36C26125R0062 Revised- Amendment 00001.pdf

PDF 484 KB Posted

Attached to
Z1DA--4 Steam Leak Repair Bldg. 100
Solicitation number
36C26125R0062
Issued by

About this file

This document is a Task Order Proposal Request for steam leak repairs at the Veterans Affairs Palo Alto Healthcare System (VAPAHCS). The solicitation is limited to contractors who were previously awarded a Veterans Integrated Service Network 21 (VISN 21) Multiple-Award Construction Contract (MACC) from Network Contracting Office 21, specifically those in MACC Group 2. The project involves repairing steam leaks in Buildings 4 and 100, including tasks such as securing steam valves, replacing unions, pipe nipples, and steam traps, and conducting leak tests.

The procurement is 100% set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) under the VISN 21 MACC Group 2. The project is located at 3801 Miranda Ave, Palo Alto, CA 94304, with a site visit scheduled for Monday, June 16th, 2025 at 10:00 AM PDT. The contract has a 30-calendar day performance period, with a disclosed project magnitude between $25,000 and $100,000. Eligible contractors include Acierto LLC, Hawk Contracting Group, Bexar Advanced Solutions Group, Patriot Construction, and several other listed firms. Award will be made to the most advantageous offer based on price only, with bid and performance bonds required.

View the file

Other files

File Type Posted
36C26125R0062 0002.docx DOCX document
36C26125R0062 0001.docx DOCX document
36C26125R0062.docx DOCX document
Wage Determination - CA20250018.txt TXT text file
SECTION 22 05 11.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NCO 21 MACC

GROUP 2

TASK ORDER PROPOSAL REQUEST

4 Steam Leak Repair Bldg. 100

PLACE OF PERFORMANCE

VAPAHCS Palo Alto 3801 Miranda Ave

Palo Alto, CA 94304

NOTICE TO VETERANS INTGRATED SERVICE NETWORK 21 (VISN 21)

MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC) HOLDERS

Description: THE RESULTING SOLICITATION IS A TASK ORDER PROPOSAL REQUEST. Proposals will only be requested and accepted from contractors who were awarded a Veterans Integrated Service Network 21 (VISN 21) Multiple-Award Construction Contract (MACC) from Network Contracting Office 21 (NCO 21).

Point of Contact: Jessica Newman, Contract Specialist, jessica.newman2@va.gov

Project Title: 4 Steam Leak Repair Bldg. 100

Project specifications and all associated project documents shall be incorporated into the Task Order proposal Request which shall be posted electronically through https://sam.gov

Questions regarding this notice shall be submitted via e-mail to: jose.hernandez1@va.gov

Site Visit: A Site Visit is scheduled for Monday, June 16th, 2025 at 10:00 AM PDT

The following firms are eligible for award of the resulting task order:

https://sam.gov/

MACC GROUP 2

Acierto, LLC Hawk Contracting Group 2053 North 2000 West P.O. Box 490 Farr West, UT 84404 Montrose, CO 81402

Bexar Advanced Solutions Group Patriot Construction 47 E. Crestwood Road 4646 Qantas Lane Kaysville, UT 84037 Stockton, CA 95206

Dsquare Construction Saw-Greenland JV 107 W. Sahuaro Street 2625 Production Road Tucson, AZ 85705 Virginia Beach, VA 23454

ESA South, Inc. Sergent Mechanical 1681 Success Drive 1617 Pacific Avenue Cantonment, FL 32533 Oxnard, CA 93033

Ground Level – Overaa Joint Venture West Point Contractors 5013 Forni Drive 2915 E. Weiding Road Concord, CA 94520 Tucson, AZ 85706

**Any offers received from contractors not mentioned above will not be accepted.

1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

7. ISSUED BY CODE 8. ADDRESS OFFER TO

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014) STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES NO

a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b. An offer guarantee is, is not required.

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

1 13

36C26125R0062

X

06-11-2025

36C261-25-AP-3426

N/A

612MCP

Department of Veterans Affairs VA Sierra Pacific Network (VISN 21) Network Contracting Office (NCO) 21 3237 Peacekeeper Way, Bldg 200 Suite 204 McClellan Park CA 95652

Jose Hernandez jose.hernandez1@va.gov

Jose Hernandez 916-923-4519

The contractor must provide all personnel, equipment, tools, materials, supervision, and other items and services necessary to conduct Bldg. 100 & 4 steam leak repairs

Place of Performance: 3801 Miranda Ave, Palo Alto, CA 94304.

NAICS: 236220

Disclosure of Magnitude: Between $25,000 and $100,000.

Site Visit: Monday June 16th, 2025. 10:00 AM PDT Location: Lobby of Bldg. 100, 3801 Miranda Ave, Palo Alto, CA 94304

RFI/Questions Due: Friday, June 20th, 2025, at 9:00 AM Pacific Time.

Proposals Due: Tuesday, June 30th, 2025, at 2:00 PM Pacific Time.

Offers shall be valid for at least 30 days.

This procurement has been 100% set aside for SDVOSB under the VISN 21 MACC Group 2.

Award will be made to the responsible offeror whose offer, conforming to the RFP, will be most advantageous to the government, considering Price Only.

Bid, and Performance bonds are required for this acquisition

10 30

X X 52.211-10

X

Electronic only 2:00pm PDT

06-30-2025

X

14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO 10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )

26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY

PHONE: FAX:

28. NEGOTIATED AGREEMENT 29. AWARD Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code)

(Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

(Type or print)

(4 copies unless otherwise specified)

(Type or print) (Type or print)

(Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror)

(To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

612MCP

Department of Veterans Affairs

Network Contracting Office (NCO) 21 3237 Peacekeeper Way, Bldg 200 Suite 204 McClellan CA 95652

Department of Veterans Affairs FMS VA-9(101) Financial Services Center

PO Box 149971 Austin TX 78714-9971

36C26125R0062

Table of Contents

PART I - THE SCHEDULE

SECTION A - SOLICITATION/CONTRACT FORM

A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)

A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION,

ALTERATION, OR REPAIR)– BACK

2.1 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—

CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023)

(DEVIATION)

2.2 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)

2.3 52.228-1 BID GUARANTEE (SEP 1996)

Project No: PAD 100 & 4 STEAM REAPIRS. April, 1, 2025

Scope of Work

1.0 General Intent

1.1 The contractor must provide all personnel, equipment, tools, materials, supervision, and other items and services necessary to conduct Bldg. 100 & 4 steam leak repairs located at VAPAHCS Palo Alto, 3801 Miranda Ave, Palo Alto, CA 94304.

1.2 The contractor must perform to the standards in this contract. This project shall take no longer than 30 calendar days from the notice to proceed to complete.

1.3 This project shall be coordinated with the appointed COR to insure minimal impact to resident’s day to day activities and minimal noise. Scheduling of work shall be at the convenience of the VAPAHCS.

2.0 General Information and Requirements

2.1 The objective of this project is to conduct Bldg. 100 & 4 steam leak repairs located at VAPAHCS Palo Alto, 3801 Miranda Ave, Palo Alto, CA 94304.

2.2 The contractor shall provide operation and maintenance instructions, and manufacturer documentation at the completion of the project. Manufacturer documentation and maintenance schedule to be provided in close out documents.

2.3 The contractor shall provide all tools, equipment, and personal protective equipment necessary to complete this project as deemed by industry standards, this SOW, all related specifications, applicable code requirements, and site policy.

2.4 The contractor shall provide daily cleanup and securing of work site, including securing tools and equipment. Disposal of all waste and debris is at the contractor’s own expense.

2.5 The contractor shall provide quality control of all work conducted and the individual appointed shall be competent and educated/experienced in the field of work this scope encompasses.

2.6 All work shall be coordinated with the COR assigned to this project and only commence once approved.

2.7 Badges: Contractor will obtain required ID badges for all employees used on project at start of each workday; Report the COR for escort to the station police service for sign in and badge issuance.

2.8 Security: The contractor and their personnel shall be subject to the same Federal laws, regulations, standards, and VA policies as VA personnel regarding information and information system security.

2.9 Schedule: Normal work hours will be 8:00am – 4:30 pm Monday-Friday excluding Government holidays unless otherwise approved by the COR. It is the intent of the Palo Alto VA Medical Center that the work is to be completed within 30 calendar days from the issuance of the Notice to Proceed (NTP). Any request to utility shutdowns must be requested in writing at a minimum of 21 days prior to the requested day of shutdown.

2.10 Codes and Standards: The Contractor shall follow all applicable codes and standards to this type of work including but not limited to Health Care System Memorandums (HCSM), OSHA Guidelines, Lock-out-Tag-out, Rules of Station, NFPA, and etcetera. If any code/standard is found to be contradictory; the authority having jurisdiction (COR) shall make the final determination and work shall proceed at no additional cost to the Government.

3.0 Specific Tasks

3.1 The contractor shall provide all supervision, administrative and technical support, labor, subcontractors, tools, transportation, materials, supplies and equipment. The contractor shall plan, schedule, and ensure effective completion of steam repairs.

3.2 The contractor will make the following repairs:

Building 4

Steam Repairs

1. The contractor will secure steam and LOTO steam valve.

2. The contractor will Provide labor and material to repair (1) 1-¼” Kunkle safety valve.

3. The contractor will secure LOTO and test pipes and unions for leaks.

Building 100

Steam Repairs

1. The contractor will secure steam valve and LOTO valve.

2. The contractor will provide labor and material to replace (1) 2” threaded union and 4’ of piping.

3. The contractor will provide labor and material to replace (1) ¾” x 4” pipe nipple and ¾” x 1” threaded bushing.

4. The contractor will provide labor and material to replace (2) low pressure steam traps and associated nipples between unions.

5. The contractor will provide labels.

6. The contractor will secure LOTO and test pipes and unions for leaks.

4.0 Technical Exhibits

4.1 – Specifications (see attached, listed below)

01 35 26 SAFETY REQUIREMENTS

See attached document: Wage Determination - CA20250018.

2.1 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON

SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND

CONSTRUCTION (JAN 2023) (DEVIATION)

(a) Pursuant to 38 U.S.C. 8127(l)(2), the offeror certifies that—

(1) If awarded a contract (see FAR 2.101 definition), it will comply with the limitations on subcontracting requirement as provided in the solicitation and the resultant contract, as follows:

(i) [] Services. In the case of a contract for services (except construction), the contractor will not pay more than 50% of the amount paid by the government to it to firms that are not certified SDVOSBs listed in the SBA certification database as set forth in 852.219–73 or certified VOSBs listed in the SBA certification database as set forth in 852.219–74. Any work that a similarly situated certified SDVOSB/VOSB subcontractor further subcontracts will count towards the 50% subcontract amount that cannot be exceeded. Other direct costs may be excluded to the extent they are not the principal purpose of the acquisition and small business concerns do not provide the service as set forth in 13 CFR 125.6.

(ii) [] General construction. In the case of a contract for general construction, the contractor will not pay more than 85% of the amount paid by the government to it to firms that are not certified SDVOSBs listed in the SBA certification database as set forth in 852.219–73 or certified VOSBs listed in the SBA certification database as set forth in 852.219–74. Any work that a similarly situated certified SDVOSB/VOSB subcontractor further subcontracts will count towards the 85% subcontract amount that cannot be exceeded. Cost of materials are excluded and not considered to be subcontracted.

(iii) [] Special trade construction contractors. In the case of a contract for special trade contractors, the contractor will not pay more than 75% of the amount paid by the government to it to firms that are not certified SDVOSBs listed in the SBA certification database as set forth in 852.219–73 or certified VOSBs listed in the SBA certification database as set forth in 852.219–

74. Any work that a similarly situated certified SDVOSB/VOSB subcontractor further subcontracts will count towards the 75% subcontract amount that cannot be exceeded. Cost of materials are excluded and not considered to be subcontracted.

(2) The offeror acknowledges that this certification concerns a matter within the jurisdiction of an Agency of the United States. The offeror further acknowledges that this certification is subject to Title 18, United States Code, Section 1001, and, as such, a false, fictitious, or fraudulent certification may render the offeror subject to criminal, civil, or administrative penalties, including prosecution.

(3) If VA determines that an SDVOSB/ VOSB awarded a contract pursuant to 38 U.S.C. 8127 did not act in good faith, such SDVOSB/VOSB shall be subject to any or all of the following:

(i) Referral to the VA Suspension and Debarment Committee;

(ii) A fine under section 16(g)(1) of the Small Business Act (15 U.S.C. 645(g)(1)); and

(iii) Prosecution for violating 18 U.S.C. 1001.

(b) The offeror represents and understands that by submission of its offer and award of a contract it may be required to provide copies of documents or records to VA that VA may review to determine whether the offeror complied with the limitations on subcontracting requirement specified in the contract. Contracting officers may, at their discretion, require the contractor to demonstrate its compliance with the limitations on subcontracting at any time during performance and upon completion of a contract if the information regarding such compliance is not already available to the contracting officer. Evidence of compliance includes, but is not limited to, invoices, copies of subcontracts, or a list of the value of tasks performed.

(c) The offeror further agrees to cooperate fully and make available any documents or records as may be required to enable VA to determine compliance with the limitations on subcontracting requirement. The offeror understands that failure to provide documents as requested by VA may result in remedial action as the Government deems appropriate.

(d) Offeror completed certification/fill-in required. The formal certification must be completed, signed and returned with the offeror’s bid, quotation, or proposal. The Government will not consider offers for award from offerors that do not provide the certification, and all such responses will be deemed ineligible for evaluation and award.

Certification

I hereby certify that if awarded the contract, [insert name of offeror] will comply with the limitations on subcontracting specified in this clause and in the resultant contract. I further certify that I am authorized to execute this certification on behalf of [insert name of offeror].

Printed Name of Signee: ___________

Printed Title of Signee: _____________

Signature: ____________

Date: ______________

Company Name and Address: _______________

(End of Clause)

2.2 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I

(FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for—

Monday June 16th, 2025

At 10:00 AM PDT

(c) Participants will meet at—

Bldg. 100 Lobby 3801 Miranda Ave Palo Alto, CA 94304

(End of Provision)

INSTRUCTIONS, CONDITIONS, AND OTHER STATEMENTS TO BIDDERS/OFFERORS

OFFER SUBMISSION:

The following documents are to be included in the solicitation submission:

1. One fully completed and signed SF 1442 Offer page, completed offer amount entered in block 17, acknowledgment of all amendments either via entering data in block 19 of the SF1442 or completing blocks 15a, b, and c of the Amendment and attaching to the SF 1442 Offer page.

2. One fully completed Supplemental Price Breakdown by Division Sheet

3. One Documentation of Safety & Environmental Record and Documentation of Experience Modification

Rate (EMR) (See below instructions).

4. Bid Bond

5. Completed Certificate 852.219-75

Offerors are responsible for ensuring and verifying their price and all required documents are received at the email address designated in block 8 of the SF 1442 Solicitation and by the date and time specified in block 13A of the SF 1442 Solicitation (subject to amendment). Any exception to the terms and conditions of this request for quotation will result in a nonresponsive quotation.

PROPOSALS ARE TO BE SENT TO:

One electronic copy via email of the price offer is to be sent to arrive on or before the due date/time at the following email address: jose.hernandez1@va.gov with solicitation number and title in the subject. Faxed quotations are not permitted under any circumstances.

PLANS/SPECIFICATIONS/DRAWINGS:

Drawings and specifications are attached in electronic format to this solicitation. Contractors are responsible for downloading and printing their own plan sets. The VA will not provide hard copies of the drawings and specifications to any Contractor. Contractors are responsible for ensuring that any construction document package used for their quotation or construction is complete and up to date.

QUESTIONS AND ANSWERS:

Submit a question via the Questions Form (included in this Solicitation), via email to jose.hernandez1@va.gov

RFI/Questions for this solicitation are due Friday, June 20th, 2025, at 12:00 PM PDT. No questions will be answered after this date/time unless determined to be in the best interest of the Government as determined by the Contracting Officer.

OFFER DUE DATE SCHEDULE:

Offers received after date and time in Block 13 of SF 1442 may be rejected.

Quotation(s) are due by the date and time shown in Block 13 of the SF 1442. Offers received after this date and time may be rejected unless considered beneficial to the government.

INSTRUCTIONS TO OFFERORS:

The apparent successful offeror must be determined as “responsible” by the Contracting Officer in accordance with FAR Part 9, Contractor Qualifications.

SITE VISIT:

Potential Offerors are strongly urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of performing construction services. Failure to inspect the site shall not constitute grounds for a claim after contract award.

mailto:jose.hernandez1@va.gov mailto:jose.hernandez1@va.gov

See Provision 52.236-27 for specific information regarding the project pre-offer site visit, which will be the only opportunity for potential Offerors to visit the site. All potential Offerors, subcontractors, and suppliers are strongly encouraged and expected to attend the pre-offer site visit.

BASIS FOR AWARD

1. INTRODUCTION:

This is a price-only selection conducted in accordance with Federal Acquisition Regulation (FAR) Part 16.505(b), Orders under multiple-award contracts, supplemented by the Department of Veterans Affairs Acquisition Regulation (VAAR). These regulations are available electronically at https://www.acquisition.gov/ and https://www.va.gov/oal/library/vaar/

2. EVALUATION:

Price Only -- The Government will evaluate the lowest price offer to determine if the price is fair and reasonable for the work to be performed. To be considered fair and reasonable for the work performed, the evaluators will also check for appearance of unbalanced line-item prices. If deemed necessary, the supplemental price breakdown information will be used to assist the Government in performing the price evaluation described above. Offers that are materially unbalanced as to prices for the basic requirement and the option quantities are not fair and reasonable. An Offer is unbalanced when it is based on prices significantly less than the cost for some work and prices that are significantly overstated for other work.

NOTICE TO PROCEED (NTP):

A notice to proceed shall be issued after the award of a fully executed contract. The NTP date and time are “to be determined” after the award to a successful contractor. The primary factor in the determination to issue NTP shall be the Prime Contractor submission of, and the Government review and approval of both Payment and Performance Bonds, both of which are enforceable legal documents.

PERFORMANCE & PAYMENT BONDS:

In accordance with FAR 28.102-1 and Contract Clause 52.228-15, offerors are reminded that any award amount over $35,000 shall require a Payment Bond (or other acceptable protection – see clause FAR 52.228-13), and awards exceeding $150,000 shall require both Payment and Performance Bonds. All bonds are due no later than 10 calendar days after award.

LIQUIDATED DAMAGES: N/A

WAGE DETERMINATION APPLICABLE TO THIS PROJECT:

General Decision Number: Davis-Bacon Act WD # CA20250018

BRAND NAME OR EQUAL:

The RFP may include the salient characteristics of the “or equal” aspect for the determination of what is equal to any cited brand name. See FAR 52.211-6 for “brand name or equal” information. Wherever a brand name is cited, the contractor shall ensure, in any resultant contract, that any equal has the salient characteristics of the brand name. Lack of confirmation shall be grounds for Government direction to replace materials or equipment by the Contractor at no additional cost or extension of the period of performance.

SYSTEM FOR AWARD MANAGEMENT (SAM):

Federal Acquisition Regulations require that federal contractors shall register in the System for Award Management (SAM) database at http://www.sam.gov and enter all mandatory information into the system.

PER VHA DIRECTIVE 7715 (06 April 2017) SAFETY & ENVIRONMENTAL RECORD AND

EXPERIENCE MODIFICATION RATE (EMR):

To be eligible for consideration and award, the contractor shall have no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years and have an EMR of equal to or less than 1.0.

https://www.acquisition.gov/ https://www.va.gov/oal/library/vaar/ http://www.sam.gov/

All contractors shall submit the following information pertaining to their past Safety & Environmental Record and EMR with their quotation.

1. SAFETY & ENVIRONMENTAL RECORD: A self-certification on company letterhead that the contractor has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years.

2. EMR: All contractors shall submit information regarding their current EMR. This information shall be obtained from the contractor’s insurance carrier and be furnished on the insurance carrier’s letterhead. Must have an EMR of equal to or less than 1.0.

PRIVACY TRAINING:

All workers regardless of project length must take VA Privacy Training which will be coordinated after project award with the Contracting Officer’s Representative (COR).

TRAINING:

All employees of the general contractor and subcontractors shall have the 10-hour OSHA certified construction safety course and/or other relevant competency training, as determined by the COR with input from the ICRA (Infection Control Risk Assessment) team. The General Contractor’s Competent Person/Superintendent shall have completed the 30-hour OSHA certified construction safety course. Documentation of training shall be submitted to the Contracting Officer for review and approval prior to any work being performed. No ID badge will be issued to an employee who does not provide this documentation. There shall be no exceptions to this requirement.

PRIVACY AND CONFIDENTIALITY:

Contractors to the Department of Veteran Affairs may be unintentionally exposed to sensitive information.

Information may be overheard, seen on documents or electronic devices, or observed that could potentially violate the privacy and confidentiality of our veterans, employees, volunteers, and their families. Regulations such as, but not limited to the Health Insurance Portability and Accountability Act of 1996 (HIPAA), Freedom of Information Act (FOIA) and Privacy Act of 1974 have been enacted to protect sensitive information from being improperly disclosed.

Information should not be divulged or released to anyone unless specifically authorized by this contract or its’ attached documents in accordance with the contracted services. Failure to comply with applicable statutes and regulation can result in the termination of this contract and civil and criminal penalties, including fines and imprisonment. All suspected or actual breeches of privacy and confidentiality should be reported immediately to the Contracting Officer, Contracting Officer’s Representative (COR) or the Facility Privacy Officer.

The C&A requirements do not apply, and a Security Accreditation Package is not required. If the contractor opts to use a computer or computer system for processing contract documents, the requirements of FIPS 140-2 for encryption of contract documents must be met.

ADDITIONAL VETCERT INFORMATION:

1. Eligibility of SDVOSBs continues to be governed by the Small Business Administration regulations, 13 CFR subparts 125.8 through 125.13, as well as the FAR, except where expressly directed otherwise by the VAAR, and 38 CFR verification regulations for SDVOSBs.

2. At the time of submission of offer, the offeror must represent to the contracting officer that it is an:

a. SDVOSB concern

b. Small business concern under the North American Industry Classification System (NAICS) code assigned to the acquisition; and

c. Verified for eligibility in the VETCERT database.

3. A joint venture may be considered an SDVOSB or VOSB concern if:

a. At least one member of the joint venture is an SDVOSB or VOSB concern, and makes the representations in paragraph (b) of this section

b. Each other concern is small under the size standard corresponding to the NAICS code assigned to the procurement.

c. The joint venture meets the requirements of paragraph 7 of the size standard explanation of affiliates in FAR 19.101; and

d. The joint venture meets the requirements of 13 CFR 125.15(b), modified to include Veteran-owned small businesses where this CFR section refers to SDVOSB concerns.

4. Any SDVOSB or VOSB concern (nonmanufacturer) must meet the requirements in FAR 19.102(f) to receive a benefit under this program.

RESPONSIBILITY REQUIREMENTS:

A responsibility check will be accomplished for the apparent awardee prior to award. Checks of the VETCERT database (to insure apparently successful offeror is a verified Service-Disabled Veteran Owned Small Business), System for Award Management (SAM) database (Central Contractor Registration, Online Representations and Certifications, and Excluded Parties List System to ensure registrations are current, valid, and no debarment records exist). Any information retrieved or received by the Government that would be cause for negative or unsatisfactory responsibility rating may result in the offeror being determined ineligible for award.

CONFORMANCE WITH ENVIRONMENTAL MANAGEMENT SYSTEMS:

The Contractor shall perform work under this contract consistent with the relevant policy and objectives identified in the agency, organizational, or facility Green Environmental Management System (GEMS) applicable for your contract. The Contractor shall perform work in a manner that conforms to all appropriate Environmental Management Programs and Operational Controls identified by the agency, organizational, or facility GEMS, and provide monitoring and measurement information as necessary for the organization to address environmental performance relative to the environmental, energy, and transportation management goals. In the event an environmental nonconformance or noncompliance associated with the contracted services is identified, the contractor shall take corrective and/or preventative actions. In the case of a noncompliance, the Contractor shall respond and take corrective action immediately. In the case of a nonconformance, the Contractor shall respond and take corrective action based on the time schedule established by the facility GEMS Coordinator. In addition, the Contractor shall ensure that their employees are aware of the roles and responsibilities identified by the environmental management system and how these requirements affect their work performed under this contract.

All on-site contractor personnel shall complete yearly EPA sponsored environmental training specified for the type of work conducted on-site. Upon inclusion in the contract, the Contracting Officer’s Representative will verify that all contractor personnel have acquired EMS Awareness Training at their appropriate site or location.

SMOKE AND CARBON MONOXIDE MONITORING REQUIREMENTS:

Contractor, his employees, his subcontractors, and their employees shall adhere to VA, VHA, and VASNHCS Policies for smoke and carbon monoxide monitoring requirements. They are available upon request from COR.

2.3 52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be percent of the bid price or , whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

2.1 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION)
2.2 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
BASIS FOR AWARD
2.3 52.228-1 BID GUARANTEE (SEP 1996)