S02 RFQ Attachment Phasing Table - 1 page.pdf

PDF 106 KB Posted

Attached to
F108--(Service) PN: 636A6-24-107, Demo Lab Equipment & ACM Abatement (DM)
Solicitation number
36C26325Q0252
Issued by

About this file

This is a phasing table that outlines the schedule for asbestos abatement work at the Des Moines VA Medical Center, specifically for Rooms 1212 and 1210. The work is divided into three phases, with each phase following an identical sequence of activities.

Each phase includes mobilization of the abatement crew, installation of temporary barriers (2 days), establishment of exhaust ventilation and decontamination areas, demolition and removal of cabinets, countertops, and flooring with mastic (3-5 days), followed by cleanup and barrier breakdown (1-2 days). After each phase, there is a 5-6 week break for VA work including new floor installation and equipment validation. The total estimated duration is 68-87 working days (approximately 3.5-4.5 months) from notice to proceed. Phase 1 focuses on Room 1212, Phase 2 on Room 1210, and Phase 3 combines work in both rooms 1210/1212.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Room 1212 – Phase 1

Mobilize abatement crew

Put up temp barriers in work area 2 days

Establish exhaust ventilation, decon area

Demolish and remove cabinets

3-5 days Demolish and remove countertops

Demolish and remove flooring and mastic

Breakdown barriers, decon, exhaust – cleanup 1 – 2 days

Demobilize abatement crew

Break for VA work (new floor in, equipment validated) 5/6 weeks

Room 1210 – Phase 2

Mobilize abatement crew

Put up temp barriers in work area 2 days

Establish exhaust ventilation, decon area

Demolish and remove cabinets

3-5 days Demolish and remove countertops

Demolish and remove flooring and mastic

Breakdown barriers, decon, exhaust - cleanup 1 – 2 days

Demobilize abatement crew

Break for VA work (new floor in, equipment validated) 5/6 weeks

Room 1210/1212 – Phase 3

Mobilize abatement crew

Put up temp barriers in work area 2 days

Establish exhaust ventilation, decon area

Demolish and remove cabinets

3-5 days Demolish and remove countertops

Demolish and remove flooring and mastic

Breakdown barriers, decon, exhaust - cleanup 1 – 2 days

Final demobilize abatement crew

Estimated total duration from notice to proceed: 68-87 working days, approx. 3.5-4.5 mos