The document is a Technical Questions and Responses Tracking Sheet for Phase I of a Design-Build parking garage project in Phoenix, Arizona, solicitation number 36C77625R0062. The document captures four key questions and answers from potential contractors regarding the project, including details about the construction timeline, proposal submission requirements, and formatting specifications. Key details include an expected construction start date of August 2026, proposal questions due on July 17th, and full proposals due on August 8th. The VA will accept Microsoft font submissions in Times New Roman, Calibri, or Aptos, and confirmed that only Phase I proposal requirements (Performance Plan, Bonding, CPARs/PPQs) are due on the specified date, with a potential site visit to follow if the contractor is accepted.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL QUESTIONS AND SOLICITATION #: 36C77625R0062
RESPONSES TRACKING SHEET – PHASE I PROJECT TITLE: 644-237 – Construct Parking Garage D-B – Phoenix, AZ
# CONTRACTOR QUESTION VA RESPONSE
1 If known, what is the expected start date for construction?
Based on the period of performance and the estimated award timeframe for this project, the expected start date for construction is August 2026.
This is subject to change as we are still in the solicitation phase and have not yet awarded the contract or started the design work.
2 Microsoft has updated their default font twice since "Times New Roman". The new default font set is now "Aptos" with the previous being "Calibri".
Will the government please allow offerors to submit proposals using any of the three recent Microsoft standard fonts?
("Times New Roman", "Calibri", or "Aptos")
Yes, we will accept all three fonts for this solicitation.
3 Could you please confirm if the Phase 1 proposal is due July 17th or August 8?
July 17th is when Phase I questions are due. August 8th is when proposals are due
4 So only the Phase 1 proposal requirements (PP, Bonding, Cpars/PPQs) are due 8/8. Site visit to follow should we be accepted?
Yes, this is correct. Also, please refer to the solicitation document to make sure that you are sending all of the requirements needed for Phase I.
File details come from the government source that posted it. Updated .