This document outlines the requirements for a solar panel maintenance and repair contract for the Department of Veterans Affairs. Over the course of three years, the contract involves replacing 150 broken solar panels at medical campuses in North Hills, California and Los Angeles. The contractor must also provide semi-annual servicing for solar panels and trackers at these locations, including cleaning, inspections, torqueing terminals and fasteners, and filter replacement. Emergency repairs are not priced as they will be handled on an as-needed basis. Questions were asked and answered regarding the current state of inverters and warranties, responsibilities for parts, requirements for cleaning and repairs, module counts at each location, and details about site access and outlets.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C26223Q0213_1.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7.
ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF
PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE
OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:
Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERE
D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED
STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF
CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF
SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 691-23-1-5091-0015 36C262 Department of Veterans Affairs Network Contracting Office 22 4811 Airport Plaza Drive Suite 600 Long Beach CA 90815 36C262 Department of Veterans Affairs Network Contracting Office 22 4811 Airport Plaza Drive Suite 600 Long Beach CA 90815 To all Offerors/Bidders
36C26223Q0213 03-09-2023
X X X
IAW FAR 13.5,
this solicitation amendment is for response to inquiries provided to the contracting entity on or before 03/08/2023 at 16:00/PST.
As a result the soli citation close date remains 03/16/2023 at 16:00/PST Attn: Edward Condreay, 36C26223Q00213, edward.condreay@va.gov
No other changes have been made to the solicitation.
Helena Roba Service Branch III, Service Chief Questions for solar maintenance contract:
1. Current status of each of the array controlled by an inverter? Specifically, are all inverters running? If not, can you provide a short synopsis of current issues?
All inverters are operating.
1. Have all the warranties for the inverters expired?
Yes all warranties have expired. The Satcon and Solaron inverter warranties have expired and the inverters are not manufactured any longer.
The SMA inverter warranties have expired.
1. Who is administering and managing warrantied parts, the contractor or COR?
Refer to response to question 2.
1. The Ground mount solar system has a Sunpower tracker system. Should the contractor also include the maintenance of the tracker system in their proposal.
Yes. Contractor shall also include in their proposal the proper maintenance of the Sunpower tracker system. Inspect and verify proper operation tracker system And tracker controllers. Lubricate tracker motors and screw jacks semi- annually.
Contractual Questions
1. The solicitation mentions 150 broken modules. To ensure correct interpretation, should my bid reflect the replacement of 150 broken modules or is 150 modules a projection for the year and my bid should reflect replacing a single module (per occurrence)?
Yes contractor should replace 150 broken modules. The Heliene 72P-325 and Sunpower E20/327 solar panels are not manufactured any longer. Contractor shall provide all labor, material, necessary mounting support and electrical wiring modifications to replace with equivalent solar panels.
1. Should my bid on the 150 PV Modules include parts and labor or just labor and the cost for the PV Module is submitted to COR for approval?
Bid should include all parts, labor, material and modifications as required. Refer to response to Contractual Question 1.
1. I assume all incidental maintenance e.g., discrepancies found during “Normal Services” are submitted to COR for approval along with contractor cost (parts/labor) for repairing said discrepancy?
Contractor shall include and take care of all normal incidental maintenance requirements as part of the bid.
1. Please confirm “PV Module Washing” is not a part of this solicitation, but as an addendum to the contract when required (hence no cost for cleaning should be included in my bid)?
Per Paragraph 5.2.1 – Contractor shall include in proposal all material and labor required to provide for solar cleaning services twice per year for the VA Sepulevda Campus and four times per year for the LA ACC Medical Center.
1. Please confirm that all combiner and inverter fuses and inverter filter costs are the contractor’s responsibility and should be included in the contractor’s bid.
Correct – contractor shall provide for all material and labor for all combiner and inverter fuses and inverter filters.
1. Section 5.1.1 (Inverter & Inverter Enclosure Cleaning) does not directly mention a schedule. Are these services to be performed annually with 5.1.2 or are these services performed more than once a year?
Section 5.1.1 refers to Inverter manufacturer maintenance requirements – contractor shall have experience in maintaining the Satcon and Solaron inverters and perform all maintenance requirements every six months torque all terminals, fasteners electrical power connections on inverters and all combiners, replace air filters, check condition of AC and DC surge suppressors, record all operating voltages and current readings, record all inspections completed to turn it in to the VA COR.
1. There are no projected hours for “0002 Emergency Repairs”. How are we supposed to bid this line item?
0003 Emergency Repair – Contractor does not have to include a price for this item.
Cleaning Questions
1. Please provide a total module count for each location.
Sunpower E20/327 solar panel 12,128 Solar Panels.
At Ground mount next to Building 7 Array 1 has 322 Kyocera KD240GX-LPB modules and 228 Heliene 325W 72PIFD1701USA panels.
Number of solar panels at Parking Lot 99 518 solar panels Number of solar panels at Parking Lot F 2,212 Kyocera 245GX-LFB
1. On buildings with solar arrays, are there any water spickets and 120VAC electrical outlets on or near the roof?
No spickets, no outlets. Contractor shall use DI water for cleaning solar panels and provide long extension cords.
4.. On buildings with solar arrays, are there any building internal or external roof access points (roof access ladders) to rooftops?
Yes There is access to the roof.
1. On carports, are there any water spickets and 120VAC electrical outlets on or near each of the carports?
No. spickets and no outlets. Contractor shall provide water portable water tank, DI water, and proper lifts. Coordinate with VA COR for weekend cleaning of solar panels for the carports. Contractor shall conserve water.
Please delete from SOW:
1.5.13 Other Direct Costs: “Note: The VA does have spare PV modules, also some of the inverters ware not being used so that contractor can coordinate with the VA COR in using for spare parts.”