This is Amendment 0002 to Solicitation 36C26127Q0067, extending the offer due date and providing answers to vendor inquiries regarding circuit breaker and feeder testing services at the Ioannis A. Lougaris VA Medical Center (Reno) in Nevada.

The solicitation is a total Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside under NAICS 238210 with a 75 percent subcontracting limitation for special trade construction contractors (VAAR 852.219-75(c)(iii)). The revised offer deadline is November 20, 2026 at 12:00 PM PST, with an optional site visit scheduled for November 5, 2026 at 1:00 PM PST at the Reno VAMC front entrance of Building 12. Questions must be submitted no later than November 16, 2026 at 12:00 PM PST to alex.arter@va.gov. The Department of Veterans Affairs Network Contracting Office (NCO 21) anticipates award within 2-3 weeks after the due date, with Notice to Proceed (NTP) intended immediately following award. The scope includes testing of 11 MV switches, 10 MV transformers, 477 circuit breakers, 570 feeder cables, and 27 LV transformers, with protective relay testing and arc-flash label updates (professionally engraved with associated room numbers). All testing must be performed during off-hours (6:00 PM to 6:00 AM), weekends, and federal holidays per SOW 8.6, following ANSI/NETA MTS and VHA Directive 1028 standards. Invoicing may be submitted in two installments—one following field testing acceptance and one following acceptance of the coordination study and final report. The contractor must be certified as a SDVOSB at time of offer and provide a signed VAAR 852.219-75 certificate.

View the file

Other files

File Type Posted
D1014-8 C03 36C26124P0555_TESTING REPORT.pdf PDF
36C26127Q0067 0001.docx DOCX document
C27 - Single-Line Schematics.pdf PDF
Facility Floor Plan.pdf PDF
36C26127Q0067_1.docx DOCX document
Facility Single Line Diagram.pdf PDF
Wage Determination 2015-5595 Washoe County.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 10-21-2026 654-27-2-6035-0001 654-27-110 36C261 Department of Veterans Affairs Network Contracting Office (NCO) 21

36C261 Department of Veterans Affairs Network Contracting Office (NCO) 21

To all Offerors/Bidders

36C26127Q0067

X X X ** HOUR & DATE for Receipt of Offers is EXTENDED to: 11-20-2026 12PM PST 654-3670162-6035-854100-2543 0100501X7 X The purpose of this amendment is to extend the offer due date from 11/09 to 11/20 at 12 PM PST.

A site visit is scheduled to take place 11/05 1PM PST. Location is Reno VAMC front entrance of BLDG 12 at the coffee cart. Address 975 Kirman Ave, Reno, NV 89502-0993.

Submit all questions NLT 11/16/2026 12PM PST.

Please see page 2, 3, and 4 for answered RFI's.

2024 Test Resulta attached.

Charee Harris Contracting Officer

1. VAAR 852.219-75 in the solicitation has box (iii), special trade construction contractors (75 percent), marked, while the requirement is coded J061 under NAICS 238210 and FAR 52.219-14 is also included. Please confirm that the 75 percent special trade limitation in box (iii) is the limitation that applies to this award. Confirmed. This requirement is solicited under NAICS 238210. The applicable limitation on subcontracting is VAAR 852.219-75(c)(iii), 75 percent for special trade construction contractors. Offeror must comply with that limitation and submit the signed certificate.

2. The SAM.gov notice shows no set-aside, while the solicitation includes VAAR 852.219-73 (total set-aside for certified SDVOSBs). Please confirm that this requirement is a total SDVOSB set-aside. Confirmed. This is a total SDVOSB set-aside per VAAR 852.219-73 and SF1449 Block 10. NCO 21 will update the SAM.gov notice to reflect the set-aside. Offerors must be certified SDVOSB in SBA Veteran Small Business Certification at time of offer.

3. Section B.1 states that invoices are submitted upon Government inspection and acceptance. Will VA accept two invoices, one after acceptance of field testing and one after acceptance of the coordination study and final report? Yes, the VA will take two invoices. Station/contracting will review these invoices for approval.

4. Amendment 0001 added Attachment C27, Single-Line Schematics. Please confirm whether C27 and the Facility Single Line Diagram together define the full quantities to be tested (MV switches, MV cable runs and vaults, liquid-filled and dry-type transformers, circuit breakers 225A and above, and feeders), or provide an equipment list with counts. Please also identify the buildings covered by "Day 12 + TBD, new facilities since 2017." In the past, a copy of 1-line diagrams was updated with color coding of each test component and a sheet with all quantiles and locations. This should be done to ensure vendor and FMS understands what scope is.

5. For the coordination study and arc flash analysis, is the 2024 study model available to the contractor, and in what software? Is there a required software platform and CAD version for the deliverables? Yes. However, I was just informed that our 2020 circuit breaker testing is the performed format which we can provide.

6. Must the coordination study and arc flash analysis be sealed by a Professional Engineer, and if so, must the engineer be licensed in Nevada? Yes engineering seal is required. No, it does not need to be Nevada. In the past, the previous vendor has had an engineer on staff who did this.

7. Please confirm that the five years of experience in the Contractor Requirements section is verified as a responsibility matter after quotes, and that the quote itself consists of price, the signed VAAR 852.219-75 certificate, amendment acknowledgments, and the items listed in FAR 52.212-1(a). Confirmed. Contractor Requirements Para 7.3 [5-year experience] will be evaluated as part of responsibility per FAR 9.104 after quotes, not as part of technical acceptability. For quote submission, see FAR 52.212-1(a) as supplemented by Addendum: price on B.2 Schedule, signed SF1449 Block 30 if required, acknowledgment of amendments per B.1 Para 4, signed VAAR 852.219-75 certificate, and proof of SDVOSB certification status. See also 52.212-3 if not in SAM.

8. Will VA facility electricians perform switching for the outages, and will VA provide temporary power or generator support where emergency branch equipment is de-energized? It is preferred that be in the vendor’s scope of work. But verbiage should state that it will be done with Electrical supervisor or designee’s authority at time of switching. Vendor should be responsible for the switching of the medium voltage system (25KV). This would be the P/Q switch in Boiler plant yard, medium voltage switches, and transformers in/on the facility down stream from the P/Q switch. VA electricians may assist with switching for 600 volts and less to aid in the testing. This must be arranged in the presented schedule to ensure proper VA staff is available.

9. What is the anticipated award date and the targeted notice-to-proceed window, so offerors can hold test crews for the night schedule? Anticipated award is within 2-3 weeks after the 11/9/2026 due date, subject to evaluations. NTP is intended ASAP after award per SOW 8.1. Offerors should plan to start coordination within 1 week of NTP. We will not require crews to be held prior to NTP.

10. Will a site visit be offered before the quote due date, and if so, will attendance be optional? VA high encourages site visits to visit equipment types, locations, and quantities. This has not been a bidding mandate to attend, but is encouraged.

11. Is there a deadline for questions, and will answers be issued by amendment? Submit questions NLT 11/02/2026 12PM PST to alex.arter@va.gov. Answers that affect the SOW or terms will be issued by formal amendment to all offerors. Administrative clarifications may be answered by email.

12. The quote submission method and address, and the question deadline. Quotes shall be submitted by email to alex.arter@va.gov. Quotes are due November 9, 2026 at 12:00 PM Pacific Time. File size: split emails if over 20MB. Submit questions NLT 11/02/2026 12PM PST to alex.arter@va.gov. Answers affecting SOW/terms/pricing will be issued by formal amendment.

13. Whether a site visit at the Ioannis A. Lougaris VAMC (Reno) will be held, and its date. A site visit is planned. Attendance will be optional. Date/time and meeting location will be issued by amendment once coordinated with Engineering. Offerors are encouraged to attend to verify existing conditions. No energized work will be performed during the site visit.

14. Breaker and feeder quantities by voltage class (LV/MV), and whether protective relay testing and arc-flash label updates are in scope. From the previous tests. There are:

11 MV Switches 10 MV Transformers 477 Circuit Breakers 570 Feeder Cables 27 LV Transformers Protective relay testing and arc-flash label updates are in the scope. The arc-flash label updates are to have their associated room numbers on them and must be done with professional engravings (i.e. no hand drawn labels).

15. Planned outage windows, and whether shutdowns must be after hours or on weekends. Yes. Per SOW 8.6, Electrical Testing shall be performed during Off Hours - 6:00 PM to 6:00 AM, weekends, and federal holidays. Photography work shall be performed during Normal Hours (Mon-Fri 6AM-6PM). The sequencing in SOW 8.1 shall be used as the basis for pricing. Final outage windows will be coordinated with the COR 2 weeks in advance per SOW 8.7 to minimize impact to patient care.

16. Required standard and deliverables (for example, NETA MTS and VHA Directive 1028 reporting). The required standard and deliverables are to be adhered to the most concurrent American National Standard: Standard for Maintenance Testing Specification for Electrical Power Equipment and Systems (ANSI/NETA MTS) as well as the VHA Directive 1028. This can be found in section 7.1 and 7.14 in the SOW. Additional code requirements can also be found in this section.

See attached document: D1014-8 C03 36C26124P0555_TESTING REPORT.