This is a Request for Proposal (RFP) for a leak detector replacement project at the VA Pacific Islands Health Care System (VAPAHCS) Palo Alto facility. The solicitation (36C26125R0036) is 100% set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) under the VISN 21 MACC Group 2, with a project scope involving the replacement of leak detection equipment in the chiller room at 3801 Miranda Ave, Palo Alto, CA 94304.
Key project details include a 15-calendar day performance period, a mandatory site visit scheduled for Wednesday, April 9th, 2025 at 9:00 AM PDT, and proposal submissions due by Monday, April 28, 2025 at 2:00 PM PDT. The contractor must provide all personnel, equipment, tools, and services to conduct the replacement, which involves installing new MSA Chillgard 5000 equipment, remote display, pull stations, horn/strobes, and sample line metal tubing. The award will be made to the most advantageous offer considering price only, with performance and payment bonds required. The project is governed by specific safety, environmental, and subcontracting requirements, including maintaining an Experience Modification Rate (EMR) of 1.0 or less.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26125R0036 0003.docx | DOCX document | |
| SOW Leak Dection VA Palo Alto Revised.pdf | ||
| 36C26125R0036 0002.docx | DOCX document | |
| Site Walk List for Leak Detector Requirement VA Palo Alto.pdf | ||
| RFI Responses - RFP 36C26124R0036 - PAD B100 Chiller Room Leak Detector Replacement.pdf | ||
| Floor plan ECC Room.pdf | ||
| SF50 Amendment 36C26125R0036 0001.pdf | ||
| SOW Leak Dection VA Palo Alto.pdf | ||
| 36C26125R0036.docx | DOCX document | |
| 01 35 26 Safety Requirements.docx | DOCX document | |
| Wage Determination Davis-Bacon Act WD CA20250018.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES
4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER
7. ISSUED BY CODE 8. ADDRESS OFFER TO
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014) STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES NO
a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________
(hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b. An offer guarantee is, is not required.
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
1 16
36C26125R0036
X
03-28-2025
640-25-2-5070-0103
None
Department of Veterans Affairs Network Contracting Office 21 (NCO 21) VA Pacific Islands Health Care System 711 Kapiolani Blvd Suite 200 Honolulu HI 96813 jessica.newman2@va.gov
Jessica Newman 808-539-1310
FY 25 Award.
The contractor must provide all personnel, equipment, tools, materials, supervision, and other items and services necessary to conduct leak detector replacement located at VAPAHCS Palo Alto, 3801 Miranda Ave, Palo Alto, CA 94304.
Place of Performance: VAPAHCS Palo Alto, 3801 Miranda Ave, Palo Alto, CA 94304
NAICS: 236220
IAW VAAR 836.204: Disclosure of magnitude is less than $250,000.
Site Visit: Wednesday, April 9th. 2025 at 9:00 AM Pacific Time VAPAHCS Palo Alto, 3801 Miranda Ave, Palo Alto, CA 94304
RFI/Questions Due: Thursday, April 17, 2025 at 2:00 PM Pacific Time
Proposals Due: Monday, April 28, 2025 at 2:00 PM Pacific Time.
Offers shall be valid for at least 30 days.
This procurement has been 100% set aside for SDVOSB under the VISN 21 MACC Group 2.
Award will be made to the responsible offeror whose offer, conforming to the RFP, will be most advantageous to the government, considering Price Only.
Bid, Performance and Payment bonds apply to this acquisition.
10 15
X X 52.211-10
X 10 Days
1 14:00 PDT
04-28-2025
X
14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )
26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY
PHONE: FAX:
28. NEGOTIATED AGREEMENT 29. AWARD Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code)
(Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
(Type or print)
(4 copies unless otherwise specified)
(Type or print) (Type or print)
(Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror)
(To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
Department of Veterans Affairs Network Contracting Office 21 (NCO 21) VA Pacific Islands Health Care System 711 Kapiolani Blvd Suite 200 Honolulu HI 96813
Department of Veterans Affairs FMS VA-9(101) Financial Services Center
PO Box 149971 Austin TX 78714-9971 866-372-1141 vafscenterprisesupport@va
Jose Hernandez Contracting Officer
Table of Contents
PART I - THE SCHEDULE
SECTION A - SOLICITATION/CONTRACT FORM
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION,
ALTERATION, OR REPAIR)– BACK
Scope of Work
1.0 General Intent
2.0 General Information and Requirements
3.0 Specific Tasks
4.0 Technical Exhibits
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
PER VHA DIRECTIVE 7715 (06 April 2017) - SAFETY & ENVIRONMENTAL RECORD AND
EXPERIENCE MODIFICATION RATE (EMR):
2.2 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—
CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023)
(DEVIATION)
2.3 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE)
(FEB 2021)
Scope of Work
1.0 General Intent
1.1 The contractor must provide all personnel, equipment, tools, materials, supervision, and other items and services necessary to conduct leak detector replacement located at VAPAHCS Palo Alto, 3801 Miranda Ave, Palo Alto, CA 94304.
1.2 The contractor must perform to the standards in this contract. This project shall take no longer than 15 calendar days from the notice to proceed to complete.
1.3 This project shall be coordinated with the appointed Contracting Officer Representative to ensure minimal impact to residents’ day-to-day activities and minimal noise. Scheduling of work shall be at the convenience of the VAPAHCS.
2.0 General Information and Requirements
2.1 The objective of this project is to conduct a leak detector replacement located at VAPAHCS Palo Alto, 3801 Miranda Ave, Palo Alto, CA 94304.
2.2 The contractor shall provide operation and maintenance instructions and manufacturer documentation after the completion of the project. Manufacturer documentation and maintenance schedule to be provided in close-out documents.
2.3 The contractor shall provide all tools, equipment, and personal protective equipment necessary to complete this project as deemed by industry standards, this SOW, all related specifications, applicable code requirements, and site policy.
2.4 The contractor shall provide daily cleanup and securing of the work site, including securing tools and equipment. Disposal of all waste and debris is at the contractor’s own expense.
2.5 The contractor shall provide quality control of all work conducted, and the individual appointed shall be competent and educated/experienced in the field of work this scope encompasses.
2.6 All work shall be coordinated with the COR assigned to this project and only commence once approved.
2.7 Badges: Contractor will obtain required ID badges for all employees used on project at start of each workday; Report the COR for escort to the station police service for sign in and badge issuance.
2.8 Security: The contractor and their personnel shall be subject to the same Federal laws, regulations, standards, and VA policies as VA personnel regarding information and information system security.
2.9 Schedule: Normal work hours will be 8:00 am – 4:30 pm Monday-Friday ,excluding Government holidays unless otherwise approved by the COR. It is the intent of the Palo Alto VA Medical Center that the work is to be completed within 15 calendar days from the issuance of the Notice to Proceed (NTP). Any request to utility shutdowns must be requested in writing at a minimum of 21 days prior to the requested day of shutdown.
Government holidays consist of the following dates:
o New Year's Day (January 1, 2025) o Birthday of Martin Luther King, Jr. (January 20, 2025) o Washington's Birthday (February 17, 2025) o Memorial Day (May 26, 2025) o Juneteenth National Independence Day (June 19, 2025) o Independence Day (July 4, 2025) o Labor Day (September 1, 2025) o Columbus Day (October 13, 2025) o Veterans Day (November 11, 2025) o Thanksgiving Day (November 27, 2025) o Christmas Day (December 25, 2025).
2.10 Codes and Standards: The Contractor shall follow all applicable codes and standards to this type of work, including but not limited to Health Care System Memorandums (HCSM), OSHA Guidelines, Lock-out-Tag-out, Rules of Station, NFPA, etc. If any code/standard is found to be contradictory, the authority having jurisdiction (COR) shall make the final determination, and work shall proceed at no additional cost to the Government.
3.0 Specific Tasks
3.1 The contractor shall provide all supervision, administrative and technical support, labor, subcontractors, tools, transportation, materials, supplies, and equipment. The contractor shall plan, schedule, and ensure the effective completion of leak detector replacement.
3.2 The contractor will perform the following operations:
1. The contractor will lockout/tagout the leak detector power source.
2. The contractor will provide project management support during duration of work.
3. The contractor will provide a demo of the existing sample piping. Piping shall be disconnected, dropped from mounting, and removed from the building to be disposed of off-site.
4. The contractor will provide mounting of VF/CI (vendor furnished/contractor installed) equipment:
(1) MSA Chillgard 5000
(1) MSA Chillgard 5000 Remote Display
(3) Pull stations
(3) Horn/Strobes
(3) “Refrigerant Leak” Labels
(6) End of line filter kits.
5. The contractor will Provide and install (6) new sample line metal tubing.
Material shall be ¼” x .035” wall, cleaned and capped, 304 stainless steel tubing with long radius bends and stainless-steel compression fittings to (3) existing chillers.
6. The contractor will conduct all electrical hook-up of new equipment.
7. The contractor will provide up to five feet (5”) of electrical conduit modification of existing equipment locations.
8. The contractor will remove lockout/tagout and perform system operations check.
4.0 Technical Exhibits
01 35 26 SAFETY REQUIREMENTS
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO
BIDDERS/OFFERORS
INSTRUCTIONS, CONDITIONS, AND OTHER STATEMENTS TO BIDDERS/OFFERORS
OFFER SUBMISSION:
The following documents are to be included in the solicitation submission:
1. One fully completed and signed SF 1442 Offer page, completed offer amount entered in block 17, acknowledgment of all amendments either via entering data in block 19 of the SF1442 or completing blocks 15a, b, and c of the Amendment and attaching to the SF 1442 Offer page.
2. One fully completed Supplemental Price Breakdown by Division Sheet
3. One Documentation of Safety & Environmental Record and Documentation of Experience Modification
Rate (EMR) (See below instructions).
4. Bid Bond
5. Completed Certificate 852.219-75
Offerors are responsible for ensuring and verifying their price and all required documents are received at the email address designated in block 8 of the SF 1442 Solicitation and by the date and time specified in block 13A of the SF 1442 Solicitation (subject to amendment). Any exception to the terms and conditions of this request for quotation will result in a nonresponsive quotation.
PROPOSALS ARE TO BE SENT TO:
One electronic copy via email of the price offer is to be sent to arrive on or before the due date/time at the following email address: jessica.newman2@va.gov with solicitation number and title in the subject. Faxed quotations are not permitted under any circumstances.
PLANS/SPECIFICATIONS:
The specifications are attached in electronic format to this solicitation. Contractors are responsible for downloading and printing their own plan sets. The VA will not provide hard copies of the specifications to any Contractor.
Contractors are responsible for ensuring that any construction document package used for their quotation or construction is complete and up to date.
QUESTIONS AND ANSWERS:
Submit a question via the Questions Form (included in this Solicitation), via email to jessica.newman2@va.gov.
RFI/Questions for this solicitation are due Thursday, April 17, 2025, at 2:00 PM PDT. No questions will be answered after this date/time unless determined to be in the best interest of the Government as determined by the Contracting Officer.
OFFER DUE DATE SCHEDULE:
Offers received after date and time in Block 13 of SF 1442 may be rejected.
Quotation(s) are due by the date and time shown in Block 13 of the SF 1442. Offers received after this date and time may be rejected unless considered beneficial to the government.
INSTRUCTIONS TO OFFERORS:
The apparent successful offeror must be determined as “responsible” by the Contracting Officer in accordance with FAR Part 9, Contractor Qualifications.
SITE VISIT:
Potential Offerors are strongly urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of performing construction services. Failure to inspect the site shall not constitute grounds for a claim after contract award.
See Provision 52.236-27 for specific information regarding the project pre-offer site visit, which will be the only opportunity for potential Offerors to visit the site. All potential Offerors, subcontractors, and suppliers are strongly encouraged and expected to attend the pre-offer site visit.
BASIS FOR AWARD
1. INTRODUCTION:
This is a price-only selection conducted in accordance with Federal Acquisition Regulation (FAR) Part 16.505(b), Orders under multiple-award contracts, supplemented by the Department of Veterans Affairs Acquisition Regulation (VAAR). These regulations are available electronically at https://www.acquisition.gov/ and https://www.va.gov/oal/library/vaar/
2. EVALUATION:
Price Only -- The Government will evaluate the lowest price offer to determine if the price is fair and reasonable for the work to be performed. To be considered fair and reasonable for the work performed, the evaluators will also check for appearance of unbalanced line-item prices. If deemed necessary, the supplemental price breakdown information will be used to assist the Government in performing the price evaluation described above. Offers that are materially unbalanced as to prices for the basic requirement and the option quantities are not fair and reasonable. An Offer is unbalanced when it is based on prices significantly less than the cost for some work and prices that are significantly overstated for other work.
NOTICE TO PROCEED (NTP):
A notice to proceed shall be issued after the award of a fully executed contract. The NTP date and time are “to be determined” after the award to a successful contractor. The primary factor in the determination to issue NTP shall be the Prime Contractor submission of, and the Government review and approval of both Payment and Performance Bonds, both of which are enforceable legal documents.
PERFORMANCE & PAYMENT BONDS:
In accordance with FAR 28.102-1 and Contract Clause 52.228-15, offerors are reminded that any award amount over $35,000 shall require a Payment Bond (or other acceptable protection – see clause FAR 52.228-13), and awards exceeding $150,000 shall require both Payment and Performance Bonds. All bonds are due no later than 10 calendar days after award.
LIQUIDATED DAMAGES: N/A
WAGE DETERMINATION APPLICABLE TO THIS PROJECT:
General Decision Number: CA20250019 per MACC Base Contract Option Year 3.
BRAND NAME OR EQUAL:
The RFP may include the salient characteristics of the “or equal” aspect for the determination of what is equal to any cited brand name. See FAR 52.211-6 for “brand name or equal” information. Wherever a brand name is cited, the contractor shall ensure, in any resultant contract, that any equal has the salient characteristics of the brand name. Lack of confirmation shall be grounds for Government direction to replace materials or equipment by the Contractor at no additional cost or extension of the period of performance.
SYSTEM FOR AWARD MANAGEMENT (SAM):
Federal Acquisition Regulations require that federal contractors shall register in the System for Award Management (SAM) database at http://www.sam.gov and enter all mandatory information into the system.
PER VHA DIRECTIVE 7715 (06 April 2017) SAFETY & ENVIRONMENTAL RECORD AND
EXPERIENCE MODIFICATION RATE (EMR):
To be eligible for consideration and award, the contractor shall have no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years and have an EMR of equal to or less than 1.0.
All contractors shall submit the following information pertaining to their past Safety & Environmental Record and EMR with their quotation.
1. SAFETY & ENVIRONMENTAL RECORD: A self-certification on company letterhead that the contractor has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years.
2. EMR: All contractors shall submit information regarding their current EMR. This information shall be obtained from the contractor’s insurance carrier and be furnished on the insurance carrier’s letterhead. Must have an EMR of equal to or less than 1.0.
PRIVACY TRAINING:
All workers regardless of project length must take VA Privacy Training which will be coordinated after project award with the Contracting Officer’s Representative (COR).
TRAINING:
All employees of the general contractor and subcontractors shall have the 10-hour OSHA certified construction safety course and/or other relevant competency training, as determined by the COR with input from the ICRA (Infection Control Risk Assessment) team. The General Contractor’s Competent Person/Superintendent shall have completed the 30-hour OSHA certified construction safety course. Documentation of training shall be submitted to the Contracting Officer for review and approval prior to any work being performed. No ID badge will be issued to an employee who does not provide this documentation. There shall be no exceptions to this requirement.
PRIVACY AND CONFIDENTIALITY:
Contractors to the Department of Veteran Affairs may be unintentionally exposed to sensitive information.
Information may be overheard, seen on documents or electronic devices, or observed that could potentially violate the privacy and confidentiality of our veterans, employees, volunteers, and their families. Regulations such as, but not limited to the Health Insurance Portability and Accountability Act of 1996 (HIPAA), Freedom of Information Act (FOIA) and Privacy Act of 1974 have been enacted to protect sensitive information from being improperly disclosed.
Information should not be divulged or released to anyone unless specifically authorized by this contract or its’ attached documents in accordance with the contracted services. Failure to comply with applicable statutes and regulation can result in the termination of this contract and civil and criminal penalties, including fines and imprisonment. All suspected or actual breeches of privacy and confidentiality should be reported immediately to the Contracting Officer, Contracting Officer’s Representative (COR) or the Facility Privacy Officer.
The C&A requirements do not apply, and a Security Accreditation Package is not required. If the contractor opts to use a computer or computer system for processing contract documents, the requirements of FIPS 140-2 for encryption of contract documents must be met.
ADDITIONAL VETCERT INFORMATION:
1. Eligibility of SDVOSBs continues to be governed by the Small Business Administration regulations, 13 CFR subparts 125.8 through 125.13, as well as the FAR, except where expressly directed otherwise by the VAAR, and 38 CFR verification regulations for SDVOSBs.
2. At the time of submission of offer, the offeror must represent to the contracting officer that it is an:
a. SDVOSB concern
b. Small business concern under the North American Industry Classification System (NAICS) code assigned to the acquisition; and
c. Verified for eligibility in the VETCERT database.
3. A joint venture may be considered an SDVOSB or VOSB concern if:
a. At least one member of the joint venture is an SDVOSB or VOSB concern, and makes the representations in paragraph (b) of this section
b. Each other concern is small under the size standard corresponding to the NAICS code assigned to the procurement.
c. The joint venture meets the requirements of paragraph 7 of the size standard explanation of affiliates in FAR 19.101; and
d. The joint venture meets the requirements of 13 CFR 125.15(b), modified to include Veteran-owned small businesses where this CFR section refers to SDVOSB concerns.
4. Any SDVOSB or VOSB concern (nonmanufacturer) must meet the requirements in FAR 19.102(f) to receive a benefit under this program.
JOINT VENTURES:
See 13 C.F.R. § 121.103 Affiliation based on joint ventures: A joint venture is an association of individuals and/or concerns with interests in any degree or proportion consorting to engage in and carry out no more than three specific or limited-purpose business ventures for joint profit over a two year period, for which purpose they combine their efforts, property, money, skill, or knowledge, but not on a continuing or permanent basis for conducting business generally.
This means that a specific joint venture entity generally may not be awarded more than three contracts over a two-year period, starting from the date of the award of the first contract, without the partners to the joint venture being deemed affiliated for all purposes. Once a joint venture receives one contract, SBA will determine compliance with the three awards in two years rule for future awards as of the date of initial offer including price.
As such, an individual joint venture may be awarded more than three contracts without SBA finding general affiliation between the joint venture partners where the joint venture had received two or fewer contracts as of the date it submitted one or more additional offers which thereafter result in one or more additional contract awards. The same two (or more) entities may create additional joint ventures, and each new joint venture entity may be awarded up to three contracts in accordance with this section. At some point, however, such a longstanding inter-relationship or contractual dependence between the same joint venture partners will lead to a finding of general affiliation between and among them.
For purposes of this provision and in order to facilitate tracking of the number of contract awards made to a joint venture, a joint venture must be in writing and must do business under its own name, and it may (but need not) be in the form of a separate legal entity, and if it is a separate legal entity it may (but need not) be populated (i.e., have its own separate employees). SBA may also determine that the relationship between a prime contractor and its subcontractor is a joint venture, and that affiliation between the two exists, pursuant to paragraph (h)(4) of this section.
RESPONSIBILITY REQUIREMENTS:
A responsibility check will be accomplished for the apparent awardee prior to award. Checks of the VETCERT database (to insure apparently successful offeror is a verified Service-Disabled Veteran Owned Small Business), System for Award Management (SAM) database (Central Contractor Registration, Online Representations and Certifications, and Excluded Parties List System to ensure registrations are current, valid, and no debarment records exist). Any information retrieved or received by the Government that would be cause for negative or unsatisfactory responsibility rating may result in the offeror being determined ineligible for award.
CONFORMANCE WITH ENVIRONMENTAL MANAGEMENT SYSTEMS:
The Contractor shall perform work under this contract consistent with the relevant policy and objectives identified in the agency, organizational, or facility Green Environmental Management System (GEMS) applicable for your contract. The Contractor shall perform work in a manner that conforms to all appropriate Environmental Management Programs and Operational Controls identified by the agency, organizational, or facility GEMS, and provide monitoring and measurement information as necessary for the organization to address environmental performance relative to the environmental, energy, and transportation management goals. In the event an environmental nonconformance or noncompliance associated with the contracted services is identified, the contractor shall take corrective and/or preventative actions. In the case of a noncompliance, the Contractor shall respond and take corrective action immediately. In the case of a nonconformance, the Contractor shall respond and take corrective action based on the time schedule established by the facility GEMS Coordinator. In addition, the Contractor shall ensure that their employees are aware of the roles and responsibilities identified by the environmental management system and how these requirements affect their work performed under this contract.
All on-site contractor personnel shall complete yearly EPA sponsored environmental training specified for the type of work conducted on-site. Upon inclusion in the contract, the Contracting Officer’s Representative will verify that all contractor personnel have acquired EMS Awareness Training at their appropriate site or location.
SMOKE AND CARBON MONOXIDE MONITORING REQUIREMENTS:
Contractor, his employees, his subcontractors, and their employees shall adhere to VA, VHA, and VASNHCS Policies for smoke and carbon monoxide monitoring requirements. They are available upon request from COR.
2.1 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I
(FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for—
Wednesday, April 9th. 2025 at 9:00 AM PDT
(c) Participants will meet at—
(End of Provision)
PER VHA DIRECTIVE 7715 (06 April 2017) - SAFETY & ENVIRONMENTAL
RECORD AND EXPERIENCE MODIFICATION RATE (EMR):
Contractor Certification Regarding Project:
To be eligible for consideration and award, the contractor shall have no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years and have an EMR of equal to or less than 1.0.
All Offerors shall submit the following information pertaining to their past Safety & Environmental Record and EMR with their offer.
1. SAFETY & ENVIRONMENTAL RECORD: A self-certification on company letterhead that the contractor has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years.
2. EMR: All Offerors shall submit information regarding their current EMR. This information shall be obtained from the Offerors’s insurance carrier and be furnished on the insurance carrier’s letterhead. If an Offeror’s EMR is above 1.0, Offeror shall submit a written explanation of the EMR from its insurance carrier furnished on the insurance carrier’s letterhead, describing the reasons for the EMR, and the anticipated date the EMR may be reduced to 1.0 or below.
2022 2023 2024 Number of serious, willful, or repeat violations from OSHA within the last 3 years. Please attach explanation for any violations. (Four serious, one repeat, or one willful disqualifies the contractor.)
Number of violations from EPA within the last 3 years. Please attach explanation for any violations.
Company’s Current Insurance Experience Modification Rate (EMR) = (Note: Contractor must support the EMR with a signed letter from Insurance Carrier on their letterhead.)
Signature:
Print Name: ____________________________________________________
2.2 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON
SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND
CONSTRUCTION (JAN 2023) (DEVIATION)
(a) Pursuant to 38 U.S.C. 8127(l)(2), the offeror certifies that—
(1) If awarded a contract (see FAR 2.101 definition), it will comply with the limitations on subcontracting requirement as provided in the solicitation and the resultant contract, as follows:
(i) [] Services. In the case of a contract for services (except construction), the contractor will not pay more than 50% of the amount paid by the government to it to firms that are not certified SDVOSBs listed in the SBA certification database as set forth in 852.219–73 or certified VOSBs listed in the SBA certification database as set forth in 852.219–74. Any work that a similarly situated certified SDVOSB/VOSB subcontractor further subcontracts will count towards the 50% subcontract amount that cannot be exceeded. Other direct costs may be excluded to the extent they are not the principal purpose of the acquisition and small business concerns do not provide the service as set forth in 13 CFR 125.6.
(ii) [] General construction. In the case of a contract for general construction, the contractor will not pay more than 85% of the amount paid by the government to it to firms that are not certified SDVOSBs listed in the SBA certification database as set forth in 852.219–73 or certified VOSBs listed in the SBA certification database as set forth in 852.219–74. Any work that a similarly situated certified SDVOSB/VOSB subcontractor further subcontracts will count towards the 85% subcontract amount that cannot be exceeded. Cost of materials are excluded and not considered to be subcontracted.
(iii) [] Special trade construction contractors. In the case of a contract for special trade contractors, the contractor will not pay more than 75% of the amount paid by the government to it to firms that are not certified SDVOSBs listed in the SBA certification database as set forth in 852.219–73 or certified VOSBs listed in the SBA certification database as set forth in 852.219–
74. Any work that a similarly situated certified SDVOSB/VOSB subcontractor further subcontracts will count towards the 75% subcontract amount that cannot be exceeded. Cost of materials are excluded and not considered to be subcontracted.
(2) The offeror acknowledges that this certification concerns a matter within the jurisdiction of an Agency of the United States. The offeror further acknowledges that this certification is subject to Title 18, United States Code, Section 1001, and, as such, a false, fictitious, or fraudulent certification may render the offeror subject to criminal, civil, or administrative penalties, including prosecution.
(3) If VA determines that an SDVOSB/ VOSB awarded a contract pursuant to 38 U.S.C. 8127 did not act in good faith, such SDVOSB/VOSB shall be subject to any or all of the following:
(i) Referral to the VA Suspension and Debarment Committee;
(ii) A fine under section 16(g)(1) of the Small Business Act (15 U.S.C. 645(g)(1)); and
(iii) Prosecution for violating 18 U.S.C. 1001.
(b) The offeror represents and understands that by submission of its offer and award of a contract it may be required to provide copies of documents or records to VA that VA may review to determine whether the offeror complied with the limitations on subcontracting requirement specified in the contract. Contracting officers may, at their discretion, require the contractor to demonstrate its compliance with the limitations on subcontracting at any time during performance and upon completion of a contract if the information regarding such compliance is not already available to the contracting officer. Evidence of compliance includes, but is not limited to, invoices, copies of subcontracts, or a list of the value of tasks performed.
(c) The offeror further agrees to cooperate fully and make available any documents or records as may be required to enable VA to determine compliance with the limitations on subcontracting requirement. The offeror understands that failure to provide documents as requested by VA may result in remedial action as the Government deems appropriate.
(d) Offeror completed certification/fill-in required. The formal certification must be completed, signed and returned with the offeror’s bid, quotation, or proposal. The Government will not consider offers for award from offerors that do not provide the certification, and all such responses will be deemed ineligible for evaluation and award.
Certification
I hereby certify that if awarded the contract, [insert name of offeror] will comply with the limitations on subcontracting specified in this clause and in the resultant contract. I further certify that I am authorized to execute this certification on behalf of [insert name of offeror].
Printed Name of Signee: ___________
Printed Title of Signee: _____________
Signature: ____________
Date: ______________
Company Name and Address: _______________
(End of Clause)
2.3 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID
GUARANTEE) (FEB 2021)
(a) Offerors shall obtain from each person acting as an individual surety on a bid guarantee—
(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203–1; and
(2) Standard Form 28, Affidavit of Individual Surety.
(b) The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228–1, Bid Guarantee, or as otherwise established by the Contracting Officer.
(c) The Contracting Officer may release the security interest on the individual surety’s assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.
(End of Provision)
ATTACHMENT
See attached document: Wage Determination Davis-Bacon Act WD CA20250019 02.
File details come from the government source that posted it. Updated .