36C26322Q0374 0001 SF30 RESPONSE TO SOLICITATION QUESTIONS.pdf

PDF 291 KB Posted

Attached to
H359--Arc Flash Studies and Documentation Findings
Solicitation number
36C26322Q0374
Issued by

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 8

None

Department of Veterans Affairs

NETWORK 23 CONTRACTING OFFICE

2501 W. 22nd St.

Sioux Falls SD 57105 John Becker john.becker3@va.gov

Department of Veterans Affairs

NETWORK 23 CONTRACTING OFFICE

2501 W. 22nd St.

Sioux Falls SD 57105

To all Offerors/Bidders

36C26322Q0374

04-15-2022

X

X X

4/22/2022, 3:00 PM Central Time

X one (1)

The purpose of this solicitation amendment is to respond to solicitation questions and to affirm evaluation factors provided in solicitation FAR Clause 52.212-2, Evaluation-Commercial Products and Commercial Services.

See Attachment for response to solicitation questions.

Any evaluation factors identified in the Statement of Work are not applicable for evaluation of quotes. Solicitation FAR Clause 52.212-2 Evaluation-Commercial Products and Commercial Services will be used to evaluate offers.

Offerors shall acknowledge receipt of this Amendment.

John Becker Contracting Officer

VA-VHA-2020-BEE57D1B

REPONSE TO SOLICITATION QUESTIONS:

Question: Facility Response

1. Are the Arc Flash Studies required to be performed using EasyPower software, or is it permissible to use another software such as SKM? It states EasyPower, but further down in the document it suggests others may be used.

Omaha/Grand Island VA Hospital:

SKM or similar products can be used (due to VA networking policies facility will request both autocad (most recent version) and pdf files for arc flash studies performed) as SKM likely has an annual subscription for facility updates that are made.

Iowa City VA Hospital:

No

Sioux Falls VA Hospital:

Other software is allowed as long as the report is complete with all calculated values per the directive.

2. Are we required to show at least three prior contracts, or five? In one place it states three, but further down in the document it states five.

As listed in the Solicitation’s Addendum to FAR 52.212-1, Instructions to Offerors, Offeror shall submit the names of the Contracting Activity and Medical Facility, point of contact, telephone number, and email for a minimum of two (2) recent and relevant jobs that show past performance information on the same type of requirement as proposed in this solicitation. If the offeror has no past performance information on this type of work, the offeror shall specifically state that it has no such past performance.

The Government reserves the right to obtain past performance information from other sources.

3. For the Arc Flash scope at Omaha and Grand Island, the document references repairs, and replacement parts. This is typically not part of scope for an Arc Flash Study, but rather something that would be included where there is testing and maintenance services being performed. Is the respondent to include provisions for repair in the Arc Flash Study services?

Omaha/Grand Island VA Hospital:

Repairs and replacement parts are to be provided as recommended by the contractor in the form of a quote (should it exceed pricing of the associated CLIN). The Contractor shall provide all replacement parts needed to keep the system in operating condition as originally designed by the manufacturer. Parts may be repaired or replaced, as the contractor deems appropriate, so long as amount listed in CLINs cited in Price/Cost Schedule are not exceeded. No used parts will be used to repair this equipment. If additional repairs are required to make the equipment operational, Contractor shall provide the nature of the repair and a budgetary cost estimate for such repairs in writing.

4. It is our understanding that the court’s The FAR Clause to mandate COVID 19

Question: Facility Response decision to block the vaccine mandate for federal contractors has not yet been overturned. Is proof of vaccine required for this contract, aside from medical or religious exemptions?

Vaccine Mandate is not included in this contract. However, COVID-19 information was included to reflect that VA Hospitals are screening for COVID upon entrance to VA facilities.

5. Will the facility provide a “Qualified” electrical person to assist in locating and identifying equipment for inclusion in the Arc Flash Studies?

Omaha/Grand Island VA Hospital:

Omaha facility has 4 electricians and Grand Island has 1 electrician that can offer support as a “qualified” electrical person.

Iowa City VA Hospital:

Yes

Sioux Falls VA Hospital:

VA will have staff onsite during all testing including throughout the night. Engineering and electrical teams will be onsite to provide room access and directions. VA personnel will not complete any of the work.

6. Will the facilities permit removing covers on energized equipment for data collection purposes, by a ‘Qualified’ person utilizing proper PPE, or does the facility(s) require all equipment to be de-energized before removing covers?

Omaha/Grand Island VA Hospital:

Due to risk of bolts, hardware or other materials coming in contact with the bus, it is requested that the contractor “qualified” person has PPE to match that of the incident energy. If exposed parts are located behind the covers, the units shall be de-energized and all conductive material removed or if improper signage on exterior of panel it should be de-energized. NEC, and NFPA 70 specify exact requirements that the VA is requesting be followed.

Iowa City VA Hospital:

Proper PPE do not have to De-Energize.

Sioux Falls VA Hospital:

Contractors must meet NFPA/NEC guidelines for PPE requirements. Panel covers may be removed for visual inspection. No hot work is authorized unless required for testing.

7. Is there a list of equipment (switchgear, panelboards, etc) for the Omaha, Grand Island, and Sioux Falls facilities?

Omaha/Grand Island VA Hospital:

Yes (see Attachment)

Sioux Falls VA Hospital:

Previous studies and one lines are available for reference.

8. Are existing single lines available for review to help quantify the size and scope of the Arc Flash studies the Omaha, Grand Island, and Sioux Falls facilities?

Omaha/Grand Island VA Hospital:

Yes (Omaha/Grand Island), please note that often these one line diagrams have not been updated and therefore may not be all inclusive.

Question: Facility Response Iowa City VA Hospital:

Yes

Sioux Falls VA Hospital:

Yes they are available

9. What format are the single lines to be provided in for the Arc Flash studies (CAD, pdf, etc.)?

Omaha/Grand Island VA Hospital:

CAD and PDF

Iowa City VA Hospital:

Both

Sioux Falls VA Hospital:

VA has CAD and PDF versions

10. Will the contractor be required to deliver and install the new Arc Flash Labels, and remove the old labels, or will the new labels be turned over for installation by facility personnel?

Omaha/Grand Island VA Hospital:

Contractor will be responsible to deliver and install new Arc Flash labels

Iowa City VA Hospital:

Either

Sioux Falls VA Hospital:

Contractor must deliver, removed existing, and install new labels.

11. Does the substation only feed the hospital?

Iowa City VA Hospital:

No

12. What is the size of the substation? Iowa City VA Hospital:

13.2

13. The current generators, do they service the whole hospital?

Iowa City VA Hospital:

Yes

14. Will a standby generator be needed in case the main generator fails? Are we providing?

Iowa City VA Hospital:

No and No

15. For Sioux Falls and Omaha/Grand Island, the statement of works have technical selection factors paragraphs that differ from the solicitation technical factors paragraph. I assume the only factors that will be used will be from the solicitation

E.7 52.212-2 EVALUATION—

COMMERCIAL PRODUCTS AND

COMMERCIAL SERVICES (NOV 2021)

paragraph?

Only the evaluation factors listed in FAR 52.212-2 will be used to evaluate Quotes.

16. Additionally, the technical factors require registration for each state the work is performed whereas FAR 52.236-25 Requirements for Registration of Designers is an engineer is registered in any state.

The Solicitation does not include FAR Clause 52.236-25 and therefore, registration is required as identified in FAR 52.212-2. Many of the states have reciprocal licensing with other states.

OMAHA EQUIPMENT LISTING

Generators # Brand Model # Serial # Location Nameplate

Power Voltage

1 CATERPILLAR 3412 81Z05946 /

6FA04047

Bld. 1 – Rm 1269A

509 KW 120/208

2 CATERPILLAR 3412 81Z04484 /

6FA03501

Bld. 1 – Rm 1269A

465 KW 120/208

3 CATERPILLAR D 343 62B12357 Bld. 2 – Boiler Plant

280 KW 480

4 ONAN DFEG A090230928 Bld. 15 – Outside 350 KW 480 5 GENERAC 2113614 SG0130 Bld. 9 – Outside 130 KW 277 6 CATERPILLAR C 175 WYB02568 Bld. 24A 3000 KW 13800 7 CATERPILLAR C 18 T3400494 Bld. 101 –

Outside

671 KW 480

Transfer Switches

# Brand Model # Serial # Location 1 Caterpillar CBTS 3035429 Bld. 101- G506 2 Caterpillar CBTS TSC03370 Bld. 101- G506 3 Caterpillar CBTS TSC03371 Bld. 101- G506 4 Caterpillar CBTS TSC03372 Bld. 101- G506 5 Cummins BTPCC-7530032 L080226163 Bld. 1 – Rm 5th Fl. Micro 6 Caterpillar CBTS 2504090 Bld. 1 – Rm 1269 7 Caterpillar CBTS 2504263 Bld. 1 – Rm 1269 8 Eaton ATH3FDA30100ESU 074819 Bld. 1 – Rm 1269 9 Eaton ATV3NBA30800XSU 074929 Bld. 1 – Rm 1269 10 Eaton ATC3C5X30800BSU 018742 Bld. 1 – Rm 1269 11 Eaton ATC3C5X30800BSU 019072 Bld. 1 – Rm 1269 12 Eaton ATC3C5X30800BSU 019018 Bld. 1 – Rm 1269 13 Eaton ATC3C5X30800BSU 018709 Bld. 1 – Rm 1269 14 Russectric RTSO3-ATA4003CMOH-REL 38410-1A Bld. 1 – Rm 1269 15 Russectric RTSO3-ATA8003CMOH-REL 38410-2A Bld. 1 – Rm 1269 16 Zenith ZBTSOOBOOO10F 7019308 Bld. 15 - Rm R105 17 Zenith ZBTSOOBOOO22F 7019310 Bld. 15 – Rm R105 18 Asco 940326095XC 30462569-001 Bld. 17 – Electrical Rm 19 Asco H3003600N7C 201092-5 Bld. 2 20 Caterpillar C175 SWG40879 Bld. 24A 21 Zenith ZB4DB02241-07C601X 151645532 Bld. 9 – Rm B03 22 Zenith ZB4DB02241-07C601X 2524317-10-1 Bld. 9 – Rm B03

Transformers

# Brand /

MVA

Serial # Type Location Mineral Oil

1 PRO / 0.3 M09G19015 Pad-mounted Bld. 20 – Outside 281 gal 2 PRO / 0.3 M09G19016 Pad-mounted North Bld. 6 – Outside 281 gal

3 PRO / 0.3 M09G19017 Pad-mounted Bld. 6 – Outside 281 gal

4 CP / 0.225 2050000713 Pad-mounted Bld. 9 – Outside 136 gal 5 CP / 0.225 2050000764 Pad-mounted Bld. 9 – Outside 157 gal

6 GE / 0.75 M154751 Substation Bld. 17 – Rm A104 145 gal

7 GE / 1.0 M154753B Substation Bld. 17 – Rm A104 165 gal

8 GE / 1.0 M154753A Substation Bld. 17 – Rm A104 165 gal

9 GE / 0.75 M154752 Substation Bld. 1 – Rm 1269 138 gal

10 WH / 0.75 PCT1773-0101 Substation Bld. 1 – Rm 1269 139 gal

11 EA / 1.5 1650008964 Substation Bld. 17 – Outside 292 gal

12 EA / 0.75 1950013801 Substation Bld. 17 – Outside 227 gal

Switchgears and related electrical equipment

# Description & Brand Serial # Location Voltage

1 MCC General Electric L-700415 Bld. 1 – B024 208

2 Eaton PRL4 191016T Bld. 15 – R105 480/277

3 Eaton PRL4 1910300T Bld. 15 – R105 480/277

4 General Electric V80912 Bld. 1 – 1269 208

5 Westinghouse V77927 Bld. 1 – 1269 208

6 Eaton 5ARMLSIG Bld. 101 – G506 480/277

7 Eaton SB612 Bld. 101 – G506 480/277

8 Federal Pacific MCC 2658D2430 Bld. 2 480/277

9 Federal Pacific MCC (Dry) 28548-001 Bld. 2 13800

10 General Electric Substation 1 AK48914 Bld. 17 480

11 General Electric Substation 2 AK48916 Bld. 17 208

12 General Electric Substation 3 AK48917 Bld. 17 208

13 General Electric E9000 00384-01 Bld. 30 480

14 Westinghouse (MCC1) 4713A99H11 Bld. 25 – B716 208

15 Westinghouse (EMCC1) 4713A99H11 Bld. 25 – B716 208

16 General Electric Main Switchgear #1 (0329A9138)

ReQ 413- 95916

Bld. 24 – West 13800

17 General Electric Main Switchgear #2 (0329A9138)

ReQ 413- 95916

Bld. 24 – East 13800

GRAND ISLAND EQUIPMENT LISTING

Generators # Brand Model # Serial # Location Electrical Outputs Voltage 1 CATERPILLAR 3412 38S06458 Bld. 17 370 KW 120/208 2 CATERPILLAR D333 66D04921 Bld. 18 100 KW 208

3 TRADEWINDS TP125E-60T3FGT 739883-

1016 Bld. 7 97 KW 208

Transfer Switches

# Brand Model # Serial # Location 1 ASCO 7000 (400 amp) 584176-004 Bld. 17 2 ASCO 7000 (260 amp) 276774-001 Bld. 17 3 ASCO 7000 (400 amp) 584176-002 Bld. 17 4 ASCO 7000 (600 amp) 584177RE Bld.17 5 ASCO 7000 (400 amp) 584176-003 Bld. 17 6 ASCO 7000 (400 amp) 584176-001 Bld. 18 7 ASCO Model 940 (400 amp) 896758001 Bld. 17 8 Zenith ZBTSH40EC-4 (400 Amp) 243882 Bld. 17 9 Zenith ZBTSH40EC-4 (400 Amp) 243883 Bld..17 10 Zenith ZTS2L22EC-4 (225 Amp) 1326427 Bld. 17 11 CAT CTGD (225 Amp) TSB05462 Bld. 17

Transformers

# Brand /

MVA

Serial # Type Location Mineral Oil

1 GE / 1.0 Q5542790-TPP Pad-mounted South Bld. 17 – Outside 453 gal

2 GE / 1.0 Q542791-TPP Pad-mounted South Bld. 17 – Outside 455 gal

3 GE / 0.15 Q544244-TRP Pad-mounted West Bld. 11 & 4 – Outside 310 gal

4 GE / 0.225 Q54482-TRP Pad-mounted East Bld. 18 – Outside 260 gal

5 +ABB / 1.5 99J814159 Pad-mounted Southeast Bld. 7 – Outside 423 gal

# Description & Brand Location Voltage 1 MCC General Electric 8000 Line Control Center – 5 Sections Bld. 7 480 2 MCC Control Center Siemens – 2 Sections Bld. 7 480 3 MDD GE Power Break 2000 A Bld. 7 480/277 4 MDD Siemens 2000 A Bld. 18 208/120 5 GE Switch Board – 6 Section Bld. 17 208/120 6 GE Switchgear Power VAC – 2 sections 13500, 2 – sections Bld. 17 208/120 7 Siemens Switchboard 17-Ndp1 – 2 Sections Bld. 17 208 8 Siemens Switchboard 17-Ndp2 – 2 Sections Bld. 17 208 9 Siemens Switchboard 17-Ndp3 – 2 Sections Bld. 17 208 10 Siemens MDD 17 EDP Bld. 17 208

11 Siemens LDP 17 EDP Bld. 17 208 12 Siemens LSDP 17 EDP Bld. 17 208 13 Siemens GDP 17 EDP Bld. 17 208

File details come from the government source that posted it. Updated .