36C78618B0355-002.docx

DOCX document 43 KB Posted

Attached to
Construction of 4x4 Cremains Section CS2 at Massachusetts National Cemetery
Solicitation number
36C78618B0355
Issued by

About this file

36C78618B0355 SOW-818-MM18-1_SOW_BidSet_May3.2018.rjh.docx

View the file

Other files

File Type Posted
36C78618C0227-000.docx DOCX document
36C78618B0355-0002000.docx DOCX document
36C78618B0355-00001000.docx DOCX document
36C78618B0355-001.docx DOCX document
36C78618B0355-003.pdf PDF
36C78618B0355-004.pdf PDF
36C78618B0355-000.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Number 818-MM18-01 Construction of New 4’ x 4’ Cremains Section CS2 at

(818) Massachusetts National Cemetery

Request for Bids

Project Location: MASSACHUSETTES NATIONAL CEMETERY (818)

Project Title: Construction of New 4’ x 4’ Cremains Section CS2

Project Number: 818-MM18-01

Statement of Work Summary: (May 3, 2018)

I. GENERAL WORK SUMMARY

A. The Contractor shall furnish all tools, labor, materials, equipment, services, and professional design services to perform work described within this Statement of Work, Technical Specification, and on the Drawings identified as “Construction of New 4’ x 4’ Cremains Section CS2” Drawing Number 818-MM18-01-001 “Site Plan / Project Location”, Drawing Number 818-MM18-01-002 “Section CS2 Layout Plan”, and Drawing Number 818-MM18-01-003 “Detail Sheet” dated November 3, 2017 at the Massachusetts National Cemetery (818) located off of Connery Ave. in Bourne, MA.

B. The Project Drawings indicate the installation of (1,000) 4’ x 4’ Cremains Grave sites within the proposed Section CS2. The work consists in general of providing “Existing Conditions” and “Final Grading Plan”, design layout and supporting calculations of the Irrigation System, soil excavation, hauling and stockpiling on site, grading, placement of monument markers, connection and installation of irrigation piping, valves and fittings, testing, field training, finish grading, installation of a “Watering Station”, placement of sod, stabilization of earthwork, and other related work contained in this Statement of Work, the Drawings, Technical Specifications, and the Contract Documents.

II. SCOPE OF WORK

A. All Bidders are strongly encouraged to inspect the site where work is to be performed and to satisfy his or her self, regarding all general and local conditions that may affect the cost of contract performance. The Contractor / Bidder shall evaluate the Project area and existing layout of Section CS1 and the existing irrigation system.

B. The Contractor shall provide all labor, equipment, material, professional design services, and supervision necessary to Develop a new in ground cremation section to accommodate one thousand (1,000) 4’ x 4’ burial sites in the area shown on the Attachment Drawings “818-MM18-01-001”. The Project Area is approximately 1 acre. The burial area should not only be functional, but also provide visitors a serene and dignified experience.

C. The Contractor shall provide and install Control Markers on a 60’ x 60’ grid as shown on the Drawings. Control marker types and details are shown on Drawing 818-MM18-01-003. The Contractor will be required to submit Shop Drawings and other submittals as part of this work regarding Control Markers. The Control Markers shall be set at depth and finished grade as shown on the Drawings.

D. The Contractor shall provide all hydraulic calculations, design layout, material, equipment, and labor to connect and extend the existing irrigation system that feeds Section CS1 so that it will feed proposed Section CS2. The General alignment of the irrigation lines will be placed in the center of the isles as shown on the Drawings.

E. The Contractor shall establish turf in the burial area of Section CS2 and the surrounding area. The Sodding Area must be cleared of all roots, limbs, large rocks, and other vegetation. The Sodding Area shall be top dressed with a minimum of 4 inches of topsoil to facilitate turf establishment and the placement of sodding.

F. The Contractor shall provide Electronic “As-Built” Drawings of all the improvements.

III. PRE-PROPOSAL REQUIREMENTS

A. Contractor / Bidder is strongly encouraged to visit the project site and inspect the project area prior to submitting a proposal to adequately understand the full scope of work and all requirements. The Contractor / Bidder is required to submit any questions or clarifications prior to request for information deadline. In no event, shall failure to properly inspect the site constitute grounds for a claim after Award.

B. When planning to conduct a site visit / inspection at the Massachusetts National Cemetery, YOU MUST CONTACT one of the following National Cemetery Administration personnel to make your arrangements. Arrangements should be made at least one week in advance of the site visit:

Cemetery POC(s):

Richard Wallace, Acting Cemetery Director (508)-563-7113 x107 Richard.wallace1@va.gov

Technical Information:

Michael Carcanague, NAD -Supervisory Engineer (

215) 381-3787 (ext. 4054) or Michael.Carcanague@va.gov

C. The Contractor / Bidder acknowledges by submitting the Bid that it has taken steps reasonably necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost, including but not limited to:

1.The conditions bearing upon transportation, disposal, handling, and storage of materials;
2.The availability of labor, water, electric power, and roads;
3.Uncertainties of weather, river stages, tides, or similar physical conditions at the site; 4.The conformation and conditions of the ground; and
5.The character of equipment and facilities needed preliminary to and during work performance.

VI. FEE SCHEDULE

A. Fee Schedule Form:

DESCRIPTION
QTY
UNIT
FEE
Development and Construction of New Cremains Section CS2 to include all labor, equipment, material, designs, plan submissions, calculations, and supervision necessary to perform work described in the VA NCA Statement of Work and Drawings for Project 818-MM18-01 for the Fixed Price provided.
1
JOB
$ _____________
TOTAL FEE ($)
$ ________________________

TOTAL FEE (WRITTEN):

B. Duration:

The term of the Contract shall be ninety (90) days from date of Notice to Proceed. The Contractor shall complete all work subject to all terms, conditions, provisions and schedules of the Contract.