These are detailed mechanical engineering drawings for the interstitial and floor plans of Building 500, specifically focusing on the 5th floor's north and west wings of a healthcare facility. The drawings provide comprehensive technical schematics for HVAC systems, including air handling units, ductwork, piping, circulating pumps, air filters, water coils, steam humidifiers, and various mechanical equipment locations and connections. The technical drawings include multiple views such as floor plans, sections, control diagrams, and detailed equipment placement layouts, with gridded reference points and extensive annotations describing equipment specifications, installation requirements, and system interconnections. The drawings appear to be part of a fully sprinkled building design, with intricate details on mechanical infrastructure placement and routing throughout the facility's interstitial spaces.

View the file

Other files

File Type Posted
36C26225Q0986 0002.docx DOCX document
36C26225Q0986 0001.docx DOCX document
36C26225Q0986.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Model the humidifier and piping

Pump back here

RISER LOCATION DOES NOT

LINE UP WITH DRAWING

500-H-1.2 LOCATION. CHS/R

LINES ARE FLIPPED ON THAT

DRAWING IN COMPARISON TO

HOW THEY SHOULD BE

ALLIGNED BASED ON THIS

DRAWING

LOCATION OF CHS/R

RISERS ON DRAWING

500-H -1.2

LOCATION OF

RISERS ON

DRAWING

500-H-1.1A