Attachment 24 - Section 23 08 00 Commissioning HVAC.pdf

PDF 86 KB Posted

Attached to
1SE Remodel- Pharmacy Expansion & Waiting - Project: 664-15-412
Solicitation number
36C26223B0014_1
Issued by

About this file

This document provides specifications for commissioning HVAC systems on a federal construction project. It details requirements for inspecting HVAC installation, completing pre-functional checklists, conducting contractor tests, and performing systems functional performance tests. The commissioning process will be managed by an appointed Commissioning Agent and involves verifying that HVAC systems, subsystems, and equipment are installed correctly and operate as intended. The related federal contract opportunity is for remodeling a pharmacy and waiting area at a Department of Veterans Affairs medical center, including commissioning of HVAC systems as described in the specifications.

View the file

Other files

File Type Posted
Award Notice (Contract 36C26223C0285).pdf PDF
Attachment 37 - I-S16_1st Floor Struct Interstitial.pdf PDF
Attachment 23 - Section 02 82 13.19 Asbestos Floor.pdf PDF
Attachment 19 - Structural Bldg 1 - As Built (3 of 4).pdf PDF
Attachment 10 - Section 28 31 00 Fire Detection Alarm.pdf PDF
Attachment 22 - Section 02 82 13.13 Glovebag Asbestos.pdf PDF
Attachment 3 - 1st Floor Interstitial Plan (As Built).pdf PDF
Attachment 4 - Basement Interstitial Plan (As Built).pdf PDF
Attachment 33 - D1CEXA (Photo 5 of 6).JPG JPG image
Attachment 36 - I-S71 thru I-S77 Bldg 1 (As Built).pdf PDF
Attachment 19 - Structural Bldg 1 - As Built (1 of 4).pdf PDF
Attachment 20 - Section 01 35 26 Safety Requirements.pdf PDF
Attachment 21 - Section 02 82 11 Asbestos Abatement.pdf PDF
Attachment 9 - Section 21 13 13 Wet-Pipe Sprinkler Sys.pdf PDF
Attachment 14 - Bldg 1 - 1st Floor FATC-I1_Inter Cat.pdf PDF
Attachment 39 - PP205 - Partial 5th Floor Plumbing.pdf PDF
Amendment 0002 (SF30) - Solicitation 36C26223B0014.pdf PDF
Attachment 7 - Section 01 45 00 Quality Control.pdf PDF
Attachment 18 - 1st Floor Plan Fully Sprinkler.pdf PDF
Attachment 30 - D1CEXA (Photo 2 of 6).JPG JPG image
Attachment 35 - I-S129_Bldg 1 Seismic (As Built).pdf PDF
Attachment 34 - D1CEXA (Photo 6 of 6).JPG JPG image
Attachment 26 - VA SD Master Finishes Legend.pdf PDF
Attachment 40 - P301 Details_Pantry-Hanger Rod.pdf PDF
Attachment 25 - Section 23 09 23 Direct-Digital Cntrl.pdf PDF
RFI Notice - Solicitation No. 36C26223B0014.pdf PDF
Attachment 8 - Section 01 91 00 General Commissioning.pdf PDF
Attachment 17 - Facility Fire Protection Study.pdf PDF
Attachment 29 - D1CEXA (Photo 1 of 6).JPG JPG image
Attachment 16 - Partial 1st Flor Power Remodel Plan.pdf PDF
Attachment 5 - Section 11 53 23 Lab Refrige.pdf PDF
Attachment 2 - VHA Master Specs-Table of Contents.pdf PDF
Attachment 1 - General Requirements-Table of Contents.pdf PDF
Attachment 11 - Physical Security Design Manual.pdf PDF
Attachment 15 - Fire Sprinkler Valves_Basement Level.pdf PDF
Attachment 32 - D1CEXA (Photo 4 of 6).JPG JPG image
Attachment 31 - D1CEXA (Photo 3 of 6).JPG JPG image
Attachment 28 - Wireframe Drawing.pdf PDF
Attachment 6 - 5th Floor Demo Plan_FV Photos.pdf PDF
Attachment 19 - Structural Bldg 1 - As Built (2 of 4).pdf PDF
Attachment 27- 5th Floor Plan Fully Sprinkler.pdf PDF
Attachment 19 - Structural Bldg 1 - As Built (4 of 4).pdf PDF
Attachment 13 - Equipment and Accessories Schedule.pdf PDF
Attachment 38 - I-S19_1st Floor Struct Interstitial.pdf PDF
Attachment 12 - Haz Mat Inspection Report.pdf PDF
Amendment 0001 (SF30) - Solicitation 36C26223B0014.pdf PDF
Pre-Bid Site Visit_Sign-In Sheet.pdf PDF
Attachment D (File 3 of 10) - 02-ARCH.pdf PDF
Attachment B - Wage Determination.pdf PDF
Attachment F - Limited Lead (XRF) Survey Report.pdf PDF
Show 40 more

Latest 50 of 63 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

03-01-23

23 08 00 - 1

SECTION 23 08 00

COMMISSIONING OF HVAC SYSTEMS

SPEC WRITER NOTES:

1. Delete between // -- -- // if not applicable to project. Also delete any other item or paragraph not applicable in the section and renumber the paragraphs.

2. Provide the year of latest edition to each publication given in Article 1.7

APPLICABLE PUBLICATIONS.

PART 1 - GENERAL

1.1 DESCRIPTION

A. The requirements of this Section apply to all sections of Division 23.

B. This project will have selected building systems commissioned. The complete list of equipment and systems to be commissioned is specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS. The commissioning process, which the Contractor is responsible to execute, is defined in Section 01 91 00 GENERAL COMMISSIONING REQUIRMENTS. A

Commissioning Agent (CxA) appointed by the VA will manage the commissioning process.

1.2 RELATED WORK

A. Section 01 00 00 GENERAL REQUIREMENTS.

B. Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

C. Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.

D. Section 23 05 41 NOISE AND VIBRATION CONTROL for HVAC PIPING AND

EQUIPMENT.

E. Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC.

F. Section 23 09 23 DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC.

1.3 SUMMARY

A. This Section includes requirements for commissioning the HVAC systems of the related subsystems and equipment. This Section supplements the general requirements specified in Section 01 91 00 GENERAL

COMMISSIONING REQUIREMENTS.

B. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for more details regarding processes and procedures as well as roles and responsibilities for all Commissioning Team members.

1.4 DEFINITIONS

A. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for definitions.

23 08 00 - 2

1.5 COMMISSIONED SYSTEMS

A. Commissioning of a system or systems specified in Division 23 is part of the construction process. Documentation and testing of these systems, as well as training of the VA’s Operation and Maintenance personnel in accordance with the requirements of Section 01 91 00

GENERAL COMMISSIONING REQUIREMENTS and of Division 23, is required in cooperation with the VA and the Commissioning Agent.

B. The Facility HVAC systems commissioning will include the systems listed in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.

1.6 SUBMITTALS

A. The commissioning process requires review of selected Submittals that pertain to the systems to be commissioned. The Commissioning Agent will provide a list of submittals that will be reviewed by the

Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to Section 01 33 23 SHOP

DRAWINGS, PRODUCT DATA, and SAMPLES for further details.

B. The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL

COMMISSIONING REQUIREMENTS.

SPEC WRITER NOTE: Insert the year of approved latest editions of the publications between the brackets and delete the brackets //----// if applicable to this project.

1.7 APPLICABLE PUBLICATIONS

A. The following publications form a part of this specification to the extent indicated by the reference thereto. In text the publications are referenced to by the acronym of the organization.

B. Department of Veterans Affairs (VA):

PG 18-10 //2007//.......Mission Critical Facilities - DRAFT

PG 18-10 //2007//.......Life-Safety Protected Facilities - DRAFT

C. American Society of Heating, Refrigerating and Air Conditioning

Engineers, Inc. (ASHRAE):

HANDBOOK //2019//.......HVAC Applications ASHRAE Handbook, Chapter 39, Testing, Adjusting, and Balancing, Chapter 44, HVAC Commissioning and Chapter 49, Sound and

Vibration Control

HANDBOOK //2017//.......HVAC Fundamentals ASHRAE Handbook, Chapter 8, Sound and Vibration

23 08 00 - 3

D. Associated Air Balance Council (AABC):

7th Edition //2016//....AABC National Standards for Total System

Balance

E. National Environmental Balancing Bureau (NEBB):

9th Edition //2019//....Procedural Standards for Testing, Adjusting, Balancing of Environmental Systems

3rd Edition //2015// ...Procedural Standards for the Measurement of

Sound and Vibration

2nd Edition //2019// ... Standard for Whole Building Technical

Commissioning of New Construction

F. Sheet Metal and Air Conditioning Contractors National Association

(SMACNA):

006//2006//.............HVAC Duct Construction Standard – Metal and

Flexible Duct

3rd Edition //2005// ... HVAC Systems Testing, Adjusting and Balancing

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.1 CONSTRUCTION INSPECTIONS

A. Commissioning of HVAC systems will require inspection of individual elements of the HVAC systems construction throughout the construction period. The Contractor shall coordinate with the Commissioning Agent in accordance with Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS and the Commissioning plan to schedule HVAC systems inspections as required to support the Commissioning Process.

3.2 PRE-FUNCTIONAL CHECKLISTS

A. The Contractor shall complete Pre-Functional Checklists to verify systems, subsystems, and equipment installation is complete and systems are ready for Systems Functional Performance Testing. The

Commissioning Agent will prepare Pre-Functional Checklists to be used to document equipment installation. Refer to Sections 23 05 41 NOISE

AND VIBRATION CONTROL for HVAC PIPING AND EQUIPMENT, Section 23 05 93

TESTING, ADJUSTING, AND BALANCING FOR HVAC and Section 23 09 23 DIRECT-

DIGITAL CONTROL SYSTEM FOR HVAC requirements. The Contractor shall complete the checklists. Completed checklists shall be submitted to the VA and to the Commissioning Agent for review. The Commissioning

Agent may spot check a sample of completed checklists. If the

Commissioning Agent determines that the information provided on the checklist is not accurate, the Commissioning Agent will return the

23 08 00 - 4 marked-up checklist to the Contractor for correction and resubmission.

If the Commissioning Agent determines that a significant number of completed checklists for similar equipment are not accurate, the

Commissioning Agent will select a broader sample of checklists for review. If the Commissioning Agent determines that a significant number of the broader sample of checklists is also inaccurate, all the checklists for the type of equipment will be returned to the Contractor for correction and resubmission. Refer to SECTION 01 91 00 GENERAL

COMMISSIONING REQUIREMENTS for submittal requirements for Pre-

Functional Checklists, Equipment Startup Reports, and other commissioning documents.

3.3 CONTRACTORS TESTS

A. Contractor tests as required by other sections of Division 23 shall be scheduled and documented in accordance with Section 01 00 00 GENERAL

REQUIREMENTS. All testing shall be incorporated into the project schedule. Contractor shall provide no less than 7 calendar days’ notice of testing. The Commissioning Agent will witness selected

Contractor tests at the sole discretion of the Commissioning Agent.

Contractor tests shall be completed prior to scheduling Systems

Functional Performance Testing.

3.4 SYSTEMS FUNCTIONAL PERFORMANCE TESTING:

A. The Commissioning Process includes Systems Functional Performance

Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The Commissioning Agent will prepare detailed Systems

Functional Performance Test procedures for review and approval by the

Resident Engineer. The Contractor shall review and comment on the tests prior to approval. The Contractor shall provide the required labor, materials, and test equipment identified in the test procedure to perform the tests. The Commissioning Agent will witness and document the testing. The Contractor shall sign the test reports to verify tests were performed. See Section 01 91 00 GENERAL

COMMISSIONING REQUIREMENTS, for additional requirements.

3.5 TRAINING OF VA PERSONNEL

A. Training of the VA operation and maintenance personnel is required in cooperation with the Resident Engineer and Commissioning Agent.

Provide competent, factory authorized personnel to provide instruction

23 08 00 - 5 to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. Contractor shall submit training agendas and trainer resumes in accordance with the requirements of Section 01 91 00 GENERAL COMMISSIONING

REQUIREMENTS. The instruction shall be scheduled in coordination with the VA Resident Engineer after submission and approval of formal training plans. Refer to Section 01 91 00 GENERAL COMMISSIONING

REQUIREMENTS and Division 23 Sections for additional Contractor training requirements.

----- END -----