657-21-709 - Addendum No. 1 - 2025 04 23.pdf
PDF 23 MB Posted
- Attached to
- Y1DA--EHRM Infrastructure Upgrades Data Center Construction - St. Louis JB - Project 657-21-709JB Federal contract opportunity
- Solicitation number
- 36C77625B0008
About this file
This document is an Addendum to a federal contract solicitation for the VA EHRM Infrastructure Upgrades Data Center Construction project at Jefferson Barracks VA Medical Center in St. Louis, Missouri. The addendum, dated 04/11/2025, provides updates to various technical drawings and specifications for the project, including modifications to architectural, structural, mechanical, and electrical plans for Building 56.
Key changes include updates to roof plans, mechanical piping relocations, electrical conduit routing, and the addition of several specification sections such as roofing preparation, TPO roofing, firestopping, hollow metal frames, interior wood doors, door hardware, seismic requirements for non-structural components, and commissioning of electronic safety and security systems. The project involves relocating the existing data center from Building 1 to Building 56, with infrastructure improvements spanning electrical systems, HVAC, space construction, fire suppression, communication infrastructure, physical security, and fiber connectivity.
View the file
Other files for this federal contract opportunity
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Spees Design Build
23830 Pacific Highway S. Suite 300
Kent, WA 98032
P: (206) 590-2118
F: (206) 590-2118
04/11/2025 Page 1 of 3
ADDENDUM 1
Client Name: U.S. Department of Veteran Affairs Date Initiated: 04/11/2025 Project: VA MO JB EHRM IU Data Center
Project No: 657-21-709JB From: Dan Schwab, PM To: Kyle Florian: Kyle.Florian@va.gov
ADDENDUM 1 Summary of Adjustments:
General Sheet 002:
o Updated Sheet Index General Specifications:
o Update:
Seals Page
Architectural Drawings:
o 56A-110: Updated roof plan for additional pad and relocated Mechanical Units.
Architectural Specifications:
o ADD Specifications:
07 01 50.19: Prepare for Roofing 07 54 23: TPO Roofing 07 84 00: Fire Stopping 08 11 13: Hollow Metal Frames 08 14 00: Interior Wood Doors 08 71 00: Door Hardware 13 05 41: Seismic Requirements for Non-Structural Components
Structural Drawings:
o Add Sheets:
S-001: Structural General Notes S-002: Abbreviations and Symbols S-101: Building 56 Roof Plan
Detail C1 – Roof Plan Detail C7 – Development and Lap Splice Length Schedules – Concrete Detail F1 – Section – Equipment Pad Detail A7 – Section – Equipment Pad
Structural Specifications:
o Add Specifications:
03 30 00: Cast In Place Concrete Mechanical Drawings:
o Drawing Update:
MP101: Refrigerant Piping Relocation to support relocation of Concrete Curbing
Effected Equipment:
• 56-CU-05-102
• 56-CU-04-102
• 54-HP-01-102
Spees Design Build
23830 Pacific Highway S. Suite 300
Kent, WA 98032
P: (206) 590-2118
F: (206) 590-2118
04/11/2025 Page 2 of 3
• 54-HP-02-102
MP102: Moved House Keeping Pad to center over grid line 2 approximately 30’ east from the original location.
Effected Equipment:
• 54-HP-01-102
• 54-HP-02-102
Electrical Drawings
- Drawing Update:
o Sheet E-101:
Updated conduit routing for new mechanical equipment placement.
Revised Keynote 2 and added Keynote 4 for additional clarity.
Revised conduit tags and continuations from BLDG 56 to fuel tank.
o Sheet E-102:
Added convenience receptacles to plan for clarity.
Revised conduit routing from BLDG 56 for clarity per the revision on sheet E-101.
Corrected fuel polishing system equipment tag.
Added Keynote 4 for above ground fuel tank.
o Sheet ED101:
Revised Keynote 1 for clarity.
o Sheet ED102:
Added Keynotes 6 and 7 for emergency push button to coordinate with Keynotes on sheet EP101.
o Sheet EL101:
Revised lighting circuit to correct panel.
Added ‘E’ designation for emergency backed lights.
o Sheet EP101:
Removed Keynote 6 from select emergency push buttons to coordinate with
Keynotes on sheet ED102.
Add Keynote 6 to select emergency push buttons for clarity.
o Sheet EP102:
Revised Unistrut-mounted disconnects, convenience receptacle and feeder locations for revised mechanical equipment placement.
o Sheet E-503:
Revised detail 4 regarding the GFCI receptacle for clarity.
o Sheet EP612:
Revised circuit breaker sizes for transformers “56-TX-PNL-A” and “56-TX-PNL-B”.
o Sheet E-701:
Revised luminare schedule notes.
Revised conduit and wire sizes for transformers “56-TX-PNL-A” and “56-TX-PNL-B”.
Added reference to convenience receptacles as added on sheet E-102.
o Sheet E-703:
Revised circuit breaker sizes for transformers “56-TX-PNL-A” and “56-TX-PNL-B”.
Corrected “56-SWBD-UPS-A” and “56-SWBD-UPS-B” panelboard names.
Electrical Specifications:
o Add Specifications:
28 08 00: Commissioning of Electronic Safety and Security Systems
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of
Construction and Facilities
Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
SPEES DESIGN BUILD
23830 PACIFIC HIGHWAY S. SUITE 203
KENT, WA 98032
/0
/2
:3
:0 a m
B
IM
/6
-2
-7
J B
V A
M O
J B
E H
R M
I U
D a ta
C e n te r/ V
A S
T L
D
C
A
R
S D
B .r v t
G-002
DRAWING INDEX
LT MA
100% CONSTRUCTION
DOCUMENTS
05/10/2024
657-21-709JBSTL JB DATA CENTER EHRM
INFRASTRUCTURE UPGRADES
JEFFERSON BARRACKS, MO
ST. LOUIS, MO 63125
GENERAL
G-001 COVER
G-002 DRAWING INDEX
CIVIL
CS100 SITES IMPROVEMENTS PLAN
CS500 SITE DETAILS
CU500 FIBER TERMINATION DETAILS
ARCHITECTURAL
56A-100 BLDG 56 - MCR PLAN AND DEMO PLAN
56A-101 BLDG 56 MCR RCP AND DEMO RCP
56A-110 BLDG 56 - ROOF PLAN
A-001 ARCHITECTURAL SYMBOLS & ABBREVIATIONS
AS101 ICRA DETAILS
SHEET # SHEET NAME
DRAWING INDEX
Revisions: Date:
STRUCTURAL
S-001 S-002 S-101
STRUCTURAL GENERAL NOTES
ABRREVIATIONS AND SYMBOLS
BLDG 56 - ROOF PLAN
MECHANICAL
FH100 DATA CENTER - FIRE PROTECTION PLAN
M-001 MECHANICAL SYMBOLS AND ABBREVIATIONS
M-500 MECHANICAL DETAILS
M-600 MECHANICAL SCHEDULES
M-700 MECHANICAL CONTROLS I
M-701 MECHANICAL CONTROLS II
MD100 DATA CENTER - DEMO RCP
MD101 DATA CENTER - DEMO FLOOR PLAN
MH100 DATA CENTER - RCP
MP100 DATA CENTER - MECHANICAL PIPING
MP101 FIRST FLOOR PLAN - MECHANICAL PIPING
MP102 ROOF PLAN - MECHANICAL PIPING
MP103 GENERATOR FUEL PIPING - MECHANICAL PIPING
P-001 PLUMBING - SCHEDULES, SYMBOLS AND ABBREVIATIONS
P-100 DATA CENTER - FOUNDATION PLAN
ELECTRICAL
E-001 ABBREVIATIONS, GENERAL NOTES, AND SHEET INDEX
E-002 ELECTRICAL LEGENDS
E-101 BLDG 56 - LEVEL 00 - ELECTRICAL PLAN
E-102 GENERATOR FUEL TANK ELECTRICAL PLAN
ED101 DATA CENTER - LIGHTING DEMOLITION PLAN
ED102 DATA CENTER - POWER DEMOLITON PLAN
ED103 DATA CENTER - TELECOMMUNICATIONS DEMOLITION PLAN
ED104 DATA CENTER - TELECOMMUNICATIONS OVERHEAD DEMOLITION PLAN
EL101 DATA CENTER - LIGHTING PLAN
EP101 DATA CENTER - POWER PLAN
EG101 DATA CENTER - GROUNDING PLAN
EP102 BLDG 56 - ROOF - ELECTRICAL PLAN
ET101 DATA CENTER - TELECOMMUNICATIONS PLAN
ET102 DATA CENTER - TELECOMMUNICATIONS OVERHEAD PLAN
EP401 BLDG 56 - LEVEL 00 - ENLARGED ELECTRICAL PLANS
EP402 BLDG 56 - LEVEL 00 - ENLARGED ELECTRICAL PLANS
E-501 ELECTRICAL DETAILS
E-502 ELECTRICAL DETAILS
E-503 ELECTRICAL DETAILS
E-504 ELECTRICAL DETAILS
E-505 ELECTRICAL DETAILS
E-506 TELECOMMUNICATIONS DETAILS
E-507 TELECOMMUNICATIONS DETAILS
E-508 TELECOMMUNICATIONS DETAILS
EP601 BLDG 56 - ONE-LINE DIAGRAM - EXISTING
EP611 BLDG 56 - ONE-LINE DIAGRAM - REVISED (1 OF 2)
EP612 BLDG 56 - ONE-LINE DIAGRAM - REVISED (2 OF 2)
E-701 ELECTRICAL SCHEDULES
E-702 ELECTRICAL SCHEDULES
E-703 ELECTRICAL SCHEDULES
Addenda 1 4/11/2025
DanSchwab Snapshot
28' - 3 3/8"
NEW CONCRETE PAD,
SEE STRUCTURAL
SHEETS
WALKWAY [PAD
SPLICE TAP
VAPOR BARRIER
SEE PLANS FOR ROOF TYPE
WALKWAY PAD
SPLICE TAP
2% M
IN
S
LO
P E
(P A
R A
LL
E
L W
S
P
LI
C E
T A
P
A
NOTE:
PROVIDE INTEGRAL CAPE PLATE AT
TOP OF ALL EXPOSED STEEL
PIPE PENETRATION
STAINLESS STEEL BAND CLAMP
WATER BLOCK MASTIC
ROOF FLASHING
SINGLE PLY ROOF SYSTEM
REFER TO PLANS AND SECTIONS
FOR WALL AND ROOF TYPE, TYP.
VAPOR BARRIER
/1
M
IN
M
IN
. 2" MIN.
3" MIN.
CL
PIPE DIA
EQUIPMENT UNIT
GROMMETED FASTENER @ 12" O.C.
METAL EXTENDER PIECE AS REQUIRED
TPO FLASING ADHERED TO
ACCEPTABLE SUBSTRATE
TPO SECUREMENT, INSTALL PER
MANUFACTURERS SPECIFICATION
HOT-AIR
WELD MEMBRANE
ROOF BOARD (AS REQUIRED)
INSULATION SECURED AS REQUIRED
VAPOR RETARDER (AS REQUIRED)
NOTES:
1. METAL EXTENDER PIECE IS REQUIRED IF EXISTING
COUNTERFLASHING IS CONTAMINATED AND
ORCOUNTERFLASHING FASCIA IS LESS THAN 4" WIDE,
FASTENED 12" O.C. WITH GROMMETTED FASTENER.
2. METAL COUNTERFLASHING IS TO BE INSTALLED TO MEET
LOCAL CODES AND REQUIREMENTS.
STRUCTURAL DECK
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of
Construction and Facilities
Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
SPEES DESIGN BUILD
23830 PACIFIC HIGHWAY S. SUITE 203
KENT, WA 98032
/9
/2
:4
:5
P M
B
IM
/6
-2
-7
J B
V A
M O
J B
E H
R M
I U
D a ta
C e n te r/ V
A S
T L
D
C
A
R
S D
B .r v t
56A-110
BLDG 56 - ROOF PLAN
LT DS
100% CONSTRUCTION
DOCUMENTS
05/10/2024
657-21-709JBSTL JB DATA CENTER EHRM
INFRASTRUCTURE UPGRADES
JEFFERSON BARRACKS, MO
ST. LOUIS, MO 63125
1/8" = 1'-0"
ROOF PLAN
1 1/2" = 1'-0"
MECH UNIT ROOF WALK PAD DETAIL
1 1/2" = 1'-0"
ROOF PIPE PENETRATION DETAIL
Revisions: Date:
Addenda 1 4/11/2025
1 1/2" = 1'-0"
ROOF CURB FLASHING
DominicDitschler Image
WSP USA Inc.
Suite 300
Federal Way, WA 98003-2600
TEL: (206) 431-2300
FAX: (206) 431-2250
33301 9th Avenue South
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
STL JB DATA CENTER EHRM
INFRASTRUCTURE UPGRADES
JEFFERSON BARRACKS, MO
ST. LOUIS, MO 63125
657-21-701JB
SPEES DESIGN BUILD
23830 PACIFIC HIGHWAY S. SUITE 203
KENT, WA 98032
(206) 590-2118
RAY SPEES S-001
STRUCTURAL GENERAL NOTES
DDV JKM
ADDENDUM 1
04/11/2025
MATERIAL SPECIFIC STANDARDS ARE LISTED IN THE RESPECTIVE MATERIAL SECTION.
1. VA SEISMIC DESIGN REQUIREMENTS, H-18-8, JULY 1ST 2023
2. 2021 INTERNATIONAL BUILDING CODE (IBC) WITH STATE AND LOCAL AMENDMENTS
CODES AND STANDARDS
REFERENCES:
ASCE 7-16 MINIMUM DESIGN LOADS FOR BUILDINGS AND OTHER STRUCTURES
VA STRUCTURAL DESIGN MANUAL PG-18-10 OCTOBER 1ST 2022, REVISED JULY 1, 2023
DESIGN LOADS
WEIGHT OF STRUCTURAL ELEMENTS AND PERMANENT FIXED EQUIPMENT.
DEAD LOADS
1. CONFLICTS BETWEEN THE DRAWINGS AND SPECIFICATIONS MUST BE BROUGHT TO THE ATTENTION OF THE CONTRACTING OFFICER AND STRUCTURAL ENGINEER OF RECORD (SER) IN WRITTEN FORM AND RESOLVED BEFORE PROCEEDING WITH AFFECTED WORK.
2. STRUCTURAL DRAWINGS REPRESENT THE COMPLETED STRUCTURE. THE CONTRACTOR IS RESPONSIBLE FOR THE MEANS AND METHODS NECESSARY TO COMPLETE THE WORK, FOR JOB SITE SAFETY AND FOR COORDINATING WITH OTHER DISCIPLINES AS REQUIRED.
3. THE CONTRACTOR IS RESPONSIBLE FOR THE ERECTION PROCEDURE AND SEQUENCING TO ENSURE STABILITY OF THE STRUCTURE DURING CONSTRUCTION. PROVIDE SHORING, BRACING, AND FALSEWORK AS NEEDED TO PROTECT THE STRUCTURE THROUGHOUT CONSTRUCTION.
4. ERECTION AIDS FOR FACILITATING CONSTRUCTION NOT SHOWN IN THESE DRAWINGS MUST BE REMOVED AND ELEMENTS RESTORED TO ITS ORIGINAL
DESIGN INTENT SHOWN PER THESE DRAWINGS.
5. STRUCTURAL DRAWINGS SHOW GENERAL AND TYPICAL DETAILS OF CONSTRUCTION. WHERE SPECIFIC CONDITIONS ARE NOT SHOWN, DETAILS OF
SIMILAR TYPE AND CHARACTER MAY BE USED BUT REQUIRE APPROVAL FROM THE SER.
6. TYPICAL DETAILS MAY NOT BE REFERENCED FROM THE PLANS BUT APPLY FOR THE CONDITIONS AS DESCRIBED BY THE DETAIL.
7. CONTRACTOR-INITIATED CHANGES REQUIRE APPROVAL FROM THE SER.
8. FOR A CONTRACTOR REQUESTED DESIGN REVISION, THE PROPOSED ALTERNATIVE MUST BE SUBMITTED TO THE CONTRACTING OFFICER FOR REVIEW AND APPROVAL BY THE SER. THE SUBMITTAL MUST INCLUDE DRAWINGS, STRUCTURAL DETAILS AND RELATED CALCULATIONS, STAMPED AND SIGNED BY A PROFESSIONAL ENGINEER LICENSED TO PRACTICE IN THE JURISDICTION OF THE PROJECT LOCATION. CALCULATIONS MUST DEMONSTRATE COMPLIANCE WITH THE CODES AND DESIGN REQUIREMENTS LISTED PER THESE DRAWINGS; AND THAT THE ALTERNATIVE DESIGN DOES NOT ADVERSELY
AFFECT THE STRUCTURE SHOWN IN THESE DRAWINGS.
9. CONTRACTOR MUST COORDINATE THESE DRAWINGS WITH THE DRAWINGS OF THE OTHER DISCIPLINES AND SPECIFICATIONS FOR ADDITIONAL INFORMATION NOT SHOWN ON THE STRUCTURAL DRAWINGS. EXAMPLES INCLUDE EMBEDDED ANCHORS, SLEEVES AND INSERTS, MISCELLANEOUS ATTACHMENT DETAILS, FLOOR FINISHES, DOOR THRESHOLDS, SLOPES TO DRAINS, OPENINGS IN STRUCTURAL ELEMENTS, ETC.
10. VERIFY DIMENSIONS AND DETAILS PRIOR TO FABRICATION AND CONSTRUCTION. THIS INCLUDES COORDINATING THE SIZE AND LOCATION OF OPENINGS THROUGH STRUCTURAL ELEMENTS WITH THE RESPECTIVE SUBCONTRACTOR, AS WELL AS COORDINATING INSERTS AND ATTACHMENTS FOR USE BY
OTHER TRADES.
11. NO PIPES OR DUCTS MAY BE PLACED IN STRUCTURAL MEMBERS UNLESS DETAILED BY THE STRUCTURAL PLANS OR APPROVED BY THE SER.
12. DIMENSIONS MUST NOT BE SCALED FROM THE DRAWINGS.
13. PROVIDE SUBMITTALS AND (FABRICATION, AND ERECTION, ETC.) SHOP DRAWINGS FOR THE WORK SHOWN IN THESE DRAWINGS TO THE CONTRACTING OFFICE FOR APPROVAL FROM THE SER. WORK MUST NOT PROCEED WITHOUT REVIEW AND APPROVAL BY THE SER.
14. SUBMIT A DETAILED PLAN OF THE CONSTRUCTION INCLUDING A DESCRIPTION OF DEMOLITION, CONSTRUCTION METHODS, ERECTION SEQUENCING, METHODS OF STABILIZING THE STRUCTURE, SHORING LAYOUT, ELEMENT SIZES, CONNECTIONS AND ACCESSORIES WITH SUPPORTING CALCULATIONS STAMPED AND SIGNED BY A REGISTERED PROFESSIONAL ENGINEER, TO THE CONTRACTING OFFICER FOR REVIEW AND APPROVAL PRIOR TO BEGINNING
WORK.
15. BY SUBMITTING FOR ENGINEER’S REVIEW, THE CONTRACTOR CONFIRMS THE ACCURACY OF THE SUBMITTALS FOR DIMENSIONS, QUANTITIES, ELEMENT SIZES, CONSTRUCTION MATERIALS, FIELD MEASUREMENTS AND THAT THE CONTENTS HAVE BEEN REVIEWED FOR MEANS, METHODS, AND OPERATIONS
OF CONSTRUCTION, AND FOR ITS ADHERENCE TO SAFETY PROTOCOLS AT THE SITE.
16. SHOP DRAWING REVIEW DOES NOT RELIEVE THE CONTRACTOR FROM HAVING SOLE RESPONSIBILITY FOR THE ACCURACY OF ELEMENT SIZES, DIMENSIONS AND DETAILS. SUCH REVIEW DOES NOT CONSTITUTE ACCEPTANCE BY THE ENGINEER OF THE CORRECTNESS OR ADEQUACY OF SUCH SUBMITTALS, NOR IS A WARRANTY THAT THE SUBMITTALS SATISFY THE REQUIREMENTS OF THE CONTRACT.
17. SHOP DRAWINGS MUST BE SUBMITTED TO THE CONTRACTING OFFICER FOR REVIEW AND APPROVAL PRIOR TO FABRICATION. UNLESS NOTED
OTHERWISE, PROVIDE SHOP DRAWINGS FOR:
a. DEFORMED BAR REINFORCING LAYOUT FOR CONCRETE AND MASONRY.
GENERAL CONDITIONS
1. REFERENCES:
A. ACI 301-20 SPECIFICATIONS FOR CONCRETE CONSTRUCTION
B. ACI 315R-18 DETAILS AND DETAILING CONCRETE CONSTRUCTION
C. ACI 318-19 BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE
D. ACI 347-14 GUIDE TO FORMWORK FOR CONCRETE
1. CONCRETE WORK MUST CONFORM TO ACI 301. FORMWORK MUST CONFORM TO ACI 347.
2. MINIMUM CONCRETE PROPERTIES AT 28-DAYS PER THE FOLLOWING TABLE.
3. FLEXURAL STRENGTH FOR SLAB-ON-GRADE CONCRETE 650 PSI AT 90 DAYS .
4. SECTIONS AND DETAILS MAY NOT SHOW ALL REQUIRED DEFORMED BAR REINFORCEMENT FOR CLARITY. ADDITIONAL REINFORCEMENT MAY BE DESCRIBED
IN PLANS, SCHEDULES, NOTES, OR OTHER DETAILS, AS APPLICABLE.
5. COORDINATE FLOOR FINISHES, SLAB SLOPES & DEPRESSIONS, FLOOR DRAINS, CURBS, CONCRETE PADS, AND OTHER CONCRETE FEATURES IDENTIFIED IN
THE CONTRACT DOCUMENTS.
6. THE STRUCTURAL DRAWINGS DO NOT NECESSARILY SHOW ALL ITEMS EMBEDDED IN THE CONCRETE. COORDINATE AND PROVIDED EMBEDDED ITEMS AS SHOWN IN THE CONTRACT DOCUMENTS AND AS REQUIRED BY THE EQUIPMENT MANUFACTURERS, AS NEEDED.
7. NON-STRUCTURAL STEEL MEMBERS EMBEDDED IN CONCRETE MUST BE HOT-DIP GALVANIZED OR PAINTED. DAMAGED COATINGS OF EMBEDDED ITEMS MUST
BE REPAIRED PRIOR TO CASTING CONCRETE.
8. PROVIDE 3/4" CHAMFER ON EXPOSED CONCRETE EDGES UNLESS NOTED OTHERWISE.
CAST IN PLACE CONCRETE
1. REFERENCES:
A. ACI 301-20 SPECIFICATIONS FOR CONCRETE CONSTRUCTION
B. ACI SP-66-04 ACI DETAILING MANUAL
C. ACI 315R-18 DETAILS AND DETAILING CONCRETE CONSTRUCTION
D. AWS D1.4 2018 STRUCTURAL WELDING CODE – REINFORCING STEEL
2. STEEL REINFORCEMENT MUST CONFORM TO:
3. PROVIDE BAR SUPPORTS AND SPACERS PER ACI 315 UNLESS NOTED OTHERWISE. DEFORMED BAR REINFORCEMENT AND INSERTS MUST BE SECURED IN- PLACE PRIOR TO PLACING CONCRETE. DO NOT PLACE REBAR MATS DIRECTLY AGAINST SOIL; REBAR MATS ADJACENT TO SOIL OR OVER MUD SLABS MUST BE
SUPPORTED BY CHAIRS, DO NOT LIFT INTO PLACE DURING POURING.
4. UNLESS INDICATED OTHERWISE, REINFORCEMENT BARS ARE CONTINUOUS AND MUST BE LAP SPLICED OR COUPLED WITH MECHANICAL CONNECTORS. LAP
LENGTH NOTES:
A. SEE DEVELOPMENT AND LAP SPLICE LENGTH SCHEDULES FOR REINFORCEMENT DETAILS.
B. LAP SPLICE LENGTH MUST BE USED FOR THE LARGER BAR SIZE WHEN BAR SIZE TRANSITIONS AT LAP.
C. OVERLAP WELDED WIRE LAYER REINFORCEMENT A LENGTH OF 1.5X WIRE DEVELOPMENT LENGTH OR ONE CROSSWIRE SPACING PLUS 2 INCHES, WHICHEVER IS LARGER.
D. MECHANICAL CONNECTORS MUST HAVE A MINIMUM CAPACITY OF 1.25 X YIELD STRENGTH OF THE BAR.
E. MECHANICAL CONNECTORS IN MEMBERS DESIGNATED AS PART OF THE SEISMIC-FORCE-RESISTING SYSTEM MUST HAVE A MINIMUM CAPACITY
EQUAL TO THE TENSILE STRENGTH OF THE BAR.
5. TYPE 1 MECHANICAL CONNECTORS MUST DEVELOP 125% OF THE YIELD STRENGTH (Fy) OF THE STRONGER OF THE TWO BAR BEING SPLICED. TYPE 2 MECHANICAL CONNECTORS MUST DEVELOP THE FULL TENSILE STRENGTH OF THE STRONGER OF THE TWO BARS BEING SPLICED. WHERE MECHANICAL CONNECTORS ARE USED IN LIEU OF LAP SPLICES, PROVIDE TYPE 2 MECHANICAL CONNECTORS EXCEPT WHERE TYPE 1 ARE PERMITTED AS INDICATED.
6. HEADED DEFORMED BARS (TERMINATORS) MUST BE INTEGRALLY FORMED OR THREADED DEVICES MEETING THE REQUIREMENTS OF ACI 318, SECTION 25.4.4.1.
7. UNLESS NOTED OTHERWISE ON THE DRAWINGS:
A. DEFORMED BAR COVER MUST CONFORM TO SPECIFIED CONCRETE COVER REQUIREMENTS OF ACI 318.
B. REINFORCEMENT MUST BE CONTINUOUS THROUGH CONSTRUCTION JOINTS
C. APPROVAL FROM SER REQUIRED BEFORE WELDING NON-ASTM A706 Gr. 60 REINFORCEMENT
D. APPROVAL FROM SER REQUIRED BEFORE FIELD BENDING REINFORCEMENT PARTIALLY EMBEDDED CONCRETE
E. MATCH DOWELS TO THE LARGER OF MULTIPLE BAR SIZES
8. DOWELS MUST BE SECURED WITH A RIGID TEMPLATE TO ENSURE SPLICE IS LOCATED INSIDE THE CONFINED REGION (REGION ENCLOSED BY SHEAR OR
HORIZONTAL REINFORCEMENT) OF CROSS-SECTION.
REINFORCING STEEL
CONDITION STANDARD AND GRADE MIN YIELD (KSI)
TYPICAL DEFORMED BAR ASTM A615 GR 60 60
LOCATION MIN 28-DAY
COMPRESSIVE
STRENGTH
(PSI)
FREEZING &
THAWING
EQUIPMENT PAD 4,500 (LIGHT WEIGHT) S0
SULFATE WATER
CONTACT
ACI 318, CH. 19 EXPOSURE CATEGORIES
CORROSION
PROTECTION
F2 W2 C1
MAX
WATER/CEME
NT RATIO
0.45
CEMENT
TYPE
II
NOMINAL MAX
AGGREGATE
SIZE
3/4"
POST INSTALLED ANCHOR IN CONCRETE
1. EXCEPT WHERE INDICATED ON THE DRAWINGS, POST-INSTALLED ANCHORS CONSIST OF THE FOLLOWING ANCHOR TYPES OR APPROVED EQUAL:
2. ANCHOR CAPACITY USED IN DESIGN MUST BE BASED ON THE TECHNICAL DATA PUBLISHED IN THE ICC APPROVAL REPORT. SUBSTITUTION REQUESTS MUST INCLUDE ICC ESR REPORT SHOWING COMPLIANCE WITH RELEVANT BUILDING CODE AND INSTALLATION CATEGORY AND BE APPROVED IN WRITING BY THE
CONTRACTING OFFICER FOR REVIEW AND APPROVAL BY THE SER PRIOR TO USE.
3. INSTALL ANCHORS PER THE MANUFACTURER INSTRUCTIONS, AS INCLUDED IN THE ANCHOR PACKAGING.
4. INSTALL ANCHORS IN ACCORDANCE WITH SPACING AND EDGE CLEARANCES INDICATED ON THE DRAWINGS.
5. EXISTING DEFORMED BAR REINFORCEMENT IN THE STRUCTURE MAY CONFLICT WITH SPECIFIC ANCHOR LOCATIONS. UNLESS NOTED OTHERWISE, THE CONTRACTOR MUST LOCATE THE POSITION OF THE EXISTING REINFORCING BARS AND AVOID CUTTING.
6. DRILLING, CORING, SAW-CUTTING, ETC. INTO CONCRETE SHALL MEET THE LATEST OSHA REGULATIONS FOR SILICA DUST EXPOSURE.
CONCRETE
SCREW
EXPANSION
ADHESIVE
UNDERCUT
CONDITION TYPE
HILTI KWIK HUS-EZ SCREW ANCHORS PER ICC ESR-3027
SIMPSON TITEN HD SCREW ANCHOR PER ICC ESR-2713
DEWALT WEDGE-BOLT+ PER ICC ESR-2526
HILTI KWIK-BOLT TZ2 ANCHOR PER ICC ESR-4266
SIMPSON STRONG BOLT 2 ANCHOR PER ICC ESR-3037
DEWALT POWER-STUD+ SD1 ANCHOR PER ICC ESR-2818
HILTI HIT-HY 200 ADHESIVE ANCHOR SYSTEM PER ICC ESR-3187
SIMPSON SET-XP ADHESIVE ANCHOR SYSTEM PER ICC ESR-2508
DEWALT PE1000+ ADHESIVE ANCHOR SYSTEM PER ICC ESR-2583
HILTI HDA-P UNDERCUT ANCHOR PER ICC ESR-1546
SIMPSON TORQ-CUT SELF UNDERCUTTING ANCHOR PER ICC ESR-2705
DEWALT CCU+ UNDERCUT ANCHOR CARBON STEEL PER ICC ESR-4810
ACCEPTABLE
ANCHORS
SPECIAL INSPECTION AND TESTING
1. SPECIAL INSPECTION AND TESTING MUST CONFORM TO SECTION 1704 OF THE INTERNATIONAL BUILDING CODE (IBC) AS AMENDED BY H-18-8.
2. ONE OR MORE QUALIFIED SPECIAL INSPECTION & TESTING AGENCIES MUST BE EMPLOYED TO PERFORM THE NECESSARY INSPECTION OF IBC SECTION 1705, AS APPLICABLE. QUALIFICATIONS FOR SPECIAL INSPECTION AND TESTING AGENCIES AND INSPECTORS MUST BE SUBMITTED TO THE CONTRACTING
OFFICER FOR REVIEW AND APPROVAL.
3. SPECIAL INSPECTOR QUALIFICATIONS MUST MEET THE REQUIREMENTS OF SPECIFICATION SECTION 01 45 35.
• FOR STATEMENT OF SPECIAL INSPECTION SEE PROJECT SPECIFICATIONS.
5. REPORTING ON SPECIAL INSPECTION AND TESTING MUST CONFORM TO IBC SECTION 1704.5 AND BE SUBMITTED TO THE CONTRACTING OFFICER WEEKLY , OR AS REQUIRED BY THE SPECIFICATIONS.
1. STRUCTURAL OBSERVATIONS MUST BE PERFORMED BY THE DESIGNATED REPRESENTATIVE BY THE GOVERNMENT, FOR THE FOLLOWING:
A. HOUSKEEPING PAD: PLACEMENT OF DEFORMED BAR REINFORCEMENT, BEFORE CONCRETE.
1. CONTRACTOR MUST NOTIFY CONTRACTING OFFICER 14 DAYS IN ADVANCE OF WHEN WORK IS EXPECTED TO COORDINATE THE DATE OF OBSERVATION.
2. STRUCTURAL OBSERVATION DOES NOT WAIVE THE RESPONSIBILITY OF SPECIAL INSPECTION REQUIREMENTS.
STRUCTURAL OBSERVATIONS
Revisions: Date:
DanSchwab Architect
ADDENDUM 1
DanSchwab Architect 04/11/2025
DanSchwab Architect
DanSchwab PolyLine
DanSchwab Text Box
INDICATES STEP FOOTING PER DETAIL
INDICATES STEP IN SLAB / DECK
INDICATES SLOPE IN SLAB / DECK
INDICATES APPROXIMATE SPOT ELEVATION
CENTERLINE
STRUCTURAL DRAWING SYMBOLS
S S
CL
SECTION OR ELEVATION CUT
SECTION, DETAIL, OR ELEVATION CALLOUT
DRAWING WHERE SECTION, DETAIL OR
ELEVATION IS SHOWN OR CALLED
FROM
TITLE
SCALE: X' = X'-XX"
PLAN
N XXXXX.XX
E XXXXX.XX
COORDINATES
GRID NO.XX
X x-xx
X x-xx
0.5%
SLOPE
WORK POINT
# PLAN REVISION
WP ##
ELEVATION OF COMPONENTS
T/XXXX
EL ##.#
x-xx
TITLE
SCALE: X' = X'-XX"
SECTION, DETAIL, OR ELEVATIONX
TRUE
NORTH
S S SOUTH
S SC SLIP-CRITICAL
S SCHED SCHEDULE
S SECT SECTION
S SF SQUARE FOOT
S SHT SHEET
S SIM SIMILAR
S SOG SLAB ON GRADE
S SPA SPACE, SPACING
S SPEC SPECIFICATION
S SQ SQUARE
S SSL SHORT SLOTTED HOLE
S SSLP SHORT SLOTTED HOLE PARALLEL
S SSLT SHORT SLOTTED HOLE
TRANSVERSE
S SST STAINLESS STEEL
S STD STANDARD
S STL STEEL
S STRUCT STRUCTURAL
S SUSP SUSPENDED
S SW SHEAR WALL
S SYMM SYMMETRICAL
T T&B TOP AND BOTTOM
T TEMP TEMPORARY
T THK THICK
T THRU THROUGH
T TOB TOP OF BEAM
T TOC TOP OF CONCRETE
T TOF TOP OF FOOTING
T TOM TOP OF MASONRY
T TOS TOP OF STEEL
T TOW TOP OF WALL
T TRANSV TRANSVERSE
T TYP TYPICAL
U UL UNDERWRITERS LABORATORIES
U UNO UNLESS NOTED OTHERWISE
V VERT VERTICAL
V VOL VOLUME
W W WEST
W W/ WITH
W W/O WITHOUT
W WD WOOD
W WP WORKING POINT
W WT WEIGHT
W WTS WELDED THREADED STUDS
W WWR WELDED WIRE REINFORCEMENT
G GA GAGE
G GALV GALVANIZED
H HDG HOT-DIP GALVANIZED
H HORIZ HORIZONTAL
H HS HIGH STRENGTH
H HSA HEADED STUD ANCHOR
H HT HEIGHT
I ID INSIDE DIAMETER
I IJ ISOLATION JOINT
I IN INCH
I INFO INFORMATION
I INT INTERIOR
J JBE JOIST BEARING ELEVATION
J JT JOINT
K KSI KIPS PER SQUARE INCH
L LBS POUNDS
L LF LINEAR FEET
L LL LIVE LOAD
L LLH LONG LEG HORIZONTAL
L LLV LONG LEG VERTICAL
L LONG LONGINTUDINAL
L LSL LONG SLOTTED HOLE
L LSLP LONG SLOTTED HOLE PARALLEL
L LSLT LONG SLOTTED HOLE
TRANSVERSE
L LT GA LIGHT GAGE
M MAX MAXIMUM
M MECH MECHANICAL
M MFR MANUFACTURER
M MIN MINIMUM
M MISC MISCELLANEOUS
M MTL METAL
N # NUMBER
N N NORTH
N NA NOT APPLICABLE
N NIC NOT IN CONTRACT
N NOM NOMINAL
N NS NEAR SIDE
N NTS NOT TO SCALE
O OA OVERALL
O OC ON CENTER
O OD OUTSIDE DIAMETER
O OF OUTSIDE FACE
O OPNG OPENING
O OPP OPPOSITE
O OWJ OPEN WEB JOIST
P PAF POWDER ACTUATED FASTENERS
P PCF POUNDS PER CUBIC FOOT
P PEMB PRE-ENGINEERED METAL
BUILDING
P PERP PERPENDICULAR
P PH PHASE
P PL PLATE
P PLWD PLYWOOD
P PNL PANEL
P PREFAB PREFABRICATED
P PROJ PROJECT
P PSF POUNDS PER SQUARE FOOT
P PSI POUNDS PER SQUARE INCH
P PT POST TENSIONED
Q QTY QUANTITY
R R RADIUS
R REF REFERENCE
R REINF REINFORCE, REINFORCEMENT
R REQD REQUIRED
R REV REVISION
R RO ROUGH OPENING
A & AND
A @ AT
A ADDL ADDITIONAL
A ADJ ADJACENT
A AFF ABOVE FINISHED FLOOR
A ALT ALTERNATE
A ALUM ALUMINUM
A APPROX APPROXIMATE
A AR ANCHOR RODS
A ARCH ARCHITECT
A ASTM AMERICAN SOCIETY FOR TESTING
AND MATERIALS
A ATFP ANTI-TERRORISM FORCE
PROTECTION
B BAL BALANCE
B BD BOARD
B BLDG BUILDING
B BLKG BLOCKING
B BLW BELOW
B BM BEAM
B BOT BOTTOM
B BRG BEARING
B BTWN BETWEEN
C CFS COLD-FORMED STEEL
C CG CENTER OF GRAVITY
C CIP CAST IN PLACE
C CJ CONTROL JOINT
C CJ CONSTRUCTION JOINT
C CL CENTERLINE
C CLR CLEAR
C CMU CONCRETE MASONRY UNIT
C COL COLUMN
C CONC CONCRETE
C CONN CONNECTION
C CONSTR CONSTRUCTION
C CONT CONTINUOUS
C CONTR CONTRACTOR
C COORD COORDINATE
C CTR CENTER
D DBL DOUBLE
D DEMO DEMOLISH
D DET DETAIL
D DIA OR Ø DIAMETER
D DIAG DIAGONAL
D DIM DIMENSION
D DIST DISTANCE
D DL DEAD LOAD
D DWG DRAWING
E E EAST
E EA EACH
E EF EACH FACE
E EL ELEVATION
E ELEC ELECTRIC
E EMBED EMBEDMENT
E ENGR ENGINEER
E EQ EQUAL
E EQUIV EQUIVALENT
E EW EACH WAY
E EXIST EXISTING
E EXP EXPANSION
E EXT EXTERIOR
F FD FLOOR DRAIN
F FDTN FOUNDATION
F FIN FINISH(ED)
F FIN FLR FINISHED FLOOR
F FLG FLANGE
F FLR FLOOR
F FOC FACE OF CONCRETE
F FOM FACE OF MASONRY
F FOS FACE OF STUD, FACE OF STEEL
F FRMG FRAMING
F FS FAR SIDE
F FT FOOT, FEET
F FTG FOOTING
F FV FIELD VERIFY
WSP USA Inc.
Suite 300
Federal Way, WA 98003-2600
TEL: (206) 431-2300
FAX: (206) 431-2250
33301 9th Avenue South
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
STL JB DATA CENTER EHRM
INFRASTRUCTURE UPGRADES
JEFFERSON BARRACKS, MO
ST. LOUIS, MO 63125
657-21-701JB
SPEES DESIGN BUILD
23830 PACIFIC HIGHWAY S. SUITE 203
KENT, WA 98032
(206) 590-2118
RAY SPEES S-002
ABRREVIATIONS AND SYMBOLS
DDV JKM
ADDENDUM 1
04/11/2025
Revisions: Date:
DanSchwab Architect
ADDENDUM 1
DanSchwab Architect 04/11/2025
DanSchwab Architect
DanSchwab PolyLine
DanSchwab
2 3 4 5 6 8
B
D
F
G
H
SHOWN AREA
PROJECT
NORTH
F1
S-101
/F1 S-101
EXIST HOUSEKEEPING PAD, TYP
CL
EQUIPMENT PER MECH
1300 LBS MAX
T Y
P
2'
2' - 6"
EXIST ROOF BEAMS, TYP
CONC PAD CENTER ABOVE
EXIST ROOF JOISTS AND
GRID LINE, TYP
EQUIPMENT PER MECH
400 LBS MAX
M
IN
7' -0
EXIST ROOF JOIST, TYP
MIN
4' - 0"
A7
S-101
EXIST ROOF JOIST, TYP
REINF EMBED LOCATION, TYP
7' -0
M
IN
G
F
2 3 4
EQ EQ
EQ EQ
5"
T Y
P
LEVEL 3
37' - 0"
#4 @ 12" OC EW
CENTER IN SLAB
#4 @ 12" OC EW
CENTER IN SLAB
STYROFOAM INFILL, TYP
TOP OF EXIST ROOFING
TOP OF EXIST CONC ROOF
EL PER PLAN
EPOXY 3" INTO EXIST SLAB WHERE
SHOWN IN PLAN, SCAN AN LOCATE
EXISTING REINF. PRIOR TO DRILLING.
DO NOT DAMAGE EXISTING
REINFORCMENT, TYP
EQUIP PER MECH, TYP
EXIST ROOF BEAM
EXIST ROOF SLAB
SIMPSON TITEN HD SS W/ 4"
EMBED. DIAMETER TO BE 1/8"
LESS THAN MFR ANCHOR
HOLE DIAMETER.
LOCATION PER MFR, TYP
M A
X
8" M
IN
5" MAX
4" MIN
#4 @ 8" OC HORIZ, TYP
#4 @ 12" OC VERT CENTER
IN CURB, TYP
4'-0" MAX TYP
5"
TYP
5" CURB
LOCATE INNER CURBS
BELOW MECH UNIT
SUPPORTS
LEVEL 3
37' - 0"
STYROFOAM INFILL, TYP
TYP
4'-0" MIN
5" MAX
4" MIN
TOP OF EXIST ROOFING
TOP OF EXIST CONC ROOF
EL PER PLAN
EPOXY 3" INTO EXIST SLAB
WHERE SHOWN IN PLAN, SCAN AN
LOCATE EXISTING REINF. PRIOR
TO DRILLING. DO NOT DAMAGE
EXISTING REINFORCMENT, TYP
EQUIP PER MECH, TYP
EXIST ROOF BEAM
EXIST ROOF SLAB
M A
X
8" M
IN
#4 @ 12" OC EW
CENTER IN SLAB
#4 @ 12" OC EW
CENTER IN SLAB
#4 @ 8" OC HORZ, TYP
#4 @ 12" OC VERT CENTER
IN CURB, TYP
5"
5" CURB TYP
SIMPSON TITEN HD SS W/ 4"
EMBED. DIAMETER TO BE
1/8" LESS THAN MFR
ANCHOR HOLE DIAMETER.
LOCATION PER MFR, TYP
ABBREVIATIONS
db = BAR DIAMETER Ld = TENSION DEVELOPMENT LENGTH Ldt = TENSION DEVELOPMENT LENGTH FOR A TOP BAR Lb = CLASS B LAP SPLICE LENGTH, 1.3Ld Lbt = CLASS B LAP SPLICE LENGTH FOR A TOP BAR, 1.3 Ldt Ldh = TENSION DEVELOPMENT LENGTH FOR A STANDARD HOOK f'c = CONCRETE COMPRESSIBLE STRENGTH AT 28 DAYS fy = BAR YIELD STRENGTH
NOTES:
1. USE THE LENGTH IN THESE SCHEDULES, UNLESS NOTED OTHERWISE.
2. USE LENGTH IN (" ") WHEN BAR COVER IS db OR LESS OR BAR CLEAR SPACING IS 2db OR LESS.
3. TOP BAR IS HORIZONTAL BAR WITH MORE THAN 12" OF FRESH CONCRETE CAST BELOW IT.
SIZE Ld Ldt Lb Lbt Ldh
#4
#5
#6
#7
#8
#9
#10
27 (40) f'c = 4,500 psi fy = 60,000 psi
39 (59)
45 (67)
50 (75)
56 (84) 73 (109)
65 (98)
58 (87)
51 (76)
35 (52) 35 (52)
51 (76)
58 (87)
65 (98)
73 (109)
45 (68)
66 (99)
76 (113)
85 (128)
94 (142)
WSP USA Inc.
Suite 300
Federal Way, WA 98003-2600
TEL: (206) 431-2300
FAX: (206) 431-2250
33301 9th Avenue South
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
STL JB DATA CENTER EHRM
INFRASTRUCTURE UPGRADES
JEFFERSON BARRACKS, MO
ST. LOUIS, MO 63125
657-21-701JB
SPEES DESIGN BUILD
23830 PACIFIC HIGHWAY S. SUITE 203
KENT, WA 98032
(206) 590-2118
RAY SPEES S-101
BLDG 56 - ROOF PLAN
DDV JKM
ADDENDUM 1
04/11/2025
PLAN NOTES:
1. REFER TO ARCHITECTURAL AND MECHANICAL DRAWINGS FOR ANY DIMENSIONS, OPENINGS, AND
ELEVATIONS NOT SHOWN.
2. REFER TO ARCHITECTURAL AND MECHANICAL DRAWINGS FOR THE FOLLOWING:
A. DIMENSIONS NOT SHOWN.
B. OPENINGS NOT SHOWN.
C. FLOOR ELEVATIONS.
01S
GENERAL NOTES
KEY PLAN
LEGEND
3/16" = 1'-0" C1
PARTIAL ROOF PLAN
1" = 1'-0" F1
SECTION - EQUIPMENT PAD
1" = 1'-0"
A7
SECTION - EQUIPMENT PAD
Revisions: Date:
1/2" = 1'-0" C7
DEVELOPMENT AND LAP SPLICE
LENGTH SCHEDULES - CONCRETE
DanSchwab Architect
ADDENDUM 1
DanSchwab Architect 04/11/2025
DanSchwab Architect
DanSchwab PolyLine
DanSchwab
SHOWN AREA
PROJECT
NORTH
2 3 4 54.84.4
G
4.6s1 s5 sC
F
CRAC RS/RL LINE DN TO
BASEMENT SEE MP100
FOR CONTINUATION
(TYP.2)
VRF/VRV RL/S LINES DN
TO BASEMENT SEE MP100
FOR CONTINUATION
(TYP.2)
CRAC RS/RL LINE UP TO
ROOF SEE MP102 FOR
CONTINUATION
(TYP.2)
VRF/VRV RS/RL LINE UP TO
ROOF SEE MP102 FOR
CONTINUATION
(TYP.2)
RECEPTION
WAITING
C1 - 4
PREFUNCTION
C1-12
STOR
1B 127
NCA OFF
1B 126NCA OFF
1B 125
NCA OFF
1B 124
NCA OFF
1B 123
NCA OFF
1B 122
LOCKERS
C1-21
REFERENCE
LIBRARY
1B 121
STOR
1B 129
DISPLAY
C1 - 20
WAITING
C1 - 13
CORR
C1-15
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of
Construction and Facilities
Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
SPEES DESIGN BUILD
23830 PACIFIC HIGHWAY S. SUITE 203
KENT, WA 98032
/9
/2
:5
:3
P M
B
IM
/6
-2
-7
J B
V A
M O
J B
E H
R M
I U
D a ta
C e n te r/ V
A S
T L
D
C
M
E
S D
B .r v t
MP101
FIRST FLOOR PLAN - MECHANICAL PIPING
MGH/JW CY/SH
100% CONSTRUCTION
DOCUMENTS
06/05/2024
657-21-709JBEHRM INFRASTRUCTURE
UPGRADES DATA CENTER - JB
JEFFERSON BARRACKS, MO
ST. LOUIS, MO 63125
KEY PLAN
GENERAL NOTES
1. FOR THE PURPOSES OF CLEARNESS AND LEGIBILITY, DRAWINGS ARE
DIAGRAMMATIC AND FOR DESIGN INTENT ONLY. CONTRACTOR MUST VERIFY ALL
DIMENSIONS BY FIELD MEASUREMENT BEFORE BEGINNING ANY FABRICATION OR
CONSTRUCTION. ALL RACKING PIPING AS CLOSE AS POSSIBLE TO INSIDE WALL OF
TELECOM ROOM
2. ALL WORK SHALL BE IN ACCORDANCE WITH APPLICABLE LASTEST VERSION OF THE
VA HVAC DESIGN GUIDE
3. ALL NEW MATERIAL, METHODS, AND EQUIPMENT SHALL BE INSTALLED IN STRICT
ACCORDANCE WITH THE BUILDING STANDARDS AS APPROVED BY THE OWNER.
4. CONTRACTOR SHALL INSTALL ALL EQUIPMENT IN STRICT ACCORDANCE WITH
MANUFACTURERS RECOMMENDATIONS.
5. COORDINATE EXACT LOCATION OF DUCTWORK WITH EQUIPMENT, LIGHTING, PIPING,
ETC..
6. BALANCE AIR SYSTEMS WITHIN 10% OF CAPACITIES LISTED.
7. CONTRACTOR SHALL COORDINATE WITH GENERAL CONTRACTOR OR OWNER PRIOR
TO ANY CUTTING OF ROOF.
1/4" = 1'-0"
FIRST FLOOR PLAN -MECHANICAL PIPING
PROJECT
NORTH
AREA OF WORK
Revisions: Date:
Addendum 1 4/11/2025
4/11/25
A
A
SHOWN AREA
PROJECT
NORTH
ROOF
1 2 3 4 5 6 7 86.4 6.65.5
4.8
4.41.3
B
C
D
E
G
4.6 5.2s1 s5 sC sA
D.5
F
EXISTING CRAC OUTDOOR UNITS (TYP 3)
56-HP-02-102
56-HP-01-102
EXISTING
CU
LOWER ROOF
UPPER ROOF
56-CU-05-102
56-CU-04-102
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of
Construction and Facilities
Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
SPEES DESIGN BUILD
23830 PACIFIC HIGHWAY S. SUITE 203
KENT, WA 98032
/9
/2
:0
:3
P M
B
IM
/6
-2
-7
J B
V A
M O
J B
E H
R M
I U
D a ta
C e n te r/ V
A S
T L
D
C
M
E
S D
B .r v t
MP102
ROOF PLAN - MECHANICAL PIPING
MGH/JW CY/SH
100% CONSTRUCTION
DOCUMENTS
06/05/2024
657-21-709JBEHRM INFRASTRUCTURE
UPGRADES DATA CENTER - JB
JEFFERSON BARRACKS, MO
ST. LOUIS, MO 63125
KEY PLAN
GENERAL NOTES
1. FOR THE PURPOSES OF CLEARNESS AND LEGIBILITY, DRAWINGS ARE
DIAGRAMMATIC AND FOR DESIGN INTENT ONLY. CONTRACTOR MUST VERIFY ALL
DIMENSIONS BY FIELD MEASUREMENT BEFORE BEGINNING ANY FABRICATION OR
CONSTRUCTION. ALL RACKING PIPING AS CLOSE AS POSSIBLE TO INSIDE WALL OF
TELECOM ROOM
2. ALL WORK SHALL BE IN ACCORDANCE WITH APPLICABLE LASTEST VERSION OF THE
VA HVAC DESIGN GUIDE
3. ALL NEW MATERIAL, METHODS, AND EQUIPMENT SHALL BE INSTALLED IN STRICT
ACCORDANCE WITH THE BUILDING STANDARDS AS APPROVED BY THE OWNER.
4. CONTRACTOR SHALL INSTALL ALL EQUIPMENT IN STRICT ACCORDANCE WITH
MANUFACTURERS RECOMMENDATIONS.
5. COORDINATE EXACT LOCATION OF DUCTWORK WITH EQUIPMENT, LIGHTING, PIPING,
ETC..
6. BALANCE AIR SYSTEMS WITHIN 10% OF CAPACITIES LISTED.
7. CONTRACTOR SHALL COORDINATE WITH GENERAL CONTRACTOR OR OWNER PRIOR
TO ANY CUTTING OF ROOF.
8. ALL REFRIGERANT LINES ARE SIZES BASED BOD. VERIFY LINE SIZING WITH
MANUFACTURER.
1/8" = 1'-0"
ROOF PLAN - MECHANICAL PIPING
PROJECT
NORTH
KEYNOTES
CRAC-04-102 TO BE INSTALLED FIRST TO MAINTAIN COOLING DURING
CONSTRUCTION. THIS INCLUDES ALL ASSOCIATED PIPING AND DIFFUSERS
Revisions: Date:
Addendum 1 4/11/2025
4/11/25
J
J
4160 VO
LTS
DUST CO
LLECTO
R
LIQ UEFIED PETRO LEUM G AS
FLAM M ABLE G AS 2
TRASH COM
PACTO
R
P
SILVERBUILDING 1 23
VA PO
LICE
E
LECTRIC ACCESS
TRANSFO
RM
ER
TRANSFO
RM
ER
TRANSFO
RM
ER
HVAC UNIT
E
LECTRIC PANEL
HVAC UNIT
S&C PAD M
O
UNTED G
EAR
CATALO
G
# 55152-C3DGIG
2P1V M
O
DEL# PM
H-9
EE13299 SG
-52
13278
BUILDING
AREA OF WORK
1 2 3 4 5 6 7 86.4 6.65.54.84.41.3
B
C
D
E
F
G
H
4.6 5.2s1 s5 sC sA
D.5
AMD / AV
PRODUCTION
COORD
BB 143
IT CDN, SHARED
BB 144
E-LEARN PROD
OFFICE
BB 145
E-LEARN PROD
OFFICE
BB 146
E-LEARN PROD
OFFICE
BB 147
GRAPHICS
OFFICE
BB 109
GRAPHICS
OFFICE
BB 108
GRAPHICS
OFFICE
BB 107
GRAPHICS
OFFICE
BB 105
OFFICE, STUDIO
MGR
BB 104
OFFICE, STUDIO
MGR
BB 100
OFFICE
PRODUCER
BA 125
OFFICE
PRODUCER
BA 123
TR
BA 105
DATA
BA 106
ELEC
BA 107
RECYCLING
ROOM
BA 104
PROD CTL VIDEO
BA 110
STAIR 1
STAIR
WOMEN
BA 100
OFFICE, SR
ENGINEER
BA 122
NAT'L MEDIA
SVCS COORD
BA 121
OFFICE
PRODUCER
BA 120
GREEN ROOM
BA 119
DRESSING RM
BA
118A
MAKE UP
BA 118
LAN / TEL / DATA
DMARK ROOM
BA 114
ENG MAINT
BA 115
OFFICE
PRODUCER
BA 116
AV PRODUCTION
SUPPORT
BA 113
CONTRACTOR
WKSTNS (2)
BA 112
SUPPORT TECH
BA
112A
STUDIO
BA 109
EQPT AV STR
BA
103A
STUDIO MECH
BA
108B
MEDIA STORAGE
BA 108
DOCK /
RECEIVING
BA 103
MAIL ROOM
BA 102
MEN
BA 101
ELEV
S - 1
ELEV
P - 1
IT NON - SECURE
STR
BB 121
IT SECURE
STORAGE
BB 120
STORAGE,
EQUIPMENT +
SUPPLIES /
PARTS
BB 119
COMBINED
COMPUTER /
SERVER ROOM
BB 102
AVID SUITE
BB 116
AVID MACHINE
ROOM
BB 117
AVID SUITE
BB 114
AVID SUITE
BB 113
MSTR OFFICE
SUPPLIES
BB 124
STAIR 2
STAIR
KIT
BB 126
TLT
BB 127
TLT
BB 128
SOCIAL MEDIA
BB 132
IT SYSTEM ADMIN
BB 133
IT SPECIALIST
BB 134
IT SPECIALIST
BB 135
IT SYSTEM
ADMIN, SHARED
BB 136
IT OFFICE ISO
BB 137
IT SPECIALIST,
SHARED
BB 138
OFFICE
ENGINEER
SHARED
BB 139
Room
BB 140
ELEARN PROD
BB 141
LRG COORD
BB 148
LRG PROGRAM
SUPPORT
BB 130
NORMAL
ELECTRICAL
ENTRY
BB
129A
EMERGENCY
ELECTRICAL
ENTRY
BB 129
EES ELEC
BB 125
MUSIC LIBRARY
BB 118
OFFICE EDIT
BB 115
OFFLINE EDIT
BB 112
GRAPHICS
STORAGE
BB 111
DUBBING / CDN
BB 106
AUDIO BOOTH
BB 110
COPY ROOM
BB 103
WK ROOM
BB 101
MASTER
CONTROL
BA 117
MECH
BB 123
HSKG
BB 122
LRG
CB-20
LRG
CB-19
LRG
CB-18
COLLABORATION
CB -50
ATS LS
ATS EQ
GSB 56
MSB 56-1
DP/56M
DP/56L
DP/56R
ATS C
TR 56-C
DP/56EQ
DP/56LS
METER
ENCLOSURE
JUNCTION
BOX
METER ENCLOSURE
(2) METER
ENCLOSURES
STACKED
METERING ENCLOSURE
HOUSEKEEPING PAD
HOUSEKEEPING PAD
METER ENCLOSURE
PRIMARY BONDING BUSBAR
ET101
ET102
EL101
EP101
ED103
ED104
ED101
ED102
56-P-10
56-P-02
56-P-04
FACP
56-AHU-0A
CONCRETE
HOUSEKEEPING
PAD
EP401
EP401
EP401
EP401
EXISTING MCC
56-P-14G
EP402
EP402
56-P-05
56-P-19
56-P-12A
56-P-18
56-P-07A
TR-56-DP-TRB
56-DP-TRB
56-DP-TRA
CONTINUE TO EXTERNAL
FUEL TANK. REFERENCE
SHEET E-102 FOR
ADDITIONAL INFORMATION
56-P-36
56-P-34A
EP402
EP402
56-P-35A
56-P-03
56-P-38
56-P-39
56-P-40
TO GENERATOR
CONTROL CABINET.
REFERENCE
SHEET E-102 FOR
ADDITIONAL INFORMATION
56-P-09I
56-P-08A
56-P-13A
56-P-09C
56-P-14E
BLDG 56
A SIDE POWER
B SIDE POWER
SHEET SHALL BE PRINTED
IN COLOR TO PROVIDE ALL
INFORMATION
LEGEND:
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of
Construction and Facilities
Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
SPEES DESIGN BUILD
23830 PACIFIC HIGHWAY S. SUITE 203
KENT, WA 98032
/0
/2
:0
:0 a m
B
IM
/6
-2
-7
J B
V A
M O
J B
E H
R M
I U
D a ta C e n te r/
V A
S T
L
D C
E
L S
D B
.r v t
E-101
BLDG 56 - LEVEL 00 - ELECTRICAL PLAN
WNM/MM JBB/JFO
100% CONSTRUCTION
DOCUMENTS
05/10/2024
657-21-709JBEHRM INFRASTRUCTURE
UPGRADES
JEFFERSON BARRACKS, MO
ST. LOUIS, MO 63125
KEY PLAN
GENERAL NOTES
TRUE
NORTH
KEY NOTES
1. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR SHALL
FIELD VERIFY ALL POWER, LIGHTING AND ASSOCIATED CIRCUITRY AS REQUIRED. ALL
RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT TO BE DEMOLISHED
SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS OTHERWISE NOTED.
2. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY
DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE
REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE
ACCEPTANCE OF THE OWNER.
3. CONTRACTOR SHALL COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM
SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED
EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY POWER
AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT. POWER TO
ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND SHALL REMAIN
ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN SHALL CONFORM WITH
VA STANDARDS.
4. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE
RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL
DRAWINGS AS REQUIRED.
- 1/8" = 1'-0"
1 BLDG 56 - LEVEL 00 - ELECTRICAL PLAN
MODIFIED EQUIPMENT. PROVIDE FEEDERS AS INDICATED.
PROVIDE JUNCTION BOX ABOVE ACCESSIBLE CEILING TO CONSOLIDATE ATS
STATUS/RUN SIGNALS/WIRING TO (1) 2" CONDUIT. ROUTE CONDUIT TO GENERATOR
BUILDING AND TERMINATE TO GENERATOR CONTROL CABINET. PROVIDE
TRENCHING AS REQUIRED. COORDINATE BACKFILL AND SURFACING REQUIREMENTS
WITH CIVIL DRAWINGS.
EXISTING FACP LOCATED IN ROOM "BA 106" ON LEVEL 00. PROVIDE ALL REQUIRED
CONNECTIONS, CONDUIT, WIRE, PROGRAMMING, AND TESTING FOR ALL ADDITIONAL
FIELD DEVICES AS REQUIRED; CONTRACTOR SHALL PROVIDE A COMPLETE AND
FULLY FUNCTIONAL SYSTEM. REFERENCE ALL ELECTRICAL PLANS FOR FIELD
DEVICE LOCATIONS.
PROVIDE (1) JUNCTION BOX AND (1) SEAL-OFF FOR EACH CONDUIT. SEAL-OFFS
SHALL BE +24" AFG. JUNCTION BOXES SHALL BE NEMA 3R.
4'0 8' 16'
PROJECT
NORTH
Revisions: Date:
ADDENDUM 1 04/11/2025
T
T
T
T
T
T T
T
T
T
T
T
T
T
T
T
T
T
T
T
T
T
T
T
T
T T
T
T
T
T
T
T
T
T
T
T
T
T
T
T
T
T
T
T
T
T
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
4160 VO
LTS
DUST CO
LLECTO
R
LIQ UEFIED PETRO LEUM G AS
FLAM M ABLE G AS 2
TRASH COM
PACTO
R
P
SILVERBUILDING 1 23
VA PO
LICE
E
LECTRIC ACCESS
TRANSFO
RM
ER
TRANSFO
RM
ER
TRANSFO
RM
ER
HVAC UNIT
E
LECTRIC PANEL
HVAC UNIT
S&C PAD M
O
UNTED G
EAR
CATALO
G
# 55152-C3DGIG
2P1V M
O
DEL# PM
H-9
EE13299 SG
-52
13278
BUILDING
AREA OF WORK
PROPOSED FIBER DUCTBANK
EX. GENERATOR BLDG
EX. BLDG 56
8' - 0
' - 6
EX. CMU
SCREEN WALL
EXISTING GENERATOR
HOUSEKEEPING PAD
BATTERY BANK
FUEL TANK
CONTROL PANEL
EXISTING 600 GAL
FUEL TANK
PANEL '56-LSGB'
30 kVA XFMR
'TR-56-LSGB'
XFMR DISCONNECT
GROUND BAR
PULL BOX,
(4) CONDUITS
GENERATOR
CONTROL CABINET
E-503
CONTINUE TO "56-ATS-A" AND "56-ATS-B"
IN BUILDING 56. SEE SHEET E-101 FOR
ADDITIONAL INFORMATION.
56-FP-02
56-P-35A
56-P-34A
CONTINUE TO ROOM BB 125. SEE SHEET E-101
FOR ADDITIONAL INFORMATION.
56-P-34B
56-P-35B
56-P-36
56-P-40
56-FP-01,
56-FPS-01
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of
Construction and Facilities
Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
SPEES DESIGN BUILD
23830 PACIFIC HIGHWAY S. SUITE 203
KENT, WA 98032
/0
/2
:1
:5 a m
B
IM
/6
-2
-7
J B
V A
M O
J B
E H
R M
I U
D a ta C e n te r/
V A
S T
L
D C
E
L S
D B
.r v t
E-102
GENERATOR FUEL TANK ELECTRICAL PLAN
WNM/MM JBB/JFO
100% CONSTRUCTION
DOCUMENTS
05/10/2024
657-21-709JBEHRM INFRASTRUCTURE
UPGRADES
JEFFERSON BARRACKS, MO
ST. LOUIS, MO 63125
KEY PLAN
GENERAL NOTES
TRUE
NORTH
KEY NOTES
1. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR SHALL
FIELD VERIFY ALL POWER, LIGHTING AND ASSOCIATED CIRCUITRY AS REQUIRED. ALL
RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT TO BE DEMOLISHED
SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS OTHERWISE NOTED.
2. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY
DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE
REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE
ACCEPTANCE OF THE OWNER.
3. CONTRACTOR SHALL COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM
SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED
EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY POWER
AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT. POWER TO
ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND SHALL REMAIN
ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN SHALL CONFORM WITH
VA STANDARDS.
4. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE
RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL
DRAWINGS AS REQUIRED.
- 1/8" = 1'-0"
1 GENERATOR FUEL TANK ELECTRICAL PLAN 4'0 8' 16'
PROJECT
NORTH
ATS STATUS/RUN CONDUIT. ROUTE CONDUIT FROM BUILDING 56 ATSs TO
GENERATOR CONTROL CABINET IN GENERATOR BUILDING. PROVIDE TRENCHING AS
REQUIRED. COORDINATE BACKFILL AND SURFACING REQUIREMENTS WITH CIVIL
DRAWINGS.
PROVIDE NEMA-3R DISCONNECT, LOCKABLE. MOUNT DISCONNECT TO UNISTRUT
RACK. REFERENCE DETAIL 4 ON SHEET E-503 FOR MATERIAL AND
CONSTRUCTABILITY REQUIREMENTS.
AUTOMATIC TRANSFER SWITCHES "56-ATS-A" AND "56-ATS-B" SHALL HAVE MINIMUM
POINTS/SIGNALS AS FOLLOWS:
- GENERATOR START SIGNAL (CALL TO RUN)
- ATS IN NORMAL POSITION "ATS-B-NPS"
- ATS IN EMERGENCY POSITION "ATS-B-EPS"
- ATS NORMAL POWER AVAILABLE "ATS-B-NPA"
- ATS EMERGENCY POWER AVAILABLE "ATS-B-EPA"
ABOVE GROUND REMOTE DIESEL GENERATOR FUEL TANK. PROVIDE ALL REQUIRED
RACEWAYS, COMPONENTS, AND CONNECTIONS AS REQUIRED FOR THE AREA.
REFERENCE NEC 515, TABLE 515.3 FOR ADDITIONAL INFORMATION.
Revisions: Date:
ADDENDUM 1 04/11/2025
AREA OF WORK
BB102
4 5 5.54.84.4
F
G
4.6 5.2s5
COMBINED
COMPUTER /
SERVER ROOM
BB 102
DP/56U
UPS
MAINTENANCE
BYPASS PANEL
UPS TE-BREAKER
PANEL
UPS
UPS
UPS CONTROL PANEL
UPS CONTROL PANEL
56-C7
56-C6
56-C5
56-C4
56-C3
56-C2
LIGHTING CONTROL PANEL
LIGHTING CONTROL PANEL
LIGHTING CONTROL PANEL
56-SP1
FIRE
SUPPRESSION
CONTROL PANEL
56-CRAC-A 56-CRAC-B
56-CRAC-C
3 4
1 1
1 1
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of
Construction and Facilities
Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
SPEES DESIGN BUILD
23830 PACIFIC HIGHWAY S. SUITE 203
KENT, WA 98032
/0
/2
:1
:0 a m
B
IM
/6
-2
-7
J B
V A
M O
J B
E H
R M
I U
D a ta C e n te r/
V A
S T
L
D C
E
L S
D B
.r v t
ED101
DATA CENTER - LIGHTING DEMOLITION PLAN
WNM/MM JBB/JFO
100% CONSTRUCTION
DOCUMENTS
05/10/2024
657-21-709JBEHRM INFRASTRUCTURE
UPGRADES
JEFFERSON BARRACKS, MO
ST. LOUIS, MO 63125
KEY PLAN
GENERAL NOTES
PROJECT
NORTH
2'0 4' 6'
PROJECT
NORTH
KEY NOTES
1. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN. CONTRACTOR SHALL FIELD VERIFY
ALL LIGHTING, CONTROLS, AND ASSOCIATED CIRCUITRY AS REQUIRED. ALL
RACEWAYS AND CONDUCTORS ASSOCIATED WITH DEMOLISHED EQUIPMENT SHALL
BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS OTHERWISE NOTED.
2. ALL DEMOLITION OF ELECTRICAL SYSTEM SHALL BE CLOSELY COORDINATED WITH
THE CONTRACTORS PHASING OF THE PROJECT. VERIFY DEMOLITION OF ELECTRICAL
WITHH ALL TRADES PRIOR TO START OF DEMOLITION.
3. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY
DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES AND THE LIKE, SHALL BE
PREPARED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE
ACCEPTANCE OF THE OWNER.
4. ALL CICUITS AND RELATED DEVICES THAT ARE TO REMAIN ARE TO STAY
"ENERGIZED" IN THE DEMOLITION AND NEW CONSTRUCTION PHASES UNTIL THE
COMPLETION OF THE WORK INDICATED IN THE PLAN.
5. THE CONTRACTOR SHALL REMOVE ALL ELECTRICAL ASSOCIATED WITH WALLS BEING
REMOVED, AND IN LOCATIONS WHERE JUNCTION BOXES WILL NOT REMAIN
ACCESSIBLE AFTER INSTALLATION OF MILLWORK.
6. CONTRACTOR SHALL DISPOSE OF THE REMOVED DEVICES. DISPOSAL OF DEVICES
SHALL COMPLY WITH ALL APPROPRIATE CODES. REUSE EXISTING CONDUITS AND
JUNCTION BOXES AS IS PRACTICAL.
7. THE CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL
PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.
8. CONTRACTOR SHALL ENSURE ALL EQUIPMENT INCLUDING, BUT NOT LIMITED TO
LIGHT BALLASTS THAT CONTAIN PCBs, SHALL BE PROPERLY REMOVED AND
DISPOSED.
EXISTING RECESSED LUMINAIRE AND ALL ASSOCIATED CONTROL DEVICES AND
WIRING TO BE DEMOLISHED.
EXISTING ROW OF LUMINAIRES AND THEIR CORRESPONDING CONDUIT AND WIRE TO
BE DEMOLISHED BACK TO SOURCE.
EXISTING EQUIPMENT TO BE DEMOLISHED. ASSOCIATED CONDUIT AND WIRE
SHALL BE DEMOLISHED BACK TO SOURCE.
APPROXIMATE FOOTPRINT OF MECHANICAL EQUIPMENT TO BE INSTALLED.
RELOCATE EXISTING EQUIPMENT WITHIN FOOTPRINT AND NEAREST WALL FROM
FLOOR TO CEILING INCLUDING EQUIPMENT BELOW TILE/ABOVE CEILING UNLESS
STATED OTHERWISE. FOR ALL RELOCATED EQUIPMENT, EXTEND CONDUIT AND WIRE
AND REROUTE AS REQUIRED.
- 3/8" = 1'-0"
1 DATA CENTER - LIGHTING DEMOLITION PLAN
Revisions: Date:
ADDENDUM 1 04/11/2025
E E
E
E
E E
E E
E
E E E
E
E
AREA OF WORK
4 5 5.54.84.4
F
G
4.6 5.2s5
UPS CONTROL
PANEL
UPS CONTROL
PANEL
EXTINGUISHING
SYSTEM ABORT
UPS SHUTDOWN
UPS
UPS
UPS TE-BREAKER
PANEL
UPS
MAINTENANCE
BYPASS PANEL
DP/56U
56-SP1
LIGHTING CONTROL PANEL
LIGHTING CONTROL PANEL
LIGHTING CONTROL PANEL
56-C2
56-C3
56-C4
56-C5
56-C6
56-C7
CAB #19
CAB #20
CAB #21
CAB #22
CAB #23
CAB #24
CAB #25
CAB #26
CAB #27
CAB #10
CAB #11
CAB #12
CAB #13
CAB #14
CAB #15
CAB #16
CAB #17
CAB #18
CAB #01
CAB #02
CAB #03
CAB #04
CAB #05
CAB #06
CAB #07
CAB #08
CAB #09
COMBINED
COMPUTER /
SERVER ROOM
BB 102
'1'
'2'
'3'
'4'
'5'
'6'
'7'
'8'
'9'
'10'
'15'
'14'
'13'
'12'
'11'
'20'
'19'
'18'
'17'
'16'
'36'
'35'
56-CRAC-A 56-CRAC-B
56-CRAC-C
TYP.
EMERGENCY PUSH
BUTTON
EMERGENCY PUSH
BUTTON
EMERGENCY PUSH
BUTTON
UPS SHUTDOWN (ABOVE)
EXTINGUISHING SYSTEM ABORT (BELOW)
EMERGENCY PUSH
BUTTON
EMERGENCY PUSH
BUTTON
UPS SHUTDOWN
EMERGENCY PUSH
BUTTON
UPS SHUTDOWN
EMERGENCY PUSH
BUTTON
UPS SHUTDOWN
EMERGENCY PUSH
BUTTON
E-505
EXISTING BUSBAR
7 1
7 1
7 1
7 1
BB 102
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of
Construction and Facilities
Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
SPEES DESIGN BUILD
23830 PACIFIC HIGHWAY S. SUITE 203
KENT, WA 98032
/0
/2
:1
:1 a m
B
IM
/6
-2
-7
J B
V A
M O
J B
E H
R M
I U
D a ta C e n te r/
V A
S T
L
D C
E
L S
D B
.r v t
ED102
DATA CENTER - POWER DEMOLITION PLAN
WNM/MM JBB/JFO
100% CONSTRUCTION
DOCUMENTS
05/10/2024
657-21-709JBEHRM INFRASTRUCTURE
UPGRADES
JEFFERSON BARRACKS, MO
ST. LOUIS, MO 63125
GENERAL NOTES
PROJECT
NORTH
- 3/8" = 1'-0"
1 DATA CENTER - POWER DEMOLITION PLAN 2'0 4' 6'
PROJECT
NORTH
KEY PLAN
KEY NOTES
DEMOLISH EXISTING ELECTRICAL CONNECTIONS BACK TO SOURCE. EXISTING DATA
CABINETS TO BE SALVAGED AND RETURNED TO THE VA.
EXISTING CABINETS DEDICATED TO I-LEAD. CABINETS AND ASSOCIATED EQUIPMENT
TO REMAIN.
EXISTING PANELS BELONGING TO I-LEAD TO BE RELOCATED. PRESERVE, MAINTAIN
AND EXTEND EXISTING BRANCH CIRCUITING FOR RETERMINATION INTO RELOCATED
PANEL. REFERENCE ONE-LINE DIAGRAM FOR ADDITIONAL INFORMATION.
EXISTING EQUIPMENT TO BE DEMOLISHED. ASSOCIATED CONDUIT AND WIRE SHALL
BE DEMOLISHED BACK TO SOURCE.
APPROXIMATE FOOTPRINT OF MECHANICAL EQUIPMENT TO BE INSTALLED.
RELOCATE EXISTING EQUIPMENT WITHIN FOOTPRINT AND NEAREST WALL FROM
FLOOR TO CEILING INCLUDING EQUIPMENT BELOW TILE/ABOVE CEILING UNLESS
STATED OTHERWISE. FOR ALL RELOCATED EQUIPMENT, EXTEND CONDUIT AND WIRE
AND REROUTE AS REQUIRED.
EXISTING EMERGENCY PUSHBUTTON TO BE RELOCATED. REFERENCE KEY NOTE '3'
ON SHEET EP101 FOR ADDITIONAL INFORMATION AND REVISED EQUIPMENT
LOCATION.
EXISTING EMERGENCY PUSHBUTTON TO BE CONNECTED TO NEW EQUIPMENT.
REFERENCE KEY NOTE '6' ON SHEET EP101 FOR ADDITIONAL INFORMATION.
Revisions: Date:
ADDENDUM 1 04/11/2025
1. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN. CONTRACTOR SHALL FIELD VERIFY
ALL ELECTRICAL, LOW VOLTAGE DEVICES AND ASSOCIATED CIRCUITRY AS
REQUIRED. ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH DEMOLISHED
EQUIPMENT SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS OTHERWISE
NOTED.
2. ALL DEMOLITION OF ELECTRICAL AND TELECOMMUNICATIONS SYSTEMS SHALL BE
CLOSELY COORDINATED WITH THE CONTRACTORS PHASING OF THE PROJECT.
VERIFY DEMOLITION OF ELECTRICAL WITH ALL TRADES PRIOR TO START OF
DEMOLITION.
3. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY
DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES, AND THE LIKE, SHALL BE
REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE
ACCEPTANCE OF THE OWNER.
4. ALL CIRCUITS AND RELATED DEVICES THAT ARE TO REMAIN SHALL STAY
"ENERGIZED" IN DEMOLITION AND NEW CONSTRUCTION PHASES UNTIL COMPLETION
OF WORK INDICATED ON THESE PLANS.
5. THE CONTRACTOR SHALL REMOVE ALL ELECTRICAL AND TELECOMMUNICATIONS
EQUIPMENT ASSOCIATED WITH WALLS BEING REMOVED, AND IN ALL LOCATIONS
WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER INSTALLATION OF
MILLWORK.
6. CONTRACTOR SHALL DISPOSE OF THE REMOVED DEVICES. DISPOSAL OF DEVICES
SHALL COMPLY WITH ALL APPROPRIATE CODES. REUSE EXISTING CONDUITS AND
JUNCTION BOXES AS IS PRACTICAL.
7. THE CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT DIRECTORIES FOR ALL
EQUIPMENT THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.
8. REMOVE ALL ABANDONED WIRING AND RACEWAYS TO SOURCE. COORDINATE WITH
COR FOR REMOVING EXISTING TERMINATION.
a,b
OS a,b a,b
OS
OS
a,b
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
a,b
AREA OF WORK
4 5 5.54.84.4
F
G
4.6 5.2
L1E b
L1 a
L1E b
L1 a
L1 a
L1E b
L1 a
L1 a
L1 a
L1 a
L1E b
L1 a
L1E b
L1 a
L1 a
L1E b
L1 a
L1E b
L1 a
L1 a
L1 a
L1 a
L1E b
L1 a
L1E b
L1 a
L1 a
L1E b
L1E b
L1 a
L1 a
L1E b
COMBINED
COMPUTER /
SERVER ROOM
BB 102
LIGHTING CONTROL PANEL
LIGHTING CONTROL PANEL
LIGHTING CONTROL PANEL
56-SP1
FIRE
SUPPRESSION
CONTROL PANEL
56-C7
56-C2
56-C6
56-CRAC-A 56-CRAC-B
56-CRAC-C
56-SWBD-UPS-A
56-SWBD-UPS-B
56-C3
L1 a
L1E b
L1 a
L1 a
L1E b
L1 a
L1E b
L1 a
L1 a
L1 a
L1E b
L1 a
L1 a
1 1 1 1 1 1 1
1 1 1
BB102
4 5 5.54.84.4
F
G
4.6 5.2
1 1
TYP.
a,b a,b a,b a,b a,b a,b a,b a,b a,b a,b a,b a,b a,b a,b a,b a,b a,b a,b
DP/56LS
X
DP/56LS
E-504
56-L1-5
X
DP/56LS
b a
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of
Construction and Facilities
Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
SPEES DESIGN BUILD
23830 PACIFIC HIGHWAY S. SUITE 203
KENT, WA 98032
/0
/2
:1
:4 a m
B
IM
/6
-2
-7
J B
V A
M O
J B
E H
R M
I U
D a ta C e n te r/
V A
S T
L
D C
E
L S
D B
.r v t
EL101
DATA CENTER - LIGHTING PLAN
WNM/MM JBB/JFO
100% CONSTRUCTION
DOCUMENTS
05/10/2024
657-21-709JBEHRM…
This is the start of the file's text. The full file is on GovTribe.