Technical Question Tracking Sheet - Tampa.docx
DOCX document 128 KB Posted
- Attached to
- Y1DA--EHRM Infrastructure Upgrades Design Tampa Federal contract opportunity
- Solicitation number
- 36C77621R0121
About this file
This presolicitation notice seeks statements of qualifications from architecture and engineering firms for design services related to infrastructure upgrades at the Marion VA Medical Center in Marion, Illinois. The project scope involves upgrades to HVAC, electrical, IT, fiber optics, data cabling, and physical security to enable the facility's adoption of the Electronic Health Record Modernization system. The anticipated contract value is between $10-20 million. Responses are due by April 30, 2021 and the design completion period is 154 calendar days from award. This is a 100% set-aside for service-disabled veteran-owned small businesses. The selected firm will provide basis of design, schematic design, design development, contract documents, and construction period services.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C77621R0121 0006.docx | DOCX document | |
| 36C77621R0121 0005.docx | DOCX document | |
| S05 - Technical Question Tracking Sheet - Tampa - Final.docx | DOCX document | |
| 36C77621R0121 0004.docx | DOCX document | |
| SF330 Request - Tampa.docx | DOCX document | |
| 36C77621R0121 0003.docx | DOCX document | |
| S05 - Technical Question Tracking Sheet - Tampa.docx | DOCX document | |
| 36C77621R0121 0002.docx | DOCX document | |
| 36C77621R0121 0001.docx | DOCX document | |
| 36C77621R0121.docx | DOCX document | |
| PPQ - PR EHRM.docx | DOCX document | |
| SOW EHRM Tampa Bay - Final.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL QUESTIONS
AND RESPONSE TRACKING SHEET
EHRM Infrastructure Upgrade Design-Build – Tampa 36C77621R0121
PROJECT TITLE3
SOLICITATION #
| QUESTION # |
| QUESTION RECEIVE |
DATE
QUESTION ANSWERED
DATE
| CONTRACTOR QUESTIONS |
| VA RESPONSES TO QUESTIONS |
| 1 |
| 8.3.21 |
| 8.3.21 |
| Page 8 of the Presolicitation Notice lists the cutoff date for question submission as “2:00 PM ET ON THURSDAY, AUGUST 2, 2021.” As I’m not sure if the cutoff date was Monday, August 2nd, or if it is this coming Thursday, August 5th |
| Technical Question cut-off date is Thurday, August 5, 2021. |
| 2 |
| 8.3.21 |
| 8.3.21 |
| Page 2 of the Presolicitation Notice and page 10 of the SOW specify 295 calendar days for the period of performance for completion of design, but page 3 of the Presolicitation Notice has “212 calendar day period of performance.” Could you please confirm whether the period of performance is 295 calendar days or 212? |
| The Period of Performance is 212 days fromm the issuance of the Notice of Award. |
| 3 |
| 8.3.21 |
| 8.3.21 |
| On page 8 of the Presolicitation Notice, under #7, first bullet point, it states to submit one SF-330 via email to the Contract Specialist Kara Evert at Jason.schultz@va.gov. Could you please confirm if we are to submit SF 330s to Jason Schultz at the listed email, or if we should submit it to Kara Evert at another email address. |
| Please submit your sf330s to Jason Schultz at Jason.schultz@va.gov. |
| 4 |
| 8.5.21 |
| 8.5.21 |
| Will the VA be updating the SOW to reflect the 212 calendar day period of performance as it currently reflects 295 calendar days? |
SF330 request has been updated to 295 calendar day period of performance for the design completion begins with the issuance of the Notice of Award which is what is stated in the SOW.
| 5 |
| 8.5.21 |
| 8.5.21 |
| Is the VA requesting a resume for each of the key positions and disciplines listed under Factor 1 on page 4 of the presolicitation notice? (Architect, CADD Technician, RCDD, Estimator, Civil Engineer, Electrical Engineer, Environmental Engineer, Fire Protection Engineer, Industrial Hygienist, Mechanical Engineer, Plumbing, Project Manager, Quality Assurance, Structural Engineer, and Physical Security Specialist.) |
Yes, a resume is requested for the disciplines listed under professional qualifcation.
| 6 |
| 8.5.21 |
| 8.5.21 |
| If the VA is not requesting a resume for each of the key positions and disciplines listed under Factor on page 4 of the presolicitation notice, please clarify which resumes are required as a part of the SF 330 submission. |
| Please refer to answer #4 |
image1.jpeg image2.jpeg
File details come from the government source that posted it. Updated .