This is a phasing table that outlines the schedule for asbestos abatement work at the Des Moines VA Medical Center, specifically for Rooms 1212 and 1210. The work is divided into three phases, with each phase following an identical sequence of activities.
Each phase includes mobilization of the abatement crew, installation of temporary barriers (2 days), establishment of exhaust ventilation and decontamination areas, demolition and removal of cabinets, countertops, and flooring with mastic (3-5 days), followed by cleanup and barrier breakdown (1-2 days). After each phase, there is a 5-6 week break for VA work including new floor installation and equipment validation. The total estimated duration is 68-87 working days (approximately 3.5-4.5 months) from notice to proceed. Phase 1 focuses on Room 1212, Phase 2 on Room 1210, and Phase 3 combines work in both rooms 1210/1212.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Room 1212 – Phase 1
Mobilize abatement crew
Put up temp barriers in work area 2 days
Establish exhaust ventilation, decon area
Demolish and remove cabinets
3-5 days Demolish and remove countertops
Demolish and remove flooring and mastic
Breakdown barriers, decon, exhaust – cleanup 1 – 2 days
Demobilize abatement crew
Break for VA work (new floor in, equipment validated) 5/6 weeks
Room 1210 – Phase 2
Mobilize abatement crew
Put up temp barriers in work area 2 days
Establish exhaust ventilation, decon area
Demolish and remove cabinets
3-5 days Demolish and remove countertops
Demolish and remove flooring and mastic
Breakdown barriers, decon, exhaust - cleanup 1 – 2 days
Demobilize abatement crew
Break for VA work (new floor in, equipment validated) 5/6 weeks
Room 1210/1212 – Phase 3
Mobilize abatement crew
Put up temp barriers in work area 2 days
Establish exhaust ventilation, decon area
Demolish and remove cabinets
3-5 days Demolish and remove countertops
Demolish and remove flooring and mastic
Breakdown barriers, decon, exhaust - cleanup 1 – 2 days
Final demobilize abatement crew
Estimated total duration from notice to proceed: 68-87 working days, approx. 3.5-4.5 mos