0001 Attachment 1 Technical Questions Received - CBOC Renovation 20230120.pdf
PDF 141 KB Posted
- Solicitation number
- 36C77623R0037
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C77623R0037 0003.pdf | ||
| 0002 Attachment 3 Past Performance Questionnaire.docx | DOCX document | |
| 36C77623R0037 0002.pdf | ||
| 0002 Attachment 2 Site Visit Itinerary and Instructions.docx | DOCX document | |
| 0002 Attachment 1 COVID-19 Safety Protocols 12-14-21.pdf | ||
| 36C77623R0037 0001.pdf | ||
| Attachment 3 Pinebrook Second Floor.pdf | ||
| Attachment 1 SOW CBOC Renovation - Brooksville.docx | DOCX document | |
| Attachment 5 SCA Wage Determination - Brooksville 20221213.pdf | ||
| Attachment 1 Appendix B - Basis for Design.docx | DOCX document | |
| Attachment 2 Pinebrook.pdf | ||
| 36C77623R0037_1.docx | DOCX document | |
| Attachment 1 Appendix A - Submission Review Tools.docx | DOCX document | |
| Attachment 4 Original_Clinic_Area.pdf | ||
| Attachment 1 Appendix C - Hazardous Materials.docx | DOCX document | |
| 36C77623R0037.docx | DOCX document |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Technical Questions
All below questions were asked by prospective offerors in regard to project 673-901 CBOC
Renovations.
• Within the SOW under Paragraph 2.3 Surveys and 2.4 Subsurface conditions each paragraph states these services are to be provided by the AE; however, within the RFQ
Para 5 – Primary Selection Criteria Professional Qualifications these positions are not listed as required disciplines for the team? Do we need to include these skill sets within our RFQ response?
o These skill sets can be covered as hired subcontractors and not an actual discipline for the team. In other words these specialties do not have to be a part of the AE team as employees, but can be a subcontractor performing these services.
This specific project will have very limited sitework as it appears in this first renovation as the funding is being locally managed. This is not a USACE or CFM
Project, for further information.
• In the Modifications to a Previous Notice, we found an error on page 9 - the last day to submit questions – Friday, January 16. Is this Friday the 20th?
o The last day for technical questions was January 16th, but late questions may be considered.
• The solicitation refers to an “Attached PPQ” on page 7 of 10 but I do not see it as an attachment. Can you provide me with a copy?
o An attachment for the Past Performance Questionnaire has been attached.
• Regarding Modification to a Previous Notice, page 5, second paragraph, would you like us to include the information for the Summary Page in section H of the SF330?
o All professional licenses/qualifications should be included in under the professional qualifications section of the SF-330.