About this file

This is a Standard Form 30 Amendment/Modification of a federal solicitation issued by the Department of Veterans Affairs Network Contracting Office (NCO) for HVAC Cooling Towers Testing and Maintenance (Solicitation Number 36C26126Q0576). The amendment, issued on May 20, 2026, serves solely to provide Question and Answer responses clarifying requirements outlined in the Performance Work Statement and Scope of Work. No changes to solicitation terms, conditions, or deadlines are made through this amendment.

The Q&A responses address 16 contractor inquiries regarding cooling tower specifications, system volumes, chemical delivery responsibilities, water treatment controller ownership, closed-loop maintenance, and sampling requirements. Key clarifications include: the VA owns existing water treatment controllers, chemical base tanks, and chemical pumps (contractor should exclude these costs from bids); the contractor is responsible for determining appropriate chemical base tank sizes and managing chemical delivery and transfer; weekly onsite testing by contractor representatives is required and cannot be substituted with remote monitoring; the contractor must collect and analyze water samples rather than VA staff; and contractors should receive and store chemical deliveries at their local site to mitigate loss or theft risks. The VA noted inability to provide specific closed-loop volumes and annual makeup water volumes due to fluctuating maintenance activities, requiring contractors to utilize estimation tools. All other contract terms and conditions remain unchanged.

View the file

Other files for this federal contract opportunity

Other files attached to F103--HVAC Cooling Towers Testing and Maintenance, newest first.
File Type Posted
36C26126Q0576 0002.docx DOCX document
36C26126Q0576 0001.docx DOCX document
Attachment 7 WD 2015-5641 Santa Clara County.pdf PDF
Attachment 5 WD 2015-5623 Alameda County.pdf PDF
Attachment 2 General Duty Clause Section 5a1.pdf PDF
Attachment 1 VHA DIRECTIVE 1061.4.pdf PDF
36C26126Q0576.docx DOCX document
Attachment 6 WD 2015-5637 San Mateo County.pdf PDF
Attachment 4 SOP 138-21-05.pdf PDF
Attachment 3 SOP 138-21-31.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 05-20-2026 640-26-4-5051-0113 None

612MCP

Department of Veterans Affairs Network Contracting Office (NCO) 21

612MCP

Department of Veterans Affairs Network Contracting Office (NCO) 21

To all Offerors/Bidders

36C26126Q0576

X X X X The purpose of this amendment is to provide the Question and Answer response below.

All other terms and conditions remain unchanged.

Tim Smith Contracting Officer Question and Answer

1) What is the system volume of each CT?

The specifications vary depending on the cooling tower. Please refer to the make and model information outlined in the Performance Work Statement, Scope of Work, or inventory for these details.

2) What are the cubic feet of each CT (including underground sumps)?

Please refer to the make and model information provided in the inventory. For PAD (VA Palo Alto), Building 100, the cooling tower sump dimensions are 25 feet by 44 feet, with an approximate depth of 6 feet.

3) What is the annual average continuous cooling tonnage for each CT?

It varies depending on the location. Please refer to the Performance Work Statement or Scope of Work for further details.

4) Who owns the existing chemical tanks, chemical pumps, and water treatment controllers?

The VA owns the existing water treatment controllers, chemical base tanks, and chemical pumps.

5) Should the cost of new water treatment controllers, chemical base tanks, and chemical pumps be included in the bid?

The VA owns the existing water treatment controllers, chemical base tanks, and chemical pumps; therefore, the cost of these systems should be excluded.

6) What is the current chemical delivery process? What package size is used for chemical base tanks, and who is responsible for transfer into the base tanks?

The contractor shall be responsible for determining the appropriate size of the chemical base tank at each location, as well as for the delivery of chemicals and their transfer into the base tanks.

7) What are the closed-loop volumes, and should the cost of biocide treatment be included?

The VA is unable to provide this information currently. The contractor may need to utilize estimation tools to approximate the volume of these closed loops. Additionally, chemicals may be added incrementally until the required parts per million (ppm) of corrosion inhibitor are achieved.

8) What is the approximate annual closed-loop makeup water volume for determining inhibitor treatment demand?

We do not have a specific number for this, as it fluctuates frequently due to leaks and ongoing maintenance activities. The demand for inhibitor treatment will vary in accordance with the condition of the loop at any given time.

9) Water samples could not be obtained during the site survey. Please provide the cooling water makeup quality or target cycles for cooling water makeup quality or target cycles at this time.

All cooling towers and closed loops are currently maintained in accordance with VA HVAC standards and are operating within established limits. At this time, we are unable to provide detailed information; however, a sample report may be made available to the awardee following contract award, in accordance with the Performance Work Statement or Scope of Work.

10) Will the onsite team pull samples for Nalco field water testing?

No, the contractor (awardee) representative will be responsible for collecting, analyzing, and reporting sample data as required by the contract. VA representatives will not collect samples on behalf of the contractor.

11) Can we propose monthly CT service with a smart controller and continuous remote monitoring as a substitute for weekly non-connected controllers?

No. The contractor’s representative is required to perform testing in person to ensure that all aspects of the system are thoroughly evaluated, and so that the technician can observe and report any changes to the COR for awareness. Please refer to the Performance Work Statement or Scope of Work for this contract for additional details.

12) Can we use third-party chemical drum drop-off delivery?

It is preferred and recommended that the contractor (awardee) receive and store chemical deliveries at their local site, as the VA will not be responsible for any missing or stolen deliveries.

13) Could you provide the model and SN?

Please refer to the Performance Work Statement or Scope of Work for a detailed inventory, which includes make and model information.

14) Could you provide information on the sort of testing and maintenance you are looking for?

Please refer to the Performance Work Statement or Scope of Work for this contract for detailed information regarding the maintenance checklist for cooling towers (CT) on a monthly, quarterly, and annual basis, as well as the types of tests required for cooling towers and closed loops.

15) Do they want a rep onsite for weekly testing?

Yes, it is required as per contract.

16) Will a total of 20 samples be collected from the entire campus or 20 samples from each individual building?

Please refer to the Performance Work Statement or Scope of Work for information regarding the number of loops and cooling towers, as well as the total number of samples to be collected. Samples are to be obtained from various buildings, campuses, or locations.