delays attributable to untimely and rejected submittals including any laboratory samples to be tested will not serve as a basis for extending contract time for completion.
1-5. Submittals shall be reviewed for compliance with contract requirements by Architect-Engineer (hired by contractor), and action thereon will be taken by COR on behalf of the Contracting Officer.
1-6. Upon receipt of submittals, Architect-Engineer will assign a file number thereto. Contractor, in any subsequent correspondence, shall
01 33 23 - 2 refer to this file and identification number to expedite replies relative to previously approved or disapproved submittals.
1-7. The Government reserves the right to require additional submittals, whether or not particularly mentioned in this contract. If additional submittals beyond those required by the contract are furnished pursuant to request therefor by Contracting Officer, adjustment in contract price and time will be made in accordance with Articles titled CHANGES
(FAR 52.243-4) and CHANGES - SUPPLEMENT (VAAR 852.236-88) of the
GENERAL CONDITIONS.
1-8. Schedules called for in specifications and shown on shop drawings shall be submitted for use and information of Department of Veterans Affairs and Architect-Engineer. However, the Contractor shall assume responsibility for coordinating and verifying schedules. The
Contracting Officer and Architect- Engineer assumes no responsibility for checking schedules or layout drawings for exact sizes, exact numbers and detailed positioning of items.
1-9. Submittals must be submitted by Contractor only and shipped prepaid.
Contracting Officer assumes no responsibility for checking quantities or exact numbers included in such submittals.
A. Submit samples in single units unless otherwise specified. Submit shop drawings, schedules, manufacturers' literature and data, and certificates in quadruplicate, except where a greater number is specified.
B. Submittals will receive consideration only when covered by a transmittal letter signed by Contractor. Letter shall be sent via first class mail and shall contain the list of items, name of Cemetery, name of Contractor, contract number, applicable specification paragraph numbers, applicable drawing numbers (and other information required for exact identification of location for each item), manufacturer and brand, ASTM or Federal Specification Number (if any) and such additional information as may be required by specifications for particular item being furnished. In addition, catalogs shall be marked to indicate specific items submitted for approval.
1. A copy of letter must be enclosed with items, and any items received without identification letter will be considered "unclaimed goods" and held for a limited time only.
01 33 23 - 3
2. Each sample, certificate, manufacturers' literature and data shall be labeled to indicate the name and location of the Cemetery, name of Contractor, manufacturer, brand, contract number and ASTM or
Federal Specification Number as applicable and location(s) on project.
3. Required certificates shall be signed by an authorized representative of manufacturer or supplier of material, and by
Contractor.
C. In addition to complying with the applicable requirements specified in preceding Article 1.9, samples which are required to have Laboratory
Tests (those preceded by symbol "LT" under the separate sections of the specification shall be tested, at the expense of Contractor, in a commercial laboratory approved by Contracting Officer.
1. Laboratory shall furnish Contracting Officer with a certificate stating that it is fully equipped and qualified to perform intended work, is fully acquainted with specification requirements and intended use of materials and is an independent establishment in no way connected with organization of Contractor or with manufacturer or supplier of materials to be tested.
2. Certificates shall also set forth a list of comparable projects upon which laboratory has performed similar functions during past five years.
3. Samples and laboratory tests shall be sent directly to approved commercial testing laboratory.
4. Contractor shall send a copy of transmittal letter to both COR and to Architect-Engineer simultaneously with submission of material to a commercial testing laboratory.
4b. Contractor shall forward a copy of transmittal letter to COR simultaneously with submission to a commercial testing laboratory.
5. Laboratory test reports shall be sent directly to COR for appropriate action.
6. Laboratory reports shall list contract specification test requirements and a comparative list of the laboratory test results.
When tests show that the material meets specification requirements, the laboratory shall so certify on test report.
7. Laboratory test reports shall also include a recommendation for approval or disapproval of tested item.
01 33 23 - 4
D. If submittal samples have been disapproved, resubmit new samples as soon as possible after notification of disapproval. Such new samples shall be marked "Resubmitted Sample" in addition to containing other previously specified information required on label and in transmittal letter.
E. Approved samples will be kept on file by the COR at the site until completion of contract, at which time such samples will be delivered to
Contractor as Contractor's property. Where noted in technical sections of specifications, approved samples in good condition may be used in their proper locations in contract work. At completion of contract, samples that are not approved will be returned to Contractor only upon request and at Contractor's expense. Such request should be made prior to completion of the contract. Disapproved samples that are not requested for return by Contractor will be discarded after completion of contract.
F. Submittal drawings (shop, erection or setting drawings) and schedules, required for work of various trades, shall be checked before submission by technically qualified employees of Contractor for accuracy, completeness and compliance with contract requirements. These drawings and schedules shall be stamped and signed by Contractor certifying to such check.
1. For each drawing required, submit one legible photographic paper or vellum reproducible.
2. Reproducible shall be full size.
3. Each drawing shall have marked thereon, proper descriptive title, including Cemetery location, project number, manufacturer's number, reference to contract drawing number, detail Section Number, and
Specification Section Number.
4. A space 120 mm by 125 mm (4-3/4 by 5 inches) shall be reserved on each drawing to accommodate approval or disapproval stamp.
5. Submit drawings, ROLLED WITHIN A MAILING TUBE, fully protected for shipment.
6. One reproducible print of approved or disapproved shop drawings will be forwarded to Contractor.
7. When work is directly related and involves more than one trade, shop drawings shall be submitted to Architect-Engineer under one cover.
1-10. Samples, shop drawings, test reports, certificates and manufacturers' literature and data, shall be submitted for approval to the
01 33 23 - 5 contractor’s hired Architect-Engineering firm (also discussed in these specifications as Professional Design firm).
1-11. At the time of transmittal to the Architect-Engineer, the Contractor shall also send a copy of the complete submittal directly to the COR.
1-12. Samples for approval shall be sent to COR. Coordinate address for shipment with the COR.
- - - E N D - - -
TESTING LABORATORY SERVICES
01 45 29 - 1
SECTION 01 45 29
TESTING LABORATORY SERVICES
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies materials testing activities and inspection services required during project construction to be provided by a
Testing Laboratory retained and paid for by Contractor. Refer to
Section 01 00 02, GENERAL REQUIREMENTS, for additional information.
1.2 RELATED DOCUMENTS
A. Section 01 00 02, GENERAL REQUIREMENTS.
1.3 APPLICABLE PUBLICATIONS
A. Publications listed below form a part of this specification to extent referenced. Publications are referenced in text by the basic designation only. Comply with applicable provisions and recommendations of the following, except as otherwise shown or specified.
B. American Association of State Highway and Transportation Officials
(AASHTO):
T27-11 Sieve Analysis of Fine and Coarse Aggregates
T96-02(R2006) Resistance to Degradation of Small-Size Coarse
Aggregate by Abrasion and Impact in the Los
Angeles Machine
T99-10 The Moisture-Density Relations of Soils Using a
2.5 Kg (5.5 lb.) Rammer and a 305 mm (12 in.)
Drop
T104-99(R2007) Soundness of Aggregate by Use of Sodium Sulfate or Magnesium Sulfate
T180-10 Moisture-Density Relations of Soils using a
4.54 kg (10 lb.) Rammer and a 457 mm (18 in.)
Drop
T191-02(R2006) Density of Soil In-Place by the Sand-Cone
Method
C. American Society for Testing and Materials (ASTM):
A325-10 Structural Bolts, Steel, Heat Treated, 120/105 ksi Minimum Tensile Strength
A370-12a Definitions for Mechanical Testing of Steel
Products
A490-12 Heat Treated Steel Structural Bolts, 150 ksi
Minimum Tensile Strength
01 45 29 - 2
C31/C31M-12 Making and Curing Concrete Test Specimens in the Field
C33/C33M-13 Concrete Aggregates
C39/C39M-12 Compressive Strength of Cylindrical Concrete
Specimens
C109/C109M-12 Compressive Strength of Hydraulic Cement
Mortars
C138/C138M-12a Unit Weight, Yield, and Air Content
(Gravimetric) of Concrete
C140-13 Sampling and Testing Concrete Masonry Units and
Related Units
C143/C143M-12 Slump of Hydraulic Cement Concrete
C141/C141M Standard Specification for Hydrated Hydraulic
Lime for Structural Purposes
C172/C172M-10 Sampling Freshly Mixed Concrete
C173/C173M-12 Air Content of freshly Mixed Concrete by the
Volumetric Method
C330/C33OM-09 Lightweight Aggregates for Structural Concrete
C567/C567M-11 Density Structural Lightweight Concrete
C780-12a Pre-construction and Construction Evaluation of
Mortars for Plain and Reinforced Unit Masonry
C1019-11 Sampling and Testing Grout
C1064/C1064M-12 Freshly Mixed Hydraulic Cement Concrete
C1077-13 Agencies Testing Concrete and Concrete
Aggregates for Use in Construction and Criteria for Laboratory Evaluation
C1314-12 Compressive Strength of Masonry Prisms
C1364-10b Architectural Cast Stone
D698-12 Laboratory Compaction Characteristics of Soil
Using Standard Effort
D1143/D1143M-07 Deep Foundations Under Static Axial Compressive
Load
D1188-07 Bulk Specific Gravity and Density of Compacted
Bituminous Mixtures Using Paraffin-Coated
Specimens
D1556-07 Density and Unit Weight of Soil in Place by the
Sand-Cone Method
01 45 29 - 3
D1557-12 Laboratory Compaction Characteristics of Soil
Using Modified Effort
D2166-06 Unconfined Compressive Strength of Cohesive
Soil
D2167-08 Density and Unit Weight of Soil in Place by the
Rubber Balloon Method
D2216-10 Laboratory Determination of Water (Moisture)
Content of Soil and Rock by Mass
D2974-07 Moisture, Ash, and Organic Matter of Peat and
Other Organic Soils
D3666-11 Minimum Requirements for Agencies Testing and
Inspection Bituminous Paving Materials
D3740-12a Minimum Requirements for Agencies Engaged in
Testing and/or Inspection of Soil and Rock
E94-04(2010) Radiographic Examination
E164-08 Contact Ultrasonic Testing of Weldments
E329-11c Agencies Engaged in Construction Inspection, Testing, or Special Inspection
E543-13 Agencies Performing Nondestructive Testing
E709-08 Guide for Magnetic Particle Testing
E1155-96(2008) Determining FF Floor Flatness and FL Floor
Levelness Numbers
D. American Welding Society (AWS):
D1.1-07 Structural Welding Code-Steel
1.4 REQUIREMENTS
A. Accreditation Requirements: Testing Laboratory retained and paid for by
Contractor must be accredited by one or more of the National Voluntary
Laboratory Accreditation Program (NVLAP) programs acceptable in the geographic region for the project. Submit for approval to the RE/COR a copy of the Certificate of Accreditation and Scope of Accreditation.
For testing laboratories that have not yet obtained accreditation by a
NVLAP program, submit an acknowledgement letter from one of the laboratory accreditation authorities indicating that the application for accreditation has been received and the accreditation process has started, and submit to the RE/COR for approval, certified statements, signed by an official of the testing laboratory attesting that the proposed laboratory, meets or conforms to the ASTM standards listed below as appropriate to the testing field.
01 45 29 - 4
1. Laboratories engaged in testing of construction materials must meet the requirements of ASTM E329.
2. Laboratories engaged in testing of concrete and concrete aggregates must meet the requirements of ASTM C1077.
3. Laboratories engaged in testing of bituminous paving materials must meet the requirements of ASTM D3666.
4. Laboratories engaged in testing of soil and rock, as used in engineering design and construction, must meet the requirements of
ASTM D3740.
5. Laboratories engaged in inspection and testing of steel, stainless steel, and related alloys will be evaluated according to ASTM A880.
6. Laboratories engaged in non-destructive testing (NDT) must meet the requirements of ASTM E543.
7. Laboratories engaged in Hazardous Materials Testing must meet the requirements of OSHA and EPA.
B. Inspection and Testing: Testing laboratory to inspect materials and workmanship and perform tests described herein and additional tests requested by Project Engineer and COR. When it appears materials furnished, or work performed by Contractor fail to meet construction contract requirements, Testing Laboratory must direct attention of
Project Engineer and COR to such failure.
C. Written Reports (both hand delivered and electrically sent): Testing laboratory to submit test reports to Project Engineer and COR, Contractor within 24 hours after each test is completed unless other arrangements are agreed to in writing by the Project Engineer and COR.
Submit reports of tests that fail to meet construction contract requirements on colored paper.
D. Once testing laboratory is satisfied that the work installed meets the project requirements, the testing laboratory shall submit pictures of the following work items to the Project Engineer, Contracting Officer, and COR prior to these work items being covered up by subsequent work:
reinforcing wire mesh and bars, geogrid fabric, and subbase. These pictures may be sent concurrently with the testing laboratory’s submission of approved inspection reports. These pictures shall clearly show the work required per the project documents, and be submitted a minimum of five (5) work days prior to planned subsequent work will cover them up. This is intended to allow sufficient time for the Project Engineer, Contracting Officer, and COR to verify work meets
01 45 29 - 5 the project requirements including approved submittals. Failure to submit pictures of work which is subsequently covered up will result in the Government requiring removal and reinstallation, such that verification can be performed on the project requirements.
E. Verbal Reports: Give verbal notification to Project Engineer and COR immediately of any irregularity.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.1 EARTHWORK
A. General: The Testing Laboratory is to provide qualified personnel, materials, equipment, and transportation as required to perform the services identified/required herein, within the agreed to schedule and/or time frame. The work to be performed is as identified herein including, but not be limited to, the following:
1. Observe fill and subgrades during proof-rolling to evaluate suitability of surface material to receive fill or base course.
Provide recommendations to the RE/COR regarding suitability or unsuitability of areas where proof-rolling was observed. Where unsuitable results are observed, witness excavation of unsuitable material and recommend to RE/COR extent of removal and replacement of unsuitable materials and observe proof-rolling of replaced areas until satisfactory results are obtained.
2. Provide full time observation of fill placement and compaction and field density testing in building areas and provide full time observation of fill placement and compaction and field density testing in pavement areas to verify that earthwork compaction obtained is in accordance with contract documents.
3. Provide supervised geotechnical technician to inspect excavation, subsurface preparation, and backfill for structural fill.
B. Testing Compaction:
1. Determine maximum density and optimum moisture content for each type of fill, backfill and subgrade material used, in compliance with one of the following standards: // AASHTO // T99/T180 // Method A // //
ASTM // D698 // D1557 // Method A // ASTM D698 and/or ASTM D1557.
2. Make field density tests in accordance with the primary testing method following either ASTM D2922 or AASHTO T238. Field density tests utilizing one of ASTM D1556, AASHTO T191, or ASTM D2167.
Should the testing laboratory propose these alternative methods, 01 45 29 - 6 they must provide satisfactory explanation to the RE/COR before the tests are conducted.
a. Building Slab Subgrade: At least one test of subgrade for every
185 m2 (2000 square feet) of building slab, but in no case fewer than three tests. In each compacted fill layer, perform one test for every 185 m2 (2000 square feet) of overlaying building slab, but in no case fewer than three tests.
b. Foundation Wall Backfill: One test per 30 m (100 feet) of each layer of compacted fill but in no case fewer than two tests.
c. Pavement Subgrade: One test for each 335 m2 (400 square yards), but in no case fewer than two tests.
d. Curb, Gutter, and Sidewalk: One test for each 90 m (300 feet), but in no case fewer than two tests.
e. Trenches: One test at maximum 30 m (100 foot) intervals per 1200 mm (4 foot) of vertical lift and at changes in required density, but in no case fewer than two tests.
f. Footing Subgrade: At least one test for each layer of soil on which footings will be placed. Subsequent verification and approval of each footing subgrade may be based on a visual comparison of each subgrade with related tested subgrade when acceptable to RE/COR. In each compacted fill layer below wall footings, perform one field density test for every 30 m (100 feet) of wall. Verify subgrade is level, all loose or disturbed soils have been removed, and correlate actual soil conditions observed with those indicated by test borings.
C. Testing for Footing Bearing Capacity: Evaluate if suitable bearing capacity material is encountered in footing subgrade.
D. Testing Materials: Test suitability of on-site and off-site borrow as directed by RE/COR.
3.2 FOUNDATION PILES [NOT USED]
3.3 LANDSCAPING
A. Test topsoil for organic materials, pH, phosphate, potash content, and gradation of particles.
1. Test for organic material by using ASTM D2974.
2. Determine percent of silt, sand, clay, and foreign materials such as rock, roots, and vegetation.
3. Test for moisture absorption capacity.
B. Submit laboratory test report of topsoil to RE/COR.
01 45 29 - 7
C. Submit recommendations for soil amendments, from a regional soil conservation service or cooperative extension, to bring soil into compliance with minimum parameters in these specifications.
3.4 ASPHALT CONCRETE PAVING
A. Aggregate Base Course:
1. Determine maximum density and optimum moisture content for aggregate base material in accordance with one of the following: // AASHTO
T180, Method D // ASTM D1557, Method D //.
2. Make a minimum of three field density tests on each day's final compaction on each aggregate course in accordance with either AASHTO
T191 or ASTM D1556.
3. Sample and test aggregate as necessary to insure compliance with specification requirements for gradation, wear, and soundness as specified in the applicable state highway standards and specifications.
B. Asphalt Concrete:
1. Aggregate: Sample and test aggregates in stock pile and hot-bins as necessary to insure compliance with specification requirements for gradation (AASHTO T27), wear (AASHTO T96), and soundness (AASHTO
T104).
2. Temperature: Check temperature of each load of asphalt concrete at mixing plant and at site of paving operation.
3. Density: Make a minimum of two field density tests in accordance with ASTM D1188 of asphalt base and surface course for each day's paving operation.
3.5 SITE WORK CONCRETE
A. Test site work concrete including materials for concrete as required in
Article CONCRETE of this section.
3.6 CONCRETE
A. Batch Plant Inspection and Materials Testing:
1. Perform continuous batch plant inspection until concrete quality is established to satisfaction of RE/COR with concurrence of
Contracting Officer and perform periodic inspections thereafter as determined by RE/COR.
2. Periodically inspect and test batch proportioning equipment for accuracy and report deficiencies to RE/COR.
3. Sample and test mix ingredients as necessary to insure compliance with specifications.
01 45 29 - 8
4. Sample and test aggregates daily and as necessary for moisture content. Test the dry rodded weight of the coarse aggregate whenever a sieve analysis is made, and when it appears there has been a change in the aggregate.
5. Certify, in duplicate, ingredients and proportions and amounts of ingredients in concrete conform to approved trial mixes. When concrete is batched or mixed off immediate building site, certify
(by signing, initialing or stamping thereon) on delivery slips
(duplicate) that ingredients in truck-load mixes conform to proportions of aggregate weight, cement factor, and water-cement ratio of approved trial mixes.
B. Field Inspection and Materials Testing:
1. Provide a technician at site of placement at all times to perform concrete sampling and testing.
2. Review the delivery tickets of the ready-mix concrete trucks arriving on-site. Notify the Contractor if the concrete cannot be placed within the specified time limits or if the type of concrete delivered is incorrect. Reject any loads that do not comply with the
Specification requirements. Rejected loads are to be removed from the site at the Contractor’s expense. Any rejected concrete that is placed will be subject to removal.
3. Take concrete samples at point of placement in accordance with ASTM
C172. Mold and cure compression test cylinders in accordance with
ASTM C31. Make at least three cylinders for each 40 m3 (50 cubic yards) or less of each concrete type, and at least three cylinders for any one day's pour for each concrete type. Label each cylinder with an identification number. RE/COR may require additional cylinders to be molded and cured under job conditions.
4. Perform slump tests in accordance with ASTM C143. Test the first truck each day, and every time test cylinders are made. Test pumped concrete at the hopper and at the discharge end of the hose at the beginning of each day’s pumping operations to determine change in slump.
5. Determine the air content of concrete per ASTM C173. For concrete required to be air-entrained, test the first truck and every 20 m3
(25 cubic yards) thereafter each day. For concrete not required to be air-entrained, test every 80 m3 (100 cubic yards) at random. For
01 45 29 - 9 pumped concrete, initially test concrete at both the hopper and the discharge end of the hose to determine change in air content.
6. If slump or air content fall outside specified limits, make another test immediately from another portion of same batch.
7. Perform unit weight tests in compliance with ASTM C138 for normal weight concrete and ASTM C567 for lightweight concrete. Test the first truck and each time cylinders are made.
8. Notify laboratory technician at batch plant of mix irregularities and request materials and proportioning check.
9. Verify that specified mixing has been accomplished.
10. Environmental Conditions: Determine the temperature per ASTM C1064 for each truckload of concrete during hot weather and cold weather concreting operations:
a. When ambient air temperature falls below 4.4 degrees C (40 degrees F), record maximum and minimum air temperatures in each
24 hour period; record air temperature inside protective enclosure; record minimum temperature of surface of hardened concrete.
b. When ambient air temperature rises above 29.4 degrees C (85 degrees F), record maximum and minimum air temperature in each 24 hour period; record minimum relative humidity; record maximum wind velocity; record maximum temperature of surface of hardened concrete.
11. Inspect the reinforcing steel placement, including bar size, bar spacing, top and bottom concrete cover, proper tie into the chairs, and grade of steel prior to concrete placement. Submit detailed report of observations.
12. Observe conveying, placement, and consolidation of concrete for conformance to specifications.
13. Observe condition of formed surfaces upon removal of formwork prior to repair of surface defects and observe repair of surface defects.
14. Observe curing procedures for conformance with specifications, record dates of concrete placement, start of preliminary curing, start of final curing, end of curing period.
15. Observe preparations for placement of concrete:
a. Inspect handling, conveying, and placing equipment, inspect vibrating and compaction equipment.
01 45 29 - 10
b. Inspect preparation of construction, expansion, and isolation joints.
16. Observe preparations for protection from hot weather, cold weather, sun, and rain, and preparations for curing.
17. Observe concrete mixing:
a. Monitor and record amount of water added at project site.
b. Observe minimum and maximum mixing times.
18. Measure concrete flatwork for levelness and flatness as follows:
a. Perform Floor Tolerance Measurements FF and FL in accordance with
ASTM E1155. Calculate the actual overall F- numbers using the inferior/superior area method.
b. Perform all floor tolerance measurements within 48 hours after slab installation and prior to removal of shoring and formwork.
c. Provide the Contractor and the RE/COR with the results of all profile tests, including a running tabulation of the overall FF and FL values for all slabs installed to date, within 72 hours after each slab installation.
19. Other inspections:
a. Grouting under base plates.
b. Grouting anchor bolts and reinforcing steel in hardened concrete.
C. Laboratory Tests of Field Samples:
1. Test compression test cylinders for strength in accordance with ASTM
C39. For each test series, test one cylinder at 7 days and one cylinder at 28 days. Use remaining cylinder as a spare tested as directed by RE/COR. Compile laboratory test reports as follows:
Compressive strength test to be the result of one cylinder, except when one cylinder shows evidence of improper sampling, molding or testing, in which case it must be discarded and strength of spare cylinder to be used.
2. Make weight tests of hardened lightweight structural concrete in accordance with ASTM C567.
3. Furnish certified compression test reports (duplicate) to RE/COR. In test report, indicate the following information:
a. Cylinder identification number and date cast.
b. Specific location at which test samples were taken.
c. Type of concrete, slump, and percent air.
d. Compressive strength of concrete in MPa (psi).
01 45 29 - 11
e. Weight of lightweight structural concrete in kg/m3 (pounds per cubic feet).
f. Weather conditions during placing.
g. Temperature of concrete in each test cylinder when test cylinder was molded.
h. Maximum and minimum ambient temperature during placing.
i. Ambient temperature when concrete sample in test cylinder was taken.
j. Date delivered to laboratory and date tested.
3.7 REINFORCEMENT
A. Review mill test reports furnished by Contractor.
B. Make one tensile and one bend test in accordance with ASTM A370 from each pair of samples obtained.
C. Written report must include, in addition to test results, heat number, manufacturer, type and grade of steel, and bar size.
D. Perform tension tests of mechanical and welded splices in accordance with ASTM A370.
3.8 PRESTRESSED CONCRETE
A. Inspection at Plant: Forms, placement and concrete cover of reinforcing steel and tendons, placement and finishing of concrete, and tensioning of tendons.
B. Concrete Testing: Test concrete including materials for concrete required in Article, CONCRETE of this section, except make two test cylinders for each day's production of each strength of concrete produced.
C. Test tendons for conformance with ASTM A416 and furnish report to
RE/COR.
D. Inspect members to insure that specification requirements for curing and finishes have been met.
3.9 ARCHITECTURAL CAST STONE
A. Perform testing according to ASTM C1364 or verify compliance by reviewing previous test results of same product.
B. Inspect the plant to verify that specification requirements for curing and finishes have been met.
3.10 MASONRY
A. Mortar Tests:
1. Laboratory compressive strength test:
a. Comply with ASTM C780.
01 45 29 - 12
b. Obtain samples during or immediately after discharge from batch mixer.
c. Furnish molds with 50 mm (2 inch), 3 compartment gang cube.
d. For type N, S, or M mortar mixes: Test one sample at 7 days, 2 samples at 28 days, and hold 1 additional sample for testing if required by Project Engineer or COR.
e. For historic mortar mixes: Test one sample at 7 days, 1 sample at
28 days, 1 sample at 180 days, and 1 additional sample for testing at 365 days.
2. Two tests during first week of operation; one test per week after initial test until masonry completion.
B. Grout Tests:
1. Laboratory compressive strength test:
a. Comply with ASTM C1019.
b. Test one sample at 7 days and 2 samples at 28 days.
c. Perform test for each 230 m2 (2500 square feet) of masonry.
C. Masonry Unit Tests:
1. Laboratory Compressive Strength Test:
a. Comply with ASTM C140.
b. Test 3 samples for each 460 m2 (5000 square feet) of wall area.
D. Prism Tests: For each type of wall construction indicated, test masonry prisms per ASTM C1314 for each 460 m2 (5000 square feet) of wall area.
Prepare one set of prisms for testing at 7 days and one set for testing at 28 days.
E. Field Inspection and Materials Testing:
1. Verify the following prior to grouting:
a. Grout space is clean.
b. Type, spacing, and placement of reinforcement, connectors, and anchors comply with the contract requirements.
3.11 STRUCTURAL STEEL [NOT USED]
3.12 STEEL DECKING [NOT USED]
3.13 SHEAR CONNECTOR STUDS [NOT USED]
DEMOLITION AND SITE CLEARING
02 41 10 - 1
SECTION 02 41 10
DEMOLITION AND SITE CLEARING
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies all site preparation work, demolition and removal of buildings, portions of buildings, utilities, other structures and debris.
1.2 RELATED WORK
A. Safety Requirements: GENERAL CONDITIONS Article, ACCIDENT PREVENTION.
B. Disconnecting utility services prior to demolition: Section 01 00 02, GENERAL REQUIREMENTS.
C. Reserved items that are to remain the property of the Government:
Section 01 00 02, GENERAL REQUIREMENTS.
1.3 PROTECTION
A. Perform demolition in such manner as to eliminate hazards to persons and property; to minimize interference with use of adjacent areas, utilities and structures or interruption of use of such utilities; and to provide free passage to and from such adjacent areas of structures.
Comply with requirements of GENERAL CONDITIONS Article, ACCIDENT
PREVENTION.
B. Provide safeguards, including warning signs, barricades, temporary fences, warning lights, and other similar items that are required for protection of all personnel during demolition and removal operations.
Comply with requirements of Section 01 00 02, GENERAL REQUIREMENTS.
C. Maintain fences, barricades, lights, and other similar items around exposed excavations until such excavations have been completely filled.
D. Provide enclosed dust chutes with control gates from each floor to carry debris to truck beds and govern flow of material into truck.
Provide overhead bridges of tight board or prefabricated metal construction at dust chutes to protect persons and property from falling debris.
E. Prevent spread of flying particles and dust. Sprinkle rubbish and debris with water to keep dust to a minimum. Do not use water if it results in hazardous or objectionable condition such as, but not limited to; ice, flooding, or pollution. Vacuum and dust the work area daily.
F. In addition to previously listed fire and safety rules to be observed in performance of work, include following:
02 41 10 - 2
1. No wall or part of wall shall be permitted to fall outwardly from structures.
2. Maintain at least one stairway in each structure in usable condition to highest remaining floor. Keep stairway free of obstructions and debris until that level of structure has been removed.
3. Wherever a cutting torch or other equipment that might cause a fire is used, provide and maintain fire extinguishers nearby ready for immediate use. Instruct all possible users in use of fire extinguishers.
4. Keep hydrants clear and accessible at all times. Prohibit debris from accumulating within a radius of 4500 mm (15 feet) of fire hydrants.
G. Before beginning any demolition work, survey the site and examine the drawings and specifications to determine the extent of the work. Take necessary precautions to avoid damages to existing items to remain in place, to be reused, or to remain the property of the Cemetery; any damaged items shall be repaired or replaced as approved by the Project
Engineer/Contracting Officer's Representative (PROJECT ENGINEER / COR).
Coordinate the work of this section with all other work and shall construct and maintain shoring, bracing, and supports as required.
Ensure that structural elements are not overloaded and shall be responsible for increasing structural supports or adding new supports as may be required as a result of any cutting, removal, or demolition work performed under this contract. Do not overload structural elements. Provide new supports and reinforcement for existing construction weakened by demolition or removal works. Repairs, reinforcement, or structural replacement must have PROJECT ENGINEER /
COR's approval.
1.4 UTILITY SERVICES
A. Demolish and remove outside utility service lines shown to be removed.
B. Remove abandoned outside utility lines that would interfere with installation of new utility lines and new construction.
C. Assume for bidding purposes that all buried (underground) pressurized piping is installed with concrete thrust blocks, which shall be demolished by the contractor as necessary for work required.
02 41 10 - 3
PART 2 – GENERAL NOTES
2.1 DEMOLITION GENERAL NOTES
A. Referenced standards contained herein and in other specification sections dictate the requirements for new work, and are not to be taken as assurance that existing work to be demolished meets these reference standards or specifications.
PART 3 – EXECUTION
3.1 SITE CLEARING
A. General: Remove trees, shrubs, grass, and other vegetation, pavements, improvements, or obstructions, as required, to permit installation of new construction. Remove similar items elsewhere on site or premises as specifically indicated. Removal includes digging out and off-site disposal of stumps and roots.
1. Cut minor roots and branches of trees indicated to remain in a clean and careful manner where such roots and branches obstruct installation of new construction.
B. Erosion Control: Provide erosion control measures to prevent erosion or displacement of soils and discharge of soil-bearing water runoff or airborne dust to adjacent properties and walkways. Install silt fence and inlet protection as shown and as per requirements of the SWPPP, prior to any soil disturbance activities. Provide temporary seeding as required by the SWPPP.
C. Maintain site controls in accordance with Storm Water Pollution
Prevention Plan and repair as directed by COTR to sustain compliance with SPDES permit. Maintain all records as required by the SWPPP.
Perform inspections as required by the SWPPP.
D. Topsoil - On-site: Topsoil is defined as friable clay loam surface soil found in a depth of not less than 150 mm (6 inches). Satisfactory topsoil is reasonably free and/or screened of subsoil, clay lumps, stones, and other objects over 25 mm (1 inch) in diameter, and without weeds, roots, and other objectionable material.
1. Strip topsoil to whatever depths encountered in a manner to prevent intermingling with underlying subsoil or other objectionable material. Remove heavy growths of grass from areas before stripping.
a. Where existing trees are indicated to remain, leave existing topsoil in place within drip lines to prevent damage to root system.
02 41 10 - 4
2. Stockpile topsoil in storage piles in areas indicated or directed.
Construct storage piles to provide free drainage of surface water.
Cover storage piles to prevent wind erosion in accordance with the
Storm Water Pollution Prevention Plan.
a. Stockpile shall be contained with erosion and sediment controls
(silt fence) and stabilized if undisturbed in accordance with the
Storm Water Pollution Prevention Plan.
3. Dispose of unsuitable or excess topsoil as specified for disposal of waste material only after approval of the Architect.
E. Clearing and Grubbing: Clear site of trees, shrubs, and other vegetation, except for those indicated to be left standing.
1. Completely remove stumps, roots, and other debris protruding through ground surface.
2. Use only hand methods for grubbing inside drip line of trees indicated to remain.
3. Fill depressions caused by clearing and grubbing operations with satisfactory soil material, unless further excavation or earthwork is indicated.
a. Place fill material in horizontal layers not exceeding 150 mm (6 inches) loose depth, and thoroughly compact each layer to a density equal to adjacent original ground.
F. Removal of Improvements: Remove existing above-grade and below-grade improvements as indicated and as necessary to facilitate new construction.
G. Abandonment or removal of certain underground pipe or conduits may be indicated on mechanical or electrical drawings and is included under work of related Division 15 and 16 Sections. Removing abandoned underground piping or conduits interfering with construction is included under this Section, except as indicated to be abandoned in-place.
H. Continue maintenance of erosion controls in compliance with the Storm
Water Pollution Prevention Plan until the work is completed and the threat of erosion is gone by either around surface stabilizer or lawn
“grow-in” is at 85% complete. Temporary erosion control devices shall not be removed until the area is certified as being stabilized by the
Qualified Inspector.
02 41 10 - 5
3.2 DEMOLITION
A. Completely demolish and remove buildings and structures, including all appurtenances related or connected thereto, as noted below:
1. As required for installation of new utility service lines.
2. To full depth within an area defined by hypothetical lines located
1500 mm (5 feet) outside building lines of new structures.
B. Debris, including brick, concrete, stone, metals and similar materials shall become property of Contractor and shall be disposed of by him daily, off the Cemetery Property to avoid accumulation at the demolition site. Materials that cannot be removed daily shall be stored in areas specified by the PROJECT ENGINEER / COR. Break up concrete slabs below grade that do not require removal from present location into pieces not exceeding 600 mm (24 inches) square to permit drainage.
Contractor shall dispose debris in compliance with applicable federal, state or local permits, rules and/or regulations.
C. In removing buildings and structures of more than two stories, demolish work story by story starting at highest level and progressing down to third floor level. Demolition of first and second stories may proceed simultaneously.
D. Remove and legally dispose of all materials, other than earth to remain as part of project work, from any trash dumps shown. Materials removed shall become property of contractor and shall be disposed of in compliance with applicable federal, state or local permits, rules and/or regulations. All materials in the indicated trash dump areas, including above surrounding grade and extending to a depth of 1500 mm
(5 feet) below surrounding grade, shall be included as part of the lump sum compensation for the work of this section. Materials that are located beneath the surface of the surrounding ground more than 1500 mm
(5 feet), or materials that are discovered to be hazardous, shall be handled as unforeseen. The removal of hazardous material shall be referred to Hazardous Materials specifications. Burning is not permitted on the property.
E. Remove existing utilities as indicated or uncovered by work and terminate in a manner conforming to the nationally recognized code covering the specific utility and approved by the PROJECT ENGINEER /
COR. When Utility lines are encountered that are not indicated on the drawings, the PROJECT ENGINEER / COR shall be notified prior to further work in that area.
02 41 10 - 6
F. Where electrical, mechanical, plumbing, fire protection, fire alarm, or security components or equipment are shown to be demolished, contractor shall demolish all piping, conduit, cables, ductwork, outlets, switches, local panels back to their point of origin. Demolition shall be done such that all national, state and local codes are met both in the process of demolition but also the finished work. As an example, demolition of electrical components shall be taken back to the panel where the circuit originates. Coordinate with the COR as necessary.
3.2 CLEAN-UP
A. On completion of work of this section and after removal of all debris, leave site in clean condition satisfactory to PROJECT ENGINEER / COR.
Clean-up shall include off the Cemetery Property disposal of all items and materials not required to remain property of the Government as well as all debris and rubbish resulting from demolition operations.
CAST-IN-PLACE CONCRETE 03 30 00 - 1
SECTION 03 30 00
CAST-IN-PLACE AND PRE-
CAST CONCRETE
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section specifies cast-in place concrete for concrete repairs of thickness exceeding three inches, including formwork, reinforcement, concrete materials, mixture design, placement procedures, and finishes, for the following:
1. Slabs-on-grade including concrete sidewalks.
2. Concrete foundations.
B. This Section also specifies pre-cast concrete requirements, which shall meet (or exceed) the requirements in this specification section.
1.3 DEFINITIONS
A. Cementitious Materials: Portland cement alone or in combination with one or more of the following: blended hydraulic cement, fly ash and other pozzolans, ground granulated blast-furnace slag, and silica fume; subject to compliance with requirements.
1.4 SUBMITTALS
A. Product Data: For each type of product indicated.
B. Design Mixtures: For each concrete mixture. Submit alternate design mixtures when characteristics of materials, Project conditions, weather, test results, or other circumstances warrant adjustments.
CAST-IN-PLACE CONCRETE 03 30 00 - 2
1. Indicate amounts of mixing water to be withheld for later addition at Project site.
C. Steel Reinforcement Shop Drawings: Placing drawings that detail fabrication, bending, and placement. Include bar sizes, lengths, material, grade, bar schedules, stirrup spacing, bent bar diagrams, bar arrangement, splices and laps, mechanical connections, tie spacing, hoop spacing, and supports for concrete reinforcement.
D. Formwork Shop Drawings: Prepared by or under the supervision of a qualified professional engineer detailing fabrication, assembly, and support of formwork.
1. Shoring and Reshoring: Indicate proposed schedule and sequence of stripping formwork, shoring removal, and installing and removing reshoring.
E. Material Certificates: For each of the following, signed by manufacturers:
1. Cementitious materials.
2. Admixtures, including compatibility certification.
3. Form materials and form-release agents.
4. Steel reinforcement and accessories.
5. Fiber reinforcement.
6. Floor and slab treatments.
7. Bonding agents.
8. Semirigid joint filler.
9. Joint-filler strips.
1.5 QUALITY ASSURANCE
A. Installer Qualifications: A qualified installer who employs on Project personnel qualified as ACI-certified Flatwork Technician and Finisher and a supervisor who is an ACI-certified Concrete Flatwork Technician.
B. Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products and that complies with ASTM C 94/C 94M requirements for production facilities and equipment.
1. Manufacturer certified according to NRMCA's "Certification of
Ready Mixed Concrete Production Facilities."
C. Testing Agency Qualifications: An independent agency, acceptable to authorities having jurisdiction, qualified according to ASTM C 1077 and ASTM E 329 for testing indicated, as documented according to
ASTM E 548.
1. Personnel conducting field tests shall be qualified as ACI
Concrete Field Testing Technician, Grade 1, according to ACI CP- 01 or an equivalent certification program.
CAST-IN-PLACE CONCRETE 03 30 00 - 3
2. Personnel performing laboratory tests shall be ACI-certified
Concrete Strength Testing Technician and Concrete Laboratory Testing Technician - Grade I. Testing Agency laboratory supervisor shall be an ACI-certified Concrete Laboratory Testing Technician - Grade II.
D. Source Limitations: Obtain each type or class of cementitious material of the same brand from the same manufacturer's plant, obtain aggregate from one source, and obtain admixtures through one source from a single manufacturer.
E. ACI Publications: Comply with the following unless modified by requirements in the Contract Documents:
1. ACI 301, "Specification for Structural Concrete," Sections 1 through 5.
2. ACI 117, "Specifications for Tolerances for Concrete Construction and Materials."
F. Concrete Testing Service: Engage a qualified independent testing agency to perform material evaluation tests and to design concrete mixtures.
G. For the purposes of this Specification, all concrete is considered to be “exposed to public view”.
H. The Contractor shall keep the following references at the project site:
1. ACI 301 (latest edition) “Specification for Structural Concrete for Buildings”.
2. ACI 305R “Hot Weather Concreting”.
3. ACI 306.1 “Cold Weather Concreting”.
1.6 DELIVERY, STORAGE, AND HANDLING
A. Steel Reinforcement: Deliver, store, and handle steel reinforcement to prevent bending and damage. Avoid damaging coatings on steel reinforcement.
PART 2 - PRODUCTS
2.1 FORM-FACING MATERIALS
A. Smooth-Formed Finished Concrete: Form-facing panels that will provide continuous, true, and smooth concrete surfaces. Furnish in largest practicable sizes to minimize number of joints.
1. Plywood, metal, or other approved panel materials.
CAST-IN-PLACE CONCRETE 03 30 00 - 4
B. Rough-Formed Finished Concrete: Plywood, lumber, metal, or another approved material. Provide lumber dressed on at least two edges and one side for tight fit.
C. Chamfer Strips: Wood, metal, PVC, or rubber strips, 3/4 by 3/4 inch, minimum.
D. Rustication Strips: Wood, metal, PVC, or rubber strips, kerfed for ease of form removal.
E. Form-Release Agent: Commercially formulated form-release agent that will not bond with, stain, or adversely affect concrete surfaces and will not impair subsequent treatments of concrete surfaces.
1. Formulate form-release agent with rust inhibitor for steel form-facing materials.
F. Form Ties: Factory-fabricated, removable or snap-off metal or glass-fiber-reinforced plastic form ties designed to resist lateral pressure of fresh concrete on forms and to prevent spalling of concrete on removal.
1. Furnish units that will leave no corrodible metal closer than 1 inch to the plane of exposed concrete surface.
2. Furnish ties that, when removed, will leave holes no larger than
1 inch in diameter in concrete surface.
3. Furnish ties with integral water-barrier plates to walls indicated to receive dampproofing or waterproofing.
2.2 STEEL REINFORCEMENT
A. Reinforcing Bars: ASTM A 615/A 615M, Grade 60, deformed.
B. Low-Alloy-Steel Reinforcing Bars: ASTM A…