The document is a Price Schedule Breakdown Sheet for a playground equipment replacement project (Project Number: 618-25-205). The sheet provides a comprehensive cost breakdown across multiple construction divisions, including General Building Construction, Mechanical and Electrical Systems, and Site Improvements. The breakdown is structured to capture costs for various project components such as general requirements, existing conditions, concrete, masonry, metals, wood, thermal protection, electrical, and site work.
The pricing template allows the contractor to itemize costs for each division and subtotal them into three main categories: General Building Construction, Mechanical and Electrical, and Site Improvements. Additional sections are provided for miscellaneous costs, profit, and overhead, with a final row for the Proposal Grand Total. This detailed pricing structure is part of a federal contract opportunity with the Department of Veterans Affairs Veterans Health Administration, specifically for replacing playground equipment at a Fisher House location, with a 120-day performance period from the Notice to Proceed.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Schedule Breakdown Sheet Project Title: Replace Playground Equip Project Number: 618-25-205 Contractor:
Division # Division Title Base Project 1 General Requirements 2 Existing Conditions 3 Concrete 4 Masonry 5 Metals 6 Wood, Plastics and Composites 7 Thermal and Moisture Protection 8 Openings 9 Finishes 10 Specialties 11 Equipment 12 Furnishings 14 Conveying Equipment Subtotal General Building Construction $
21 Fire Suppression 22 Plumbing 23 Heating, Ventilating and Air Conditioning 25 Integrated Automation 26 Electrical 27 Communications 28 Electronic Safety and Security Subtotal Mechanical and Electrical $
31 Earthwork 32 Exterior Improvements 33 Utilities 34 Transportation Subtotal Site Improvements $
Miscellaneous (Contractor shall identify any costs included)
Subtotal All Divisions & Miscellaneous (if any) $ Profit Overhead Proposal Grand Total $