Attachment - VA Response to RFIs 1-10 Solicitation No. 36C26126Q0490.pdf
PDF 99 KB Posted
- Solicitation number
- 36C26126Q0490
About this file
This document is a Questions and Answers (Q&A) response file for VA Solicitation No. 36C26126Q0490 concerning Building 101 Mixing Valve Replacements. The VA addresses ten Requests for Information (RFIs) that clarify scope, schedule, and technical requirements for the project.
Key technical requirements include: replacement of existing Armstrong "Brain" control panels and blue Valbia automatic control valves with Armstrong DRV80 mixing valves (or equivalent brand-name or equal products); no integration of new valves into the Building Automation System (BAS) by the contractor; and replacement of mixing valves only, with no changes to pressure relief valves, balancing valves, backflows, or other auxiliary equipment. Existing shutoff valves are operational and do not require replacement. The Contract Officer Representative (COR) will be responsible for system balancing and final temperature verification, eliminating the need for a manufacturer's representative at startup and commissioning. All mixing valves must be replaced during a single shutdown with no phased installation required and no temporary domestic hot water service needed during construction. The 60-day contract duration already includes material lead time; any lead times exceeding this period require a manufacturer's justification letter submitted to the VA for consideration. The solicitation contains additional details regarding hours of work and procurement requirements that contractors must review.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26126Q0490 0004.docx | DOCX document | |
| S02 1449 36C26126Q0490_2 revised 05-07-26.pdf | ||
| 36C26126Q0490 0003.docx | DOCX document | |
| Attachment - Pre-Solicitation Site Visit Sign In Sheet 04-15-26.pdf | ||
| 36C26126Q0490 0002.docx | DOCX document | |
| 36C26126Q0490 0001.docx | DOCX document | |
| Attachment - REQUEST FOR INFORMATION RFI FORM.docx | DOCX document | |
| Attachment - Salient Characteristics 03-03-26.pdf | ||
| Attachment - Specification Section 01 35 26 revised 03-05-26.pdf | ||
| Attachment - Davis-Bacon Act Wage Determination CA20260018 01-30-2026.pdf | ||
| Attachment - Vavle Data Plate Picture.pdf | ||
| 36C26126Q0490_2.docx | DOCX document |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VA Response to RFIs for Solicitation No. 36C26126Q0490
Bldg. 101 Mixing Valve Replacements
RFI #1 – Are shutdowns restricted to nights, weekends or off-hours?
VA Response: No. Please read the solicitation for the hours of work.
RFI #2 - Is the contractor responsible for integrating new mixing valves into the existing BAS system? If so, who is the controls contractor monitoring the BMS System.
VA Response: No. Please read the solicitation for the requirements of this procurement.
RFI #3 - Are existing control panels (Armstrong “Brain” / BrainScan) to remain or be replaced?
VA Response: Replaced. Please read the solicitation for the requirements of this procurement.
RFI #4 - It was mentioned during the site visit that the blue Valbia automatic control valves would stick and not actuate and need to be turned manually. Are these control valves to be replaced or to remain?
VA Response: Replaced.
RFI #5 - Please advise if any other valves, PRVs, balancing valves, T&Ps, backflows, or control valves need to be replaced with these mixing valves?
VA Response: No, just mixing valves.
RFI #6 - Are the existing shutoff valves to the mixing valves operational or should other we consider other means of achieving a positive water shutoff?
VA Response: They are operational.
RFI #7 - If equipment lead times exceed the 60-day contract duration, will schedule adjustments be allowed?
VA Response: Since a 60-day material order lead time has already been included within the period of performance, a justification letter from the manufacturer will be required to be provided to the VA for consideration.
RFI #8 - Are alternate manufacturers acceptable in lieu of Armstrong DRV80? Yes you can do equivileant.
VA Response: This is a brand name or equal procurement. Please read the solicitation for what is required.
RFI #9 - Is manufacturer’s representative required for startup, programming, and commissioning of Armstrong DRV80 valves? If not, who is responsible for system balancing and final temperature verification?
VA Response: No. The COR will be responsible.
RFI #10 - Can all mixing valves be replaced during a single shutdown, or is phased installation required? Is temporary domestic hot water service required during construction?
VA Response: 1 shutdown. No.
-----------------------------------------------END OF RFIs--------------------------------------------